Bee Branch Watershed Application, State Flood Mitigation Board GrantMasterpiece on the Mississippi Dubuque kard All- America City 1111 2007 • 2012 • 2013 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Bee Branch Watershed Flood Mitigation Project — Grant Application DATE: November 18, 2013 Civil Engineer Deron Muehring is recommending approval to submit an application to the State of Iowa Flood Mitigation Program Board for $98,494,178 in state sales tax increment funding for the Bee Branch Watershed Flood Mitigation Project, as follows: 1. Approval of the application in its entirety, which includes but is not limited to, the Project Plan that describes the 12 phases and their projected schedule, and the proposed issuance of debt to support the Plan. 2. Approval of the City's authorized representatives for the grant. 3. Approval of the local match funding, which comes from 3 main sources. These are the Stormwater Utility Fee, grants that the City already has acquired, and assessments on pervious alleys. The State of Iowa Flood Mitigation Program was created in 2012 establishing a Flood Mitigation Sales Tax Increment Fund. The Sales Tax Increment Fund is to consist of the increase in the state share of the sales tax revenues from communities with qualifying applications. The maximum state share of sales tax increment that can be diverted from the state and used instead for flood mitigation projects is $30 million a year for 20 years for a total of $600 million. The maximum award for any qualifying single community is $15 million per year. To qualify for sales tax increment funding, federal financial assistance must have been secured for the project. A local match is also required and the state sales tax increment cannot exceed 50% of the total project cost. In April of 2013 the State Flood Mitigation Program Board was established. The Board will begin considering applications for funding on November 21, 2013. Six Presidential Disasters have been issued between 1999 and 2011 due to flash flooding as a result of localized, intense rainstorms in the Dubuque area. Flash flooding occurs with little or no warning time, with water levels rising and flowing at extremely fast rates. The Bee Branch Watershed, which covers approximately 6.5 square miles within the most developed part of the City and where over 50% of Dubuque residents either live or work, is continually hit the hardest with flash flooding. It should be noted that the flash flooding experienced in the Bee Branch Watershed is not just a little water in the basement. Residents have reported and documented flooding that reached the rafters, flooding that inundated water heaters, furnaces, and electrical boxes, and flooding that caused fires in the home. And the flooding is not limited to basements. It is stormwater rushing down streets from curb to curb, stalling vehicles, stranding motorists, and even floating cars. The flash flooding also damages public and private infrastructure, resulting in the disruption of commerce and expensive repairs, on a repeated basis. While many Dubuque residents and businesses are forced to deal with occasional flooding, the flash flooding experienced within the Bee Branch Watershed has repeatedly posed a clear danger to the lives and livelihood of citizens. The May 1999 storm was one of the most destructive flash floods in the City's history, with $16 million in property damage. The City Council took action and commissioned an engineering study to look into the nature of the flooding and identify solutions to mitigate or eliminate the flash flooding experienced in the Bee Branch Watershed. The Drainage Basin Master Plan was completed in 2001. A study in 2009 by the Federal Emergency Management Agency identified a flood prone area with 1,373 properties. In addition to homes, there are over 70 businesses in the at -risk area with over $500 million in annual sales. Eighty -five percent of the impacted properties have buildings that are potentially eligible for listing on the National Register of Historic Places. In fact, 57% of the buildings are more than 100 years old. The flood prone area in the Bee Branch Watershed encompasses historic neighborhoods offering some of the community's most affordable workforce housing. Most residents are working families, many are elderly -- those least likely to recover from repetitive flood loss. Repetitive flood damage leads to disinvestment; from 2004 to 2009, while commercial property values grew by 39% citywide, they fell by 6% in the Bee Branch Watershed flood prone area. The Drainage Basin Master Plan also outlined several improvements throughout the watershed to mitigate future flooding and disasters. Collectively, the improvements form the basis of the Bee Branch Watershed Flood Mitigation Project. Having identified the flooding issue as a top priority, the Dubuque City Council adopted the Drainage Basin Master Plan and established funding, including a stormwater management utility fee, to construct this important public infrastructure project, the Bee Branch Watershed Flood Mitigation Project. The City of Dubuque established the Bee Branch Citizen Advisory Committee in 2003 to solicit public input to assure that in addition to flooding, the project addresses the issues and concerns of residents and businesses most directly impacted by the flooding. The Committee formally met 6 times between 2003 and 2004, developing recommendations that were then presented to the City Council. Additional citizen input was obtained through a series of 9 public workshops. Notices were provided by direct mail to over 2,000 households in the areas most directly impacted. In addition, press releases were issued to notify all residents of the workshops. The recommendations center around the "day- lighting" of the buried Bee Branch Creek thereby creating an attraction, enhancing the neighborhoods, preventing flooding and improving the quality of life of Bee Branch Watershed residents. Citizens also recommended improvements such as pervious 2 pavement systems to address the flooding. To the extent feasible, their preferences have been implemented in the project design. The Bee Branch Watershed Flood Mitigation Project is a multi - phased, fiscally responsible investment. It reflects a holistic approach to mitigate flooding as it will also improve water quality, stimulate investment, and enhance the quality of life. Having secured the necessary federal and state funding approvals, permits, and funding, Dubuque has pushed forward with planning, execution, and completion of three phases and the initiation of two more. The 12 phases of the Flood Mitigation Project are: Bee Branch Watershed Flood Mitigation Project Phases Phase Description Est. Completion Est. Cost 1 Carter Road Detention Basin 2 West 32nd Street Detention Basin 3 Historic Millwork District 4 Lower Bee Branch Creek Restoration 5 Flood Mitigation Gate Replacement 6 Impervious Surface Reduction 7 Upper Bee Branch Creek Restoration 8 22nd Street Storm Sewer Improvements 9 Flood Mitigation Maintenance Facility 10 North End Storm Sewer Improvements 11 Water Plant Flood Protection 12 17th Street Storm Sewer Improvements Completed 2004 Completed 2009 Completed 2012 2014 2015 2034 2016 2020 2020 2019 2020 2020 $1,076,315 $4,158,589 $7,977,311 $21,274,685 $2,099,000 $57,420,000 $64,823,636 $3,380,000 $4,360,000 $1,160,000 $3,800,000 $7,520,000 Individually, the 12 phases of the project will provide some benefit. But flash flooding can be expected to occur until all of the