Loras Blvd. Traffic Signalization Project_Hearing i5~~~E ~Yk-~ MEMORANDUM August 26, 2006 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Loras Boulevard Traffic Signalization Replacement Project (CIP 1011133 - Traffic Signal Mastarm Retrofit) Sealed bids were received for the Loras Boulevard Traffic Signalization Replacement Project. City Engineer Gus Psihoyos recommends award of the contract to the low bidder, Portzen Construction, Inc., in the amount of $282,680.25, which is 1.05% under the estimate of probable cost. I concur with the recommendation and respectfully request Mayor and City Council approval. (1)1j ~ ptL Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer .,.J 5~~%duE ~<k~ MEMORANDUM August 25, 2006 FROM: Michael C. Van Milligen, City Manager Gus Psi hoyos, City Engineer _ 90 TO: SUBJECT: Loras Boulevard Traffic Signalization Replacement Project (CIP 1011133 - Traffic Signal Mastarm Retrofit) INTRODUCTION The enclosed resolutions authorize the award of the construction contract for the Loras Boulevard Traffic Signalization Replacement Project. BACKGROUND This project provides for the standardization of mastarm-mounted signals along the Loras corridor: Bluff and 14th Streets, Locust and 14th Streets, Main and 14th Streets, and Iowa and 14th Streets. The project will also include pre-emption capabilities and battery backup systems. The project has been expanded from its original scope to include sidewalk ramp improvements, a fiber optic conduit inner-connect between the signals and some additional roadway pavement improvements near the intersections. New traffic controller equipment and mast-arms have already been purchased for the project to eliminate the long lead time in ordering. BID RESULTS Sealed bids were received on the project on August 24, 2006. Portzen Construction, Inc. of Dubuque, Iowa, submitted the low bid in the amount of $282,680.25. This amount is 1.05% under the estimate of probable cost. A summary of the bid proposals received is as follows: Contractor Name Total Bid Portzen Construction, Inc Tschiggfrie Excavating, Inc $282,680.25 $335,659.60 RECOMMENDATION I recommend that the contract be awarded to Portzen Construction, Inc. in the amount of $282,680.25. PROJECT COST - BUDGET IMPACT The estimate of probable costs for the Loras Boulevard Traffic Signalization Replacement Project is summarized as follows: Cost Estimate Bid Award Total Project Cost $285,700.00 $28,570.00 $47,140.50 $361,410.50 $282,680.25 $28,268.03 $46,642.24 $357.590.52 Construction Contract Contingency Construction Engineering & Inspection The project funding summary is as follows: CIP 1001133 2501615 3001266 1021608 3001041 3501425 Fund Description Fund Amount Traffic Signal Mastarm Retrofit Traffic Signal Intersection Reconstruction Traffic Signal Interconnect Conduit Replacement Downtown Streetlight Replacement Schedule Curb/Catch Basin Replacement City of Dubuque Sidewalk Program $236,119.27 $46,625.00 $45,935.00 $12,150.00 $10,056.75 $ 6,704.50 Total Project Funding $357.590.52 ACTION TO BE TAKEN I recommend that the City Council adopt the attached resolutions awarding the Loras Boulevard Traffic Signalization Replacement Project to Portzen