MEMORANDUM
October 30,2006
TO:
The Honorable Mayor and City Council Members
FROM:
Michael C. Van Milligen, City Manager
SUBJECT: Villa Street Retaining Wall - Ornamental Railing Project
CIP No. 3501432 - Steps, Railing, and Fence
Sealed bids were received for the Villa Street Retaining Wall - Ornamental Railing
Project. City Engineer Gus Psihoyos recommends award of the contract to the low
bidder, Becker & Sons Stone Co., Inc., in the amount of $104,755.40, which is 12.7%
below the estimate of probable cost.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
flc4 4~;1tJL-
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psi hoyos, City Engineer
D~~~E
~~~
MEMORANDUM
October 30, 2006
FROM:
Michael C. Van Milligen, City Managey;
Gus Psihoyos, City Engineer 9:f~~
TO:
SUBJECT: Villa Street Retaining Wall - Ornamental Railing Project
CIP No.: 3501432 - Steps, Railing, and Fence
INTRODUCTION
The enclosed resolutions authorize the award of the construction contract for the Villa
Street Retaining Wall - Ornamental Railing Project.
DISCUSSION
The Villa Street Retaining Wall - Ornamental Railing Project shall provide for the
removal of all remaining piers and cable guardrail and will reconstruct and replicate the
limestone pier caps along with the installation of ornamental hoop wall top railing, from
approximately 110 feet south of Rush Street to Cleveland Park.
BID RESULTS
Sealed bids were received on the project on October 26, 2006. Becker & Sons Stone
Co., Inc. of Dubuque, Iowa, submitted the low bid in the amount of $104,755.40. This
amount is 12.7% below the estimate of probable cost. A summary of the bid proposals
received is as follows:
Contractor Name
Total Bid
Becker & Sons Stone Co.
Becker & Becker Stone Co.
Tricon Construction
Klauer Development
$104,755.40
$120,299.15
$123,124.90
$141,026.00
RECOMMENDATION
I recommend that the contract be awarded to Becker & Sons Stone Co., Inc. in the
amount of $104,755.40.
PROJECT COST-BUDGET IMPACT
The estimate of probable costs for the Villa Street Retaining Wall - Ornamental Railing
Project is summarized as follows:
Construction Contract
Contingency
Construction Engineering & Inspection
Bid Estimate
$ 120,000.00
12,000.00
13,200.00
~ 145,200.00
Award
$104,755.40
12,000.00
13,200.00
~129,955.40
The project funding summary is as follows:
CIP No. Fund Description
3501432 Steps, Railing and Fencing
Total Project Funding
Fund Amount
$129,955.40
$129,955.40
ACTION TO BE TAKEN
I recommend that the City Council adopt the attached resolutions awarding the Villa
Street Retaining Wall - Ornamental Railing Project to Becker & Sons Stone Co., Inc. in
the amount of $104,755.40.
Prepared by Robert D. Schiesl, Assistant City Engineer
cc: Dawn Lang, Budget Director
Laura Carstens, Planning Services Manager
Don Vogt, Public Works Director
John Klostermann, Public Works
Development
BIDDER: Klaue
I UNIT COST I
TOTAL COST
$6147,90
$11,44000
$7875,00
$808.00
$608.00
$2020.00
$18,518.35
$30318.75
$60,774.00
$880.00
$220.00
$1~416,00
1 $141,026.001
17,5%
BASE BID:
BIDDER: Tocon Construction
I UNIT COST I
$6147.90
$52.00
$375.00
$808.00
$60800
$2,02000
$50,50
$91875
$88,82
$2,00
SO,50
$141600
TOTAL COST
$10000,00
$1540.00
$2310.00
$220.00
$220.00
$3080.00
$17,234.90
$33000.00
$51,800.00
$1100.00
$220.00
$2,400.00
I $123,124.901
2,6%
BASEBIO:
BlDDER:Becker&BeckerStoneCo
$1000000
$7,00
$110.00
$220,00
$22000
$3080,00
$4700
$1000,00
$74,00
~
~
12,40000
TOTAL COST
$1800,00
$583000
$4515,00
$500,00
$750,00
$750,00
$22918,75
$3257100
$49500,00
$550.00
$114,40
1500.00
1 $120.299.151
6"
BASEBIO:
BIDDER: Becker" Sons Stone Co
I UNIT COST I
$1800.00
$26.50
$215.00
$500.00
$750.00
$750,00
$62,50
$987,00
$70,71
~
$0:16
~500,00
I $10.4,755.401
.12.7%
BASEBIO:
CITY OF DUBUQUE" ENGINEERING DIVISION. BID TABULATION SHEET
October 26, 2006
BID DATE
BID TABULATION FOR VILLA STREET RETAINING WALL
ORNAMENTAL RAILING PROJECT
TOTAL COST
$200,00
$1320,00
$2100,00
$100,00
$5000
$100,00
$1540140
$36300,00
$48006.00
$880,00
$198.00
$100,00
I UNIT COST I
$200,00
$600
$10000
$100,00
$50,00
$100,00
$4200
$1100,00
$6656
$2,00
$0,45
$100.00
ESTIMATE
COST
ESTIMATE
UNIT COST
ESTIMATE
QUANTITY
~
220,0
2UL
~
~
...1.Q.....