improvements are implemented. But it is also true that with the completion of each subsequent phase, the threat of flash flood damage is lessened and the resulting damage will be mitigated. The combined phases of the project will reduce the volume of floodwaters, slow the rate the floodwaters flow through the upper watershed, increase the safe conveyance of floodwaters through the flood -prone area, and provide physical barriers to prevent floodwaters from inundating the City's only potable water source. The City has already taken steps to reduce the volume of floodwaters by beginning the process of converting pervious alleys and street systems into pervious pavement systems to convey floodwaters into the ground. Eight alleys have already been converted and an additional 73 currently under design will be converted in the next 3 years utilizing financial assistance through the Clean Water Act. In addition, streets in the flood -prone Historic Millwork District were also redone with pervious pavement systems. The City has also taken action in order to reduce the rate that floodwaters flow from upstream areas down into the flood -prone area by constructing a new detention basin and modifying another upstream of the flood -prone area. A total of 20 properties were acquired to allow for the construction of the Carter Road Detention Basin and expansion 3 of the 32nd Street Detention Basin. The City expended over $5.2 million for acquisition, engineering design, and construction of these basins. Embracing the idea of day - lighting the buried Bee Branch Creek, the City has undertaken a substantial effort to increase the safe conveyance of floodwaters through the flood -prone area in a manner that will not negatively impact downstream properties. The City acquired and deconstructed over 100 properties to clear the path for the Bee Branch Creek Restoration. The City hired an engineering consulting team to design the creek restoration project. The City hired a construction contractor to begin construction of the Lower Bee Branch Creek Restoration.The City anticipates soliciting bids to construct portions of the Upper Bee Branch Creek Restoration in early 2014. In total, the City has already spent more than $20 million towards the Bee Branch Creek Restoration. While the City took steps to complete the first 2 phases of the Project and start 2 more, flash flooding and disasters have repeatedly occurred in 2002, 2004, 2008, 2010, and most recently in 2011. With each disaster, especially the latest where 10 inches of rain fell in 12 hours, the need to implement the components of the Bee Branch Watershed Flood Mitigation Project is ever present. The 2010 State of Iowa Hazard Mitigation Plan estimates that Dubuque County has an annual loss of $10,556,235 due to flooding. I would like to quote portions of an August 29, 2010 article written by Orlan Love that appeared in the Cedar Rapids Gazette titled, "Data Suggests Iowa Really is Getting Wetter." "The past three years have been the wettest 36 month period in the 138 years that Iowa has been keeping records, said State Climatologist Harry Hillaker. From August 2007 through July 2010, Iowa recorded a statewide average of 134.72 inches of precipitation, beating the old record of 124.8 inches established from October 1990 through September 1993, Hillaker said. In 2007, Iowa recorded 43.85 inches, making it the state's fifth- wettest year; 2008, with 43.79 inches, was the fourth wettest; 2009, with 40.05 inches, was the 11th wettest; and this year, with 34.66 inches through August 18, is on track to become the second - wettest year, Hillaker said. To put those 40- inches plus years in context, consider that Iowa has had just 11 of them in 138 years and that the long term statewide average over the past 138 years has been 32.44 inches. From 1875 to 1950, Iowa recorded only two years with more than 40 inches of precipitation. Since 1950, the state has recorded eight such years, and this year likely will be the ninth, Takle said." (Iowa State University Eugene Tackle, one of the State's leading Climate Scientists) 4 "And when it rains, it pours. Since 1910, days with more than 4 inches of precipitation have increased 50 percent in the Upper Midwest, said Christopher Anderson, assistant director of Iowa State University's Climate Science Initiative. During the late 1800s, Cedar Rapids averaged 4.2 days a year with precipitation of 1.25 inches or more — the amount at which runoff to streams typically becomes significant. By 2008, that figure had risen to 6.6 days per year, a 57 percent increase, Anderson said. Expressing that same trend another way, Anderson said that between 1895 and 1947, Cedar Rapids had two years in which 1.25 inches or more of precipitation fell on nine or more days. Since 1947, Cedar Rapids has recorded 11 such years, he said. Comprehensive, integrated watershed and flood plain management should be the state's top priority in reducing future risks, said Lt. Gen. Ron Dardis, director of the Rebuild Iowa Office, a temporary state agency created after the floods and tornadoes of 2008. The state has already expended more than $500 million in efforts to recover from 2008 floods, which caused an estimated $8 billion to $10 billion in damages, Dardis said. 'Can we afford to pay for disasters of this magnitude on a recurring basis ?' he asked." The City of Dubuque has completed an application seeking $98,494,178 in state sales tax increment funding for the Bee Branch Watershed Flood Mitigation Project. The multi - phased Bee Branch Watershed Flood Mitigation Project maximizes the use of multiple funding sources. The City of Dubuque has applied for and been awarded financial assistance from eight agencies from both the State of Iowa and Federal government. The City of Dubuque has issued General Obligation (GO) Bonds, plans to issue additional bonds, and has allocated funds from the local Stormwater Utility to help fund this project. The local financial assistance received by the City from private donations also shows the continued support from the community for this project. The City of Dubuque has contracted with several consulting and engineering firms to provide estimated costs for the Bee Branch Watershed Flood Mitigation Project. The estimates were also reviewed by the City's engineers and compared with other projects the City has completed to make sure the cost estimates were an accurate depiction of the project. 