Construction, Inc. in the amount of $282,680.25. Prepared by David Ness, PE cc: Dawn Lang, Budget Director Bob Schiesl, PE, Assistant City Engineer Chris Kohlmann, Information Services Laura Carstens, City Planner Dave Johnson, Assistant Planner David Ness, PE .. RESOLUTION NO. 428-06 RESOLUTION ADOPTING PLANS AND SPECIFICATIONS Whereas, on the 2nd day of August, 2006, plans, specifications, form of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa, for the Loras Boulevard Traffic Signalization Replacement Project. Whereas, notice of hearing on plans, specifications, form of contract, and estimated cost was published as required by law. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the said plans, specifications, form of contract and estimated cost are hereby approved as the plans, specifications, form of contract and estimated cost for said improvements for said project. Passed, adopted and approved this 5th day of September, 2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk .. RESOLUTION NO. 429-06 AWARDING CONSTRUCTION CONTRACT FOR THE LORAS BOULEVARD TRAFFIC SIGNALIZATION REPLACEMENT PROJECT Whereas, sealed proposals have been submitted by contractors for the Loras Boulevard Traffic Signalization Replacement Project pursuant to Resolution No. and notice to bidders published in a newspaper published in the City of Dubuque, Iowa on the 11th day of August, 2006. Whereas, said sealed proposals were opened and read on the 24th day of August, 2006, and it has been determined that the bid of Portzen Construction, Inc. of Dubuque, Iowa, in the amount of $282,680.25 was the lowest bid for the furnishings of all labor and materials and performing the work as provided for in the plans and specifications. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That the contract for the above improvement be awarded to Portzen Construction, Inc. and the Manager be and is hereby directed to execute a contract on behalf of the City of Dubuque for the complete performance of the work. BE IT FURTHER RESOLVED: That upon the signing of said contract and the approval of the contractor's bond, the City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful bidders. Passed, approved and adopted this 5th day of September, 2006. Roy D. Buol, Mayor Attest Jeanne F. Schneider, CMC, City Clerk RESOLUTION NO. 430-06 APPROVING CONSTRUCTION CONTRACT WITH PORTZEN CONSTRUCTION, INC. FOR THE LORAS BOULEVARD TRAFFIC SIGNALIZATION REPLACEMENT PROJECT Whereas the City Council by Resolution NO.429-06 awarded the construction contract for the Loras Boulevard Traffic Signalization Replacement Project to Portzen Construction, Inc.; and Whereas Portzen Construction, Inc. has submitted the attached executed contract and bond. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: 1. The contract and bond attached hereto are hereby approved. 2. The City Manager is hereby authorized and directed to execute the contract on behalf of the City of Dubuque. Passed, approved and adopted this 5th day of September, 2006. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk " w w . o 2 o " :l o . ~ o . 2 o . " a " 2 . W W 2 a 2 W W o o o . o o " o ~ o . ~ i ~ i . , i ~ ] J ffi o o . ~ , ~ w ~ ~ o rn ~ ~I- ~I ,! "' I. > , .. ...! h ~ , '::,E . . ~ ~ ~ ~ 0" il'~ "0 " ~ z o z ~ ! o rn ~~...,'.