3667
~
700,0
440.0
440,0
'0
[::J
--'L
~
EACH
--'L
--'L
--'L
~
EACH
~
~
~
--'L
BID ITEM DESCRIPTION
BASE BID
Mobilization
Excavetlon Wall Stone I Concrete Removal
Remove & Dispose Existing Limestone Piers
Remove & Dispose Existina Cable Guardrail
Remove & Dispose Existing Fence & Posts
Temporary FenCina
Retaining Wall Limestone - Complete
Limestone Piers Construct New - Comolete
Standard Ornamentai Hoop Railing, 42" Heigh
TOPSOil 12" Backfill. Complete
Seed. Fertilize & Mulct1
TraffiC & Safety Control
,
2
3
4
5
6
7
8
9
"
"
"
I $120,000.001
.j
EST. BASE BlO
BASE 810 (%) OVER' UNDER (
.
RESOLUTION NO. 537-06
RESOLUTION ADOPTING PLANS AND SPECIFICATIONS
Whereas, on the 27th day of September, 2006, plans, specifications, form
of contract and estimated cost were filed with the City Clerk of Dubuque, Iowa for
the Villa Street Retaining Wall - Ornamental Railing Project.
Whereas, notice of hearing on plans, specifications, form of contract, and
estimated cost was published as required by law.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
That the said plans, specifications, form of contract and estimated cost are
hereby approved as the plans, specifications, form of contract and estimated cost
for said improvements for said project.
Passed, adopted and approved this 6th day of November, 2006.
Roy D. Buol, Mayor.
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO. 538-06
AWARDING CONSTRUCTION CONTRACT FOR THE VILLA STREET
RETAINING WALL - ORNAMENTAL RAILING PROJECT
Whereas, sealed proposals have been submitted by contractors for the
Villa Street Retaining Wall - Ornamental Railing Project pursuant to Resolution
No. and notice to bidders published in a newspaper published in the City
of Dubuque, Iowa on the 6th day of October, 2006.
Whereas, said sealed proposals were opened and read on the 26th day of
October, 2006, and it has been determined that the bid of Becker & Sons Stone
Co., Inc. of Dubuque, Iowa, in the amount of $104,755.40 was the lowest bid for
the furnishings of all labor and materials and performing the work as provided for
in the plans and specifications.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
That the contract for the above improvement be awarded to Becker &
Sons Stone Co., Inc. and the Manager be and is hereby directed to execute a
contract on behalf of the City of Dubuque for the complete performance of the
work.
BE IT FURTHER RESOLVED:
That upon the signing of said contract and the approval of the contractor's
bond, the City Treasurer is authorized and instructed to return the bid deposits of
the unsuccessful bidders.
Passed, approved and adopted this 6th day of November, 2006.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO. 539-06
APPROVING CONSTRUCTION CONTRACT WITH BECKER & SONS
STONE CO., INC. FOR THE VILLA STREET RETAINING WALL.
ORNAMENTAL RAILING PROJECT
Whereas the City Council by Resolution No.538-06 awarded the
construction contract for the Villa Street Retaining Wall - Ornamental
Railing Project to Becker & Sons Stone Co., Inc.; and
Whereas Becker & Sons Stone Co., Inc. has submitted the attached
executed contract and bond.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF DUBUQUE, IOWA:
1. The contract and bond attached hereto are hereby approved.
2. The City Manager is hereby authorized and directed to execute the
contract on behalf of the City of Dubuque.
Passed, approved and adopted this 6th day of November, 2006.