5 Financing for the project was reviewed by the City's financial advisor, Piper Jaffray, so that the City of Dubuque could provide the most accurate financing costs for the project; however, until the bonds are sold, financing fees and interest rates may fluctuate. The City has also selected an underwriter, R.W. Baird. The selected underwriter will be providing suggestions with respect to structure, timing and marketing of the bonds being sold in order to sell the bonds with the best possible structure and at the lowest interest cost. City Attorney Barry Lindahl and the City's bond counsel, Ahlers and Cooney, has reviewed the Flood Mitigation statute in regard to what is allowed to be pledged for sales tax increment debt and are of the opinion that the City's financing plan is in compliance with that statute. Because of the public support for the Bee Branch Watershed Flood Mitigation Project, the stated commitment of the City of Dubuque City Council to implement the various phases of the project, and because the City has already started implementing some of the improvements, non - public investment in the Bee Branch Watershed has already eclipsed $139 million since 2008 with an additional $215 million expected to follow in the next five years for a combined total of $354 million in non - public investment. With the exception of the planned improvements to protect the Water Plant, which is outside the Bee Branch Watershed, from flooding that would result from a breach or overtopping of the Mississippi River levee, implementation of all the improvements associated with the Bee Branch Watershed Flood Mitigation Project are necessary to mitigate the flash flooding predicted and witnessed in the Bee Branch Watershed. There is no question that the existence of the Carter Road Detention Basin that has been functional since 2003 mitigated to some extent the flooding that occurred in 2004, 2006, 2008, 2010, and 2011. And yet, the damage that resulted from these rainstorms and ensuing flash flooding still proved beyond the resources of the City and State of Iowa, prompting Presidential Disaster Declarations. But it is also true that with the completion of each subsequent phase, the threat of flash flood damage is lessened and the resulting damage will be mitigated. In order to provide the required local match for the Bee Branch Watershed Mitigation Project and construct the improvements according to the schedule outlined herein, the City will need to adjust the stormwater utility rates accordingly. However, the increases will be more gradual and peak at $9.00 on July 1, 2021, versus the rate schedule adopted previously with the Fiscal Year 2013 Budget, which outlined that the rate would peak at $9.00 on July 1, 2016. As currently exists, properties that are exempt from property taxes (non- profits) only pay 50% of the storm water fee, as do low- income individuals. Farms receive a 75% discount. The Fiscal Year 2014 City budget includes $237,440 from the General Fund to cover these discounts. The grant would also mean that improvements could be completed over the next 20 years (mostly in the next 6 years) instead of completing them over 50 years in the former plan. 6 The Bee Branch Watershed Flood Mitigation Project will prevent an estimated $582 million in damages over the 100 -year design life of the project, with a return on investment of roughly $3 for each $1 spent. Should the City receive this State grant, the flood protection will be provided sooner, over the next 20 years -front loaded in the next 6 years, instead of over the next 50 years, and the impact on the Dubuque citizens and businesses will be less, with the monthly Stormwater Utility Fee rising to $9.00 per month on July 1, 2021, instead of July 1,2016. I concur with the recommendation and respectfully request Mayor and City Council approval. itivivi kri:.,74,,,, Michael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Jenny Larson, Budget Director Ken TeKippe, Finance Director Gus Psihoyos, City Engineer Laura Carstens, Planning Services Manager Don Vogt, Public Works Director Bob Green, Water Department Manager Deron Muehring, Civil Engineer 7 Masterpiece on the Mississippi TO: FROM: Deron Muehring, Civil Engineer SUBJECT: DATE: November 15, 2013 Dubuque kard All- America City 1111 2007 • 2012 • 2013 Michael C. Van Milligen, City Manaaer Bee Branch Watershed Flood Mitigation Project — Grant Application INTRODUCTION The purpose of this memo is to request City Council approval to submit an application to the State Flood Mitigation Program Board for $98,494,178 in state sales tax increment funding for the Bee Branch Watershed Flood Mitigation Project, as follows: 1. Approval of the application in its entirety, which includes but is not limited to, the Project Plan that describes the 12 phases and their projected schedule, and the proposed issuance of debt to support the Plan. 2. Approval of the City's authorized representatives for the grant. 3. Approval of the local match funding, which comes from 3 main sources. These are the Stormwater Utility fee, grants that the City already has acquired, and assessments on pervious alleys. BACKGROUND State Flood Mitigation Program The State Flood Mitigation Program (the Program) was created in 2012 establishing two possible funding sources for Bee Branch Watershed improvements: a Flood Mitigation Fund and a Sales Tax Increment Fund. To date, no funds have been appropriated for the Flood Mitigation Fund. The Sales Tax Increment Fund is to consist of the increase in the state share of the sales tax revenues from communities with qualifying applications. The maximum state share of sales tax increment that can be diverted from the state and used instead for flood mitigation projects is $30 million a year for twenty (20) years for a total of $600 million. The maximum award for any qualifying single community is $15 million per year. To qualify for sales tax increment funding, federal financial assistance must have been secured for the project. A local match is also required and the state sales tax increment cannot exceed 50% of the total project cost. In April of 2013 the State Flood Mitigation Program Board (the Board) was established. And at its third meeting in July of 2013, the Board adopted the administrative rules for the Program. As a result, the Board can begin considering applications in November of 2013. Bee Branch Watershed Flood Mitigation Project Six Presidential Disasters have been issued between 1999 and 2011 due to flash flooding as a result of localized, intense rainstorms in the Dubuque area. Flash flooding occurs with little or no warning time, with water levels rising and flowing at extremely fast rates. The Bee Branch Watershed, which co approximately 6.5 square miles within developed part of the City and where our residents either live or work, is co hardest with flash flooding. It should b the flash flooding experienced in the Watershed is not just a little water in th Residents have reported and documented flooding that reached the rafters, flooding that inundated water heaters, furnaces, and electrical boxes, flooding that caused fires in the home. And the flooding is not limited to basements. It is stormwater urb to curb, stalling and even floating cars. ages public and private e disruption of commerce and expensive repairs, on a Dubuque residents and businesses are forced to deal with flooding experienced within the Bee Branch Watershed r danger to the lives and livelihood of citizens. vers the most over 50% of ntinually hit the e noted that Bee Branch P hasement rushing down streets from c vehicles, stranding motorists The flash flooding also dame resulting in thE basis. While many occasional flooding, the flash has repeatedly posed a cleai Basement flooding with inundated water heaters, furnaces, and electrical panels. flooding in streets, stranding motorists in stalled cars. The May 1999 storm was one of the most destructive flash floods in the City's history, with $16 million in property damage. The City took action and commissioned an engineering study to look into the nature of the flooding and identify solutions to mitigate or eliminate the flash flooding experienced in the Bee Branch Watershed. The Drainage Basin Master Plan completed in 2001 established that there are more than 1 ,100 properties at risk of flood damage as a result of the flash flooding. A subsequent study in 2009 by the Federal Emergency Management Agency (FEMA) identified a flood prone area with 1 ,373 properties. In addition to homes, there are over 70 businesses in the at -risk area with over $500 million