~I Z o ~ " ~ o > ~ o rn L o o u ~ g 8 00000 000"10 ~8~~8 ..: oj,.;~- ",' "~' ~&1~~ :::,:=-",-;;; Hi Iccl r7l~~: ~~~ ~~>- CZ UW "."~' .".. * "'-"'-:i 1!~l~ 2sSi ~g~: ~lli~ ~a-- CZ UW 888'g8:7l8g ~~~~~~~~ <;i ,.... ",.:::! ",-~- 8 8 8 gl81 o. _c.~' ~~888 ~~;;~ ..:rl :::: 888~ l;J5::gt;i ""D"''' N~~::! "'0150 ;:::~,,~ "'N~'" N 8888 UH r ~ ~ ~f ~ g 818, ".g~ ,. ..+ 8888 00"'8 ;8~o "':~<;i;;i (j+I+1 , +121.1 I I , ~ ~, W~ W I~ ~,~ -Ii ii~1 ; "ill' ~ ai j ri ~....mmo Ili&~~~ ~~~~~ /."'<D.....'" :'''''''~ ~ ~ ~ g8g81l1:e8g "'~o.o2";8:!l s_ "'_ 21';: m ~ "_"- ~~""N~"'-N . N ., ~ 00 o u ~ Z o Rfi5~8lQg8:ll c;;;:I;....~.,;,.;g.... <000"10 i'l~~~~ ...- ",-~" , ....................... ~ 00 o u ~ g 8,8jg8ll,l,g8g ~~2~~$~~ ~ ~- '<t-,.; ~ ",-,.; ..1...... g 8 8 gl"lglgl~'I' 81'881881 . . . ~". 0 M . e ~IU ... .[.i.i.[. ..:: = o . 88888 Un. II . ..................... 88 Ii: 8 g ~ sj;? :::~~~:[ ~I +I~I~I+I+I .1+1+1 ~ ~~~~~~~~ I~~~~~ I I 88888 .. ~ U "i"," ~" ! ~ . ~] ~.,. ., , . .! o u I.' jl :J Itll ~)I~~~ i ~~~~~,,<l! {5j~iii~~i ~8~888~~~ ~;r<l!;r;r~U'l~~ "''''...'''''',....,''' I ! ~,_'I i :01 :. , Illll j O~N ... ..~~'!! ~~o! ~>-0~ <Il~~:' ~lli~ ~~-- o z UW m~ ~"',...~ ~HI ! ~~ i !liDo::,!'! 'R(')lli~ o~~ll j~~~ ..uw 88"~ g ~q:~ a; "'...,...... ~"::' '" g IH!" ~tl~- ::i3S" ~ 'R(')lli::E o~~~ ~8~1- o. .~., 01-- <0 ~~~~ ~"........,. u; 888 ~o~ " nq Jltl~- !liD"] 'Rt'llli~ o~~g .!~~I- u:uUJ ~:g~~'8g88 \H?~~~~~~ vi -:;" ':if' ':ii".... N~"~" 0",,00g08':if ~."'~~,.;:;::",~ ~....!;j\;;mfil"'''' ~! -:; ':if ':if 88888888 UUU~~ ~ 1l:l"1',l" r;.;" 'ii ....'t-~" 81818188 g g 8 U~88~~" /!.f1l:l1',l r;.; ~ ~ .;.1.1.... . " . .~o ~~~~ ~"~" ~"* ............ , ii'j" ~~~ .-- orO <Il~~] I~lli2; ~~~~ lj!1SiDl- "u ~,.. ~"~ ~*~ ~~ :{g~ ~ i!!i"i" ..0 ~ ~;; wuz ~~~ o Z z t~~ !!luw o f ~ 0; > , mt ~ . " g ~ 00 Z o u " ~ .~--~ 8.0~" ~,Z" ~'~ "U~ H~ ~c ~"l'l"~"~ ~;i~ ~" ........... '-'i":i~ ~ ~ ~ ~ ~:=t; .!!! <Il~~] ~~ffi:i t~~g iBiD>- "0 ~ 0; > ~ ;::0; ::q ~ , c u , ~ o o " 8'888 g -g~, 8, ~~~ ~"~-~: ~8g8~~@~ ~~~~ ~~~ ~ ~~~~";M~~ ~~~g ~;i~ ~ .................... .......... ... 88888g88 IfUUUCC -,:;;:-:;"':ii":;;:" I.'j..................... :;, +1+1+1+1 +1+1+1+1 ~ i j il ""_c ~ =!:~i ~ '" _ .'I' .'l1 _ '5 W " 0 0 ~ - w :I: :I: ~~~~~~ ~ .. '" h r r 1il~~~~~ i!.3.'I · -::< , , ~ '""a;-li " :~~j~~~~] ; 'u, u, u, "'I':: ~:o:::o:: -,jUHH!:><jl~~ ,..~~~~~;;:"" ;"l'l;;;~~~~~ IH! :;I >- (')_ ~~~~ ",t'llli::< ~~~! <OZ ~ow ~ii ." 0 ~~; i:lg~ ln~lli o~z t~~ wuW a ~ ~:ii ." 0 ~~;; ouz ~~~ o~z t~~ llioLlJ o " . w i m Z o c u , ~ ~ o u " ~ g 4 D~~~E ~ck~ MEMORANDUM August 1, 2006 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Loras Boulevard Traffic Signalization Replacement Project (CIP 1011133 - Traffic Signal Mastarm Retrofit) City Engineer Gus Psihoyos recommends initiation of the bidding process for the Loras Boulevard Traffic Signalization Replacement Project, and further recommends that a public hearing be set for September 5, 2006. I concur with the recommendation and respectfully request Mayor and City Council approval. /t/{ ~ 1'11/J Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Gus Psi hoyos, City Engineer