in annual sales. Eighty -five percent (85 %) of the impacted properties have buildings that are potentially eligible for listing on the National Register of Historic Places, the official list of the Nation's historic places worthy of preservation. In fact, fifty - seven percent (57 %) of the buildings are more than 100 years old. The flood prone area in the Bee Branch Watershed encompasses historic neighborhoods offering some of the community's most affordable workforce housing. Most residents are working families, 2 many are elderly -- those least likely to recover from repetitive flood loss. Repetitive flood damage leads to disinvestment; from 2004 to 2009, while commercial property values grew by 39% citywide, they fell by 6% in the Bee Branch Watershed flood prone area. The Drainage Basin Master Plan also outlined several improvements throughout the watershed to mitigate future flooding and disasters. Collectively, the improvements form the basis of the Bee Branch Watershed Flood Mitigation Project. Having identified the flooding issue as a top priority, the Dubuque City Council adopted the Drainage Basin Master Plan and established funding, including a stormwater management utility fee, to construct the Bee Branch Watershed Flood Mitigation Project. The City of Dubuque established the Bee Branch Citizen Advisory Committee in 2003 to solicit public input to assure that in addition to flooding, the project addresses the issues and concerns of residents and businesses most directly impacted by the flooding. The Committee formally met 6 times between 2003 and 2004, developing recommendations that were then presented to the City Council. Additional citizen input was obtained through a series of 9 public workshops. Notices were provided by direct mail to over 2,000 households in the areas most directly impacted. In addition, press releases were issued to notify all residents of the workshops. The recommendations center around the "day- lighting" of the buried Bee Branch Creek thereby creating an attraction, enhancing the neighborhoods, and improving the quality of life of Bee Branch Watershed residents. Citizens also recommended improvements such as pervious pavement systems to address the flooding. To the extent feasible, their preferences have been implemented in the project design. The Bee Branch Watershed Flood Mitigation Project is a multi - phased, fiscally responsible investment. It reflects a holistic approach to mitigate flooding as it will also improve water quality, stimulate investment, and enhance the quality of life. Having secured the necessary federal and state funding approvals, permits, and funding, Dubuque has pushed forward with planning, execution, and completion of three phases and the initiation of two more. The 12 phases of the Flood Mitigation Project are: Bee Branch Watershed Flood Mitigation Project Phases Phase Description 1 Carter Road Detention Basin 2 West 32nd Street Detention Basin 3 Historic Millwork District 4 Lower Bee Branch Creek Restoration 5 Flood Mitigation Gate Replacement 6 Impervious Surface Reduction 7 Upper Bee Branch Creek Restoration 8 22nd Street Storm Sewer Improvements 9 Flood Mitigation Maintenance Facility 10 North End Storm Sewer Improvements 11 Water Plant Flood Protection 12 17th Street Storm Sewer Improvements Est. Completion Completed 2004 Completed 2009 Completed 2012 2014 2015 2034 2016 2020 2020 2019 2020 2020 Est. Cost $1,076,315 $4,158,589 $7,977,311 $21,274,685 $2,099,000 $57,420,000 $64,823,636 $3,380,000 $4,360,000 $1,160,000 $3,800,000 $7,520,000 3 Individually, the 12 phases of the project will provide some benefit. But flash flooding can be expected to occur until all of the improvements are implemented. But it is also true that with the completion of each subsequent phase, the threat of flash flood damage is lessened and the resulting damage will be mitigated. The combined phases of the project will reduce the volume of floodwaters, slow the rate the floodwaters flow through the upper watershed, increase the safe conveyance of floodwaters through the flood -prone area, and provide physical barriers to prevent floodwaters from inundating the City's only potable water source. The City has already taken steps to reduce the volume of floodwaters by beginning the process of converting pervious alleys and street systems into pervious pavement systems to convey floodwaters into the ground. Eight alleys have already been converted and an additional 73 currently under design will be converted in the next 3 years utilizing financial assistance through the Clean Water Act. In addition, streets in the flood -prone Historic Millwork District were also redone with pervious pavement systems. The City has also taken action in order to reduce the rate that floodwaters flow from upstream areas down into the flood -prone area by constructing a new detention basin and modifying another upstream of the flood -prone area. A total of 20 properties were acquired to allow for the construction of the Carter Road Detention Basin and expansion of the 32nd Street Detention Basin. The City expended over $5.2 million for acquisition, engineering design, and construction of these basins. Finally, embracing the idea of day- lighting the buried Bee Branch Creek, the City has undertaken a substantial effort to increase the safe conveyance of floodwaters through the flood -prone area in a manner that will not negatively impact downstream properties. The City acquired and deconstructed over 100 properties to clear the path for the Bee Branch Creek Restoration. The City hired an engineering consulting team to design the creek restoration project. The City hired a construction contractor to begin construction of the Lower Bee Branch Creek Restoration. And the City anticipates soliciting bids to construct portions of the Upper Bee Branch Creek Restoration in early 2014. In total, the City has already spent more than $20 million towards the Bee Branch Creek Restoration. While the City took steps to complete the first 2 phases of the Project and start 2 more, flash flooding and disasters have repeatedly occurred in 2002, 2004, 2008, 2010, and most recently in 2011. With each disaster, especially the latest where 10 inches of rain fell in 12 hours, the need to implement the components of the Bee Branch Watershed Flood Mitigation Project is ever present. The 2010 State of Iowa Hazard Mitigation Plan estimates that Dubuque County has an annual loss of $10,556,235 due to flooding. Bee Branch Watershed Flood Mitigation Project Phase Descriptions While more detail is provided in the Drainage Basin Master Plan (DBMP), a brief description of each phase is outlined below. 4 Phase 1: Carter Road Detention Basin (Completed in 2003) The first phase of the Bee Branch Watershed Flood Mitigation Project involved the construction of a new detention basin in the northwest portion of the Bee Branch Watershed. Comprised of an earthen dam approximately 350 feet long and 40 feet high, it can impound 59.3 million gallons of stormwater runoff. The principal outlet of the dry bottom detention basin is a 15 -inch diameter culvert with a 24 -inch diameter gated culvert. The high flow outlet is a 48- inch diameter riser pipe that is approximately 37 -feet high. An asphalt access road provides access to the outlet structure for operational and maintenance needs. Creation of the detention basin required the acquisition of property and easements. As outlined in the Drainage Basin Master Plan, the purpose of the Carter Road Detention Basin is to hold back stormwater, and detain it to allow time for the downstream flood -prone area to drain. The Carter Road Detention Basin is designed to reduce the peak flow of runoff from a 100 -year rain by 98% from 1,490 cubic feet per second down to 30 cubic feet per second. The detention basin can temporarily store up to 59.3 million gallons of stormwater. Phase 2: West 32'' Street Detention Basin (Completed in 2009) The second phase involves the expansion of the West 32 "d Street Detention Basin which was originally built in the early 1950s. This project phase required the acquisition of sixteen (16) properties, as well as, street and utility reconstruction to gain access to the storm sewer system and a gate structure for maintenance of the expanded basin's wet pond. The expanded West 32 "d Street Detention Basin provides the maximum amount of storage possible given the available land area. The basin was planted with a combination of wild flowers, prairie grass, and wetland vegetation which maximizes its ability to retain runoff and reduce flows and volumes to downstream properties. As outlined in the Drainage Basin Master Plan, expansion of the West 32nd Street Detention Basin, in conjunction with the construction of the new Carter Road Detention Basin, detains stormwater to the extent that the existing downstream Bee Branch storm sewer is capable of handling the peak flood flows from 32 "d Street to 24th Street. Prior to expansion, floodwaters would overwhelm the downstream storm sewer, overtop the basin, and result in a wall of water flowing through the City's north end contributing to the street and basement flooding. As a result of the improvements, the storage capacity was more than double from 15 million gallons to 33.5 million gallons and the peak flow of runoff 5 out of the detention basin is reduced to 30% of the peak flow into the basin and downstream flooding has been slightly reduced. Phase 3: Historic Millwork District (Completed in 2012) With federal funding from the U.S. Department of Transportation through the Transportation Investment Generating Economic Recovery (TIGER) grant, the City's first pervious pavement street was constructed in the area known as the Historic Millwork District. The project was constructed over two years and included the reconstruction of 10th Street from Jackson to Elm Streets, Washington Street from 9th to 11th Streets, Jackson Street from 7th to 11th Streets with pervious materials, pervious alleys, utility upgrades, streetscaping, intermodal components, and pervious parking areas. The utility upgrades included the construction of new storm sewers, to improve the stormwater conveyance in the area. The project resulted in streets with pervious pavement systems that effectively convey stormwater into the underlying soils versus collecting it and sending it quickly downstream where it previously contributed to flooding. The underlying soils have permeability rates of over 6 inches per hour. In addition to changes to the streets, pervious pavement systems were also utilized in alleys. The system was designed to mitigate the recurring flooding problem that plagued the Historic Millwork District and stood in the way of its redevelopment. Pervious pavement system installed in the flood-prone Historic Millwork District Phase 4: Lower Bee Branch Creek Restoration (Under Construction) As outlined in the Drainage Basin Master Plan and the Bee Branch Creek Alignment Study, the Lower Bee Branch Creek Restoration Project includes the construction of the 2,500 - foot long creek and flood plain area from Kerper Boulevard west and north to the railroad tracks just south of Garfield Avenue, replacing the underground Bee Branch Storm Sewer. In addition to day - lighting and restoring the Bee Branch Creek, this phase included the restoration of the floodplain, dredging of the 16th Street Detention Basin, relocation of utilities, and reworking the street system through the area to accommodate the new flood mitigation facility and the redevelopment of adjacent private property. Creek day - lighting required the construction of two bridges, maintenance access to the creek, hike /bike trail, safety and security measures, vegetation, recreational components and overlook areas for better monitoring of the creek. The acquisition of property is required to make room for the day - lighted creek and floodplain. 6 While the improvements upstream in the Bee Branch Watershed contribute to the solution, they cannot reduce the runoff flows to the point where the existing downstream Bee Branch storm sewer can handle flows without causing flooding. This phase involved the removal of the buried storm sewer and its replacement with a restored creek and flood plain. This "day- lighting" of the lower reach of the buried Bee Branch Creek from the 16th Street Detention Basin allows stormwater from flash floods to safely move through this area of the watershed without flooding adjacent properties. Waterways buried under streets, vacant lots or city parks can be dug up and restored to their natural above - ground state —a process called day - lighting. By uncovering buried streams, water would again flow along the surface instead of being routed through pipes, or a 16 -foot wide and 8 -foot high brick sewer in the case of the Bee Branch Creek in the City of Dubuque. The day - lighting of the Bee Branch Creek will greatly expand the capacity of the Bee Branch storm sewer trunk line. Historically storm sewers are streams or creeks that have been diverted into a culvert pipe to make way for urban development; natural waterways that once flowed over land were then routed into and through underground pipes. Burying a stream was the method used to control the water and flooding by hiding it underground. That is until the pipes are no longer sufficient to carry the waters and result in flash flooding. Successful daylighting projects have already been completed in cities around the world including Seoul, London, Philadelphia, and Springfield, MO among others. This is the natural and preferred method to handle stormwater flooding. The 16th Street Detention Basin was modified in 1973 to function as an integral part of the floodwall /levee system that prevents the Mississippi from flooding the Bee Branch Watershed. The day - lighting of the Bee Branch creek necessitated that the 16th Street Detention Basin be dredged and reshaped as part of the Lower Bee Branch Creek Restoration. This ensures that the floodwall /levee system functions as designed and that flooding does not occur on the City side of the system when the Mississippi is above flood stage. The Bee Branch storm sewer only had the capacity for a 3 -year flood event. The Lower Bee Branch Creek Restoration, in combination with the other associated projects, will allow for a 100 -year event to safely pass through the watershed without flooding and flood damage. Phase 5: Flood Mitigation Gate Replacement (Under Design) This phase involves the replacement of the flood mitigation gates, repair of the concrete gate structure and concrete wing walls, installation of check valves on the pump discharges, and installation of new air release valves at the Mississippi River floodwall's Bee Branch pumping station. The flood gates were installed in the 1950s and modified by the U.S. Army Corps of Engineers (USAGE) for the Dubuque's Flood Mitigation System, the John C. Culver Floodwall, in the early 1970s. The 16th Street Detention Basin discharges into a cutoff channel of the Mississippi River through twin 12 -foot by 12 -foot concrete box culverts under normal river stages. During gravity flow, the twin 12 -foot by 12 -foot flood gates are open; conversely, during flood events, the flood gates are closed to prevent the Mississippi River from flooding the landward side of the levee. 7 An alternative design has been developed that would allow interior floodwaters to automatically pass into the Mississippi River when a positive hydraulic gradient occurs, eliminating the need to manually operate the system in inclement weather. Today, when the flood control gates are closed, all stormwater from the Bee Branch Watershed must be pumped through the floodwall /levee system into the Mississippi River. Under the proposed system, when the depth of floodwaters on the City side exceed the depth of the Mississippi River, stormwater would flow from the 16th Street Detention Basin into the Mississippi River automatically, augmenting the discharge of the pumps. The flood gates prevent the Mississippi River from flooding the Bee Branch Watershed. Phase 6: Impervious Surface Reduction (Under Construction) This phase of the project involves the replacement of impervious alley surfaces within the Bee Branch Watershed with pervious pavement systems to convey the stormwater into the ground. Of the 245 alleys within the Bee Branch Watershed, eight (8) alleys have been reconstructed with pervious pavement systems. Utilizing federal financial assistance, design is underway to reconstruct another 73 alleys over a three year period so that by the end of 2015, 33% of the alleys in the Bee Branch Watershed will have been converted to pervious systems that convey stormwater into the ground versus shedding runoff to surrounding properties and downstream in the Bee Branch Watershed. The remaining alleys are to be converted into similar conveyance systems. While each alley has unique conditions to be considered such as underlying soil porosity and alley slope, the pervious pavement system will include reconstruction of the alley surface itself as well as the sub- base, safety and security measures where appropriate, and the addition, relocation or reconstruction of underground utilities. There is a direct correlation between impervious area and the runoff generated as a result of a rainstorm. The impervious area reduction planned for the Bee Branch Watershed is critical to address the predicted and increasingly intense rainstorms witnessed in Dubuque since 1999. Conventional approaches to stormwater management can attempt to address increased runoff and prevent flooding and flood damage, but even they have their limitations. That is why it is important to incorporate an approach that restores hydrologic functions through techniques such as pervious pavement, which conveys runoff into the ground closer to where it originates rather than conveying it quickly downstream. Pervious pavement can reduce localized flooding and significantly reduce negative downstream impacts in a way that other approaches are less able to do. All of the alleys in the Bee Branch Watershed are located over soils with permeability rates conducive to accepting stormwater. All soil permeability rates are above the 0.5 inches per hour threshold for pervious alleys with 31 % of the alleys being over soils with permeability rates between 2.0 and 6.0 inches per hour. With the conversion of impervious surfaces to pervious surfaces, and the corresponding reduction in directly 8 connected impervious areas, runoff reductions of up to 80% will be realized within the watershed. Phase 7: Upper Bee Branch Creek Restoration (Under Design) As outlined in the Drainage Basin Master Plan and the Bee Branch Creek Alignment Study, the Upper Bee Branch Creek Restoration Project includes the removal of a buried storm sewer and replacing it with a 2,300 -foot long creek and flood plain area from where the Lower Bee Branch Creek Restoration terminates just south of Garfield Avenue north to 24th Street. In addition to the restoration /day - lighting of the creek and floodplain, this phase includes the construction of vehicular and pedestrian bridges, bike /hike trails (that includes replacement of what has to be removed to restore the creek), multi -use maintenance access, utility relocations, vegetation, overlooks (for better monitoring of the creek), safety and security measures, parking, and education and recreational components. The acquisition of property is required to make room for the day - lighted creek and floodplain. Artist's rendering of the day - lighted Bee Branch Creek as presented in the 2004 Bee Branch Creek Alignment Study The Upper Bee Branch Creek Restoration Project includes the construction of large- diameter culverts under the Canadian Pacific (CP) Railroad yard and Garfield Avenue. It also includes property acquisitions (both partial and full), roadway reconfigurations, construction of bridge crossings and an outfall at 24th Street where the existing Bee Branch storm sewer will remain albeit in a re- aligned configuration. The improvements upstream in the Bee Branch Watershed associated with Phase 1 and Phase 2 of the project detain floodwaters to the extent that the downstream Bee Branch storm sewer from W. 32nd Street to 24th Street has the capacity to handle floodwaters. But at 24th Street, additional floodwaters flow to the storm sewer from the east, at 22nd Street additional floodwaters flow to the storm sewer from the west, and at 17th Street additional floodwaters flow to the storm sewer from the west which collectively overwhelm the storm sewer resulting in the frequent flash flooding experienced over the past twelve years. Therefore, increased conveyance is necessary to safely allow floodwaters to pass through the watershed without causing flooding. This phase builds on the creek day - lighting associated with the Lower Bee Branch Creek Restoration. It involves the removal of the buried storm sewer and its replacement with a larger restored creek and flood plain. Phase 8: 22nd Street Storm Sewer Improvements (Under Design) This phase involves the construction of a large diameter storm sewer from 22nd Street west across Central Avenue. Due to the size of the proposed storm sewer required to 9 reduce stormwater runoff and flooding, total street reconstruction along with utility and traffic signal replacement is necessary. Stormwater can form what resembles a river running down 22nd Street from Central Avenue to Elm Street. Construction of the Bee Branch Watershed Flood Mitigation Project will alleviate this somewhat by ensuring that the stormwater sewer between Central Avenue and Elm Street does not fill up and surcharge due to downstream storm sewer capacity. Without this increased capacity, the surcharging will still occur as the storm sewer between Central and Elm is not large enough to handle even a moderate rain event. A hydraulic capacity analysis of the Kaufmann Avenue (22nd Street) storm sewer revealed that the existing storm sewer is insufficient to convey more than a 2- year rain event. Upsizing the storm sewer between Central Avenue and Elm Street is only feasible after construction of the restored Bee Branch Creek which will be able to handle the additional stormwater. Phase 9: Flood Mitigation Maintenance Facility (Under Design) In order to maintain the mile long creek and floodplain areas and ensure they function as designed, when necessary, a Flood Control Maintenance Facility is planned near 16th and Elm Streets in the vicinity of the Lower Bee Branch Creek Restoration. In addition to providing work space for City employees assigned to maintaining the Bee Branch Creek Restoration, it will provide storage of a boat recently purchased by the City to provide access to every foot of the newly created shoreline. It will also provide public restrooms which will double as a storm shelter for people within the greenway in the event that severe weather approaches while they are in the mile long corridor. Parking will also be provided. The Flood Control Maintenance Facility will provide the work space and equipment storage areas necessary to provide adequate maintenance of the Bee Branch Creek Restoration and the 16th Street Detention Basin and ensure that the facilities are able to function at an optimum level when a flash flood occurs. Phase 10: North End Storm Sewer Improvements (Under Design) This phase includes the upgrading of the storm sewers within the heart of the at -risk properties on 25tH 26tH 27tH 28th 2gtn and 30th Streets between White and Elm Streets. Currently the existing storm sewers in this area only handle minimal rain events; they will be upsized to handle stormwater runoff from heavy rains. While each street's storm sewer will be considered individually, the storm sewer capacity will be expanded up to ten times the current capacity. Typically, storm sewers are designed to handle rain in small quantities and not designed to capture stormwater from short duration, high intensity rains that can cause flash floods. With the completion of the restored Bee Branch Creek, upgrading the local storm sewers will significantly decrease localized street flooding and basement flooding and prevent the effects of flash flooding witnessed in the past in this area of the watershed. The storm sewer along each street would intercept and convey approximately 55 cubic feet per second (cfs) to the Bee Branch storm sewer requiring a combination of 15, 18, 24, and 30 -inch diameter storm sewer and approximately 105 storm sewer inlets. 10 Phase 11: Water Plant Flood Protection (Under Design) The water plant is the public supply of potable water for the community. The City has concerns over the impact of flooding on the water treatment plant should there be significant interior drainage flooding or a breach in the John C. Culver Floodwall along the Mississippi River. In response to this concern, a conceptual analysis of a structural flood - proofing strategy was conducted. The City is interested in a structural solution that incorporates a combination of permanent and temporary measures for flood proofing. The analysis used available Light Detection and Ranging (LiDAR) topographic data, aerial images of the area, and information on typical earthen berm and floodwall requirements. It is recommended that the water treatment plant be equipped with a permanent concrete floodwall along the existing alignment of the property fence line, with the ability to deploy temporary measures at the access point openings. The floodwall will be 6 feet aboveground and is recommended to have a T -wall footing. Due to the floodwall construction, stormwater modifications will need to be designed and constructed. Gravity stormwater pipes will be equipped with backflow prevention devices to prevent ponding water from collecting within the flood proofed area. Stormwater conveyance systems otherwise impacted would need to be replaced with pumping capacity to pump to the Mississippi River or other downstream stormwater management facility This phase of the project is designed to ensure adequate water for firefighting and a potable water supply for the Dubuque Community and beyond. Flood proofing of the water treatment plant will protect the facility and allow it to remain in operation and available in the event of a levee failure or localized flash flooding. The cost to reconstruct and /or relocate the existing potable water treatment plant is estimated to be between $65 and $80 million. In its present condition, the water treatment plant is designed to run as is for another 30 to 40 years. The Water Plant is not in the Bee Branch Watershed. Phase 12: 17th Street Storm Sewers (Under Design) As outlined in the DBMP, this project involves the construction of a large diameter storm sewer from Elm Street to W. Locust Street and Dorgan Place to safely convey more stormwater from the W. Locust Street sub - watershed to the restored Lower Bee Branch Creek. Due to the size of the proposed storm sewer, the project will require total street reconstruction and the reconstruction /relocation of underground utilities. The DBMP identified multiple locations between W. Locust Street and the Bee Branch Creek Restoration where the existing storm sewer capacity is not adequate to carry even the 10 -year rainstorm. A problem area was identified at the base of Locust Street and 17th Street where the grade flattens along the street causing flooding in the area. In addition, stormwater will flow rapidly down 17th Street much like a running river. The expansion of the capacity of storm sewer inlets and pipes would significantly reduce flooding of streets and adjacent properties within the Locust Street Drainage Subarea. The hydraulic model indicated that a 72 -inch diameter relief storm sewer was required 11 to safely convey the 10 -year storm with minimal street flow. The recommendation for the Locust Street Drainage Subarea is to provide for a replacement 84 -inch diameter storm sewer system along 17th Street. This increased sewer will provide additional conveyance capacity for the downstream portion of the Locust Street Drainage Subarea and mitigate the flash flooding witnessed along 17th Street. DISCUSSION The City of Dubuque has completed an application seeking $98,494,178 in state sales tax increment funding for the Bee Branch Watershed Flood Mitigation Project. The application is based on the premise that the application will be approved by the Flood Mitigation Board before December 31, 2013. If the application approval process is delayed until after December 31, 2013, the projected sales tax increment would be negatively impacted and the City would need to adjust the amount of annual sales tax increment requested in the application. If approval of the application is delayed, the City of Dubuque would not receive the first payment of sales tax increment until January 15, 2015 and implementation of Bee Branch Watershed Flood Mitigation Project elements would be delayed at least one year. Recognizing that many communities across Iowa have suffered through extreme weather events over the past decades, triggering numerous disaster declarations, the City of Dubuque has taken a proactive yet conservative approach to use the Sales Tax Increment funds to leverage local, state, and private financial assistance for the Bee Branch Watershed Flood Mitigation Project. The City is asking for less than $7 million in sales tax increment in any given year, with an average annual request of only $4,689,709. The City also is not requesting all of the sales tax increment that will be generated over the 20 year period. In fact, the City of Dubuque is only asking for 59.37% of the 70% of the eligible City of Dubuque projected sales tax increment. Instead of borrowing for all of the phases of the Bee Branch Watershed Flood Mitigation Project in the first year, the City of Dubuque is strategically spreading the project phases over the twenty years that the flood mitigation legislation allows for projects to be completed. This allows more sales tax increment to be available for other Iowa communities that may have project funding requests through the flood mitigation program and allows for the proper implementation of the City of Dubuque's Flood Mitigation project. Table 1 shows the City of Dubuque projected 70% sales tax increment compared to the portion of the City of Dubuque 70% sales tax increment the requested in the City application by year. Strategically spreading the project phases over twenty years reduces the City and lenders risk when issuing debt since in total the City will only be requesting 59.37% of the projected City of Dubuque 70% State Sales Tax Increment, leading to more competitive interest rates. This also allows the City to construct many of the phases over time on a pay -as -you go basis. 12 Table 1 City of Dubuque Projected 70% Sales Tax Increment Request Compared to City of Dubuque Maximum Projected 70% Sales Tax Increment City of Dubuque City of Dubuque City of Dubuque Projected 70% 70% Sales Tax Increment Fiscal Maximum Projected Sales Tax Increment % of Maximum Projected Year 70% Sales Tax Increment Request 70% Sales Tax Increment 2014 $332,469 $332,469 100.00% 2015 $1,407,664 $1,407,664 100.00% 2016 $2,132,255 $2,132,255 100.00% 2017 $2,871,049 $2,871,049 100.00% 2018 $3,624,322 $3,624,322 100.00% 2019 $4,392,361 $4,392,361 100.00% 2020 $5,175,452 $5,175,452 100.00% 2021 $5,973,893 $5,973,893 100.00% 2022 $6,787,982 $6,787,982 100.00% 2023 $7,618,027 $6,944,414 91.16% 2024 $8,464,342 $6,968,288 82.33% 2025 $9,327,245 $6,946,514 74.48% 2026 $10,207,060 $6,957,577 68.16% 2027 $11,104,120 $6,947,487 62.57% 2028 $12,018,761 $6,947,500 57.81% 2029 $12,951,331 $6,500,000 50.19% 2030 $13,902,178 $6,000,000 43.16% 2031 $14,871,662 $5,500,000 36.98% 2032 $15,860,148* $3,260,000 20.55% 2033 $16,868,008* $2,824,951 16.75% Total $165,890,329 $98,494,178 *Cannot exceed $15,000,000 in one year per Iowa Code. * *Total City of Dubuque maximum State Tax Increment with $15,000,000 limitation is $163,162,173. The Iowa Department of Revenue provided the City of Dubuque with annual sales tax information for fiscal years 2011, 2012 and 2013. This information was combined with information provided on the Iowa Department of Revenue's website for the City of Dubuque's historic taxable retail sales for the past ten years. Table 2 shows the City of Dubuque annual taxable sales and annual taxable sales growth. The rate of change each year was calculated, and the ten year average growth rate was used to project future sales tax increment growth by year. The ten year historic growth rate on taxable retail sales in the City of Dubuque was calculated at 1.97 %. The City's financial advisor, Piper Jaffray, has concluded that use of historical sales tax growth average for purposes of projections is a responsible basis for calculation. Table 3 demonstrates how the City of Dubuque calculated sales tax increment. The top portion of the table shows the historic retail sales and annual retail sales growth percentage for the City of Dubuque for Fiscal Years 2003 to 2013. The Gross Sales Tax Revenue column shows the amount of state 13 sales tax revenue (5% of retail sales) generated each fiscal year. The ten year historic growth rate on taxable retail sales in the City of Dubuque is 1.97 %. Table 2 Annual Taxable Sales & Annual Sales Growth Fiscal Annual Annual Taxable Taxable Sales Year Growth % Sales Growth ($) 2003 $838,324,775 2004 3.36% $866,476,233 $28,151,458 2005 3.94% $900,625,915 $34,149,682 2006 5.31% $948,460,852 $47,834,937 2007 2.28% $970,039,446 $21,578,594 2008 1.90% $988,428,418 $18,388,972 2009 - 2.75 %* $961,287,890 $(27,140,528) 2010 - 1.38 %* $948,022,147 $(13,265,743) 2011 1.42% $961,477,950 $13,455,803 2012 4.04% $1,000,299,252 $38,821,302 2013 1.57% $1,016,036,855 $15,737,603 10 Year Avg. 1.97% * Major flash flooding events occurred June 2008 and July 2010 having an effect on sales tax increment revenues within a year after each event. The bottom portion of the chart shows the projection of annual retail sales and sales tax revenue for fiscal years 2014 to 2033. The annual retail sales column is increased each year by the ten year historic growth rate on taxable retail sales of 1.97 %. The 70% of City of Dubuque State Sales Tax column shows the amount of sales tax generated in the City from which the sales tax increment can be calculated beginning in fiscal Year 2014. The base year for calculating the sales tax increment is fiscal year 2013. The first year that sales tax increment will be available is fiscal year 2014; however, only the last two quarters in fiscal year 2014 are eligible to be paid into the Flood Mitigation project fund. The last two quarters of the fiscal year only provide 47.7% of the sales tax revenue in the entire year for the City of Dubuque, so only 47.7% of fiscal year 2014 sales tax growth was used to project sales tax increment revenue which results in increment of $332,469. The City of Dubuque is eligible to collect all quarters of sales tax increment beginning in Fiscal Year 2015. Table 4 shows the City of Dubuque 70% sales tax increment requested compared to the total available State Flood Mitigation Program sales tax increment by year. The City of Dubuque has estimated sales tax increment conservatively. The last two quarters of the fiscal year only provide 47.7% of the sales tax revenue in the entire year for the City of Dubuque, so only 47.7% of fiscal year 2014 sales tax growth was used to project sales tax increment revenue. In addition, the City of Dubuque kept the negative sales tax growth years in the calculation (Fiscal Year 2009 and 2010). 14 Table 3 City of Dubuque Projected 70% Sales Tax Increment and Annual Growth Percent City of Dubuque Maximum Annual Annual 70% of City of Projected 70% Fiscal Annual Retail Retail Sales Retail Sales Gross Sales Sales Tax Dubuque State Sales Tax Year Sales Growth ($) Growth % Tax Revenue Growth % Sales Tax Increment 2003 $838,324,775 $41,916,239 $29,341,367 2004 $866,476,233 $28,151,458 3.36% $43,323,812 3.36% $30,326,668 2005 $900,625,915 $34,149,682 3.94% $45,031,296 3.94% $31,521,907 2006 $948,460,852 $47,834,937 5.31% $47,423,043 5.31% $33,196,130 2007 $970,039,446 $21,578,594 2.28% $48,501,972 2.28% $33,951,380 2008 $988,428,418 $18,388,972 1.90% $49,421,421 1.90% $34,594,995 2009 $961,287,890 $(27,140,528) -2.75% $48,064,395 -2.75% $33,645,077 2010 $948,022,147 $(13,265,743) -1.38% $47,401,107 -1.38% $33,180,775 2011 $961,477,950 $13,455,803 1.42% $48,073,898 1.42% $33,651,729 2012 $1,000,299,252 $38,821,302 4.04% $50,014,963 4.04% $35,010,474 2013 $1,016,036,855 $15,737,603 1.57% $50,801,843 1.57% $35,561,290 Average Annual Historic Growth Rate % 1.97% $519,973,989 1.97% $363,981,792 2014 $1,035,951,177 $19,914,322 1.97% $51,797,559 1.97% $36,258,291 $332,469 2015 $1,056,255,820 $20,304,643 1.97% $52,812,791 1.97% $36,968,954 $1,407,664 2016 $1,076,958,435 $20,702,614 1.97% $53,847,922 1.97% $37,693,545 $2,132,255 2017 $1,098,066,820 $21,108,385 1.97% $54,903,341 1.97% $38,432,339 $2,871,049 2018 $1,119,588,930 $21,522,110 1.97% $55,979,446 1.97% $39,185,612 $3,624,322 2019 $1,141,532,873 $21,943,943 1.97% $57,076,644 1.97% $39,953,651 $4,392,361 2020 $1,163,906,917 $22,374,044 1.97% $58,195,346 1.97% $40,736,742 $5,175,452 2021 $1,186,719,492 $22,812,576 1.97% $59,335,975 1.97% $41,535,183 $5,973,893 2022 $1,209,979,194 $23,259,702 1.97% $60,498,960 1.97% $42,349,272 $6,787,982 2023 $1,233,694,787 $23,715,592 1.97% $61,684,739 1.97% $43,179,317 $7,618,027 2024 $1,257,875,204 $24,180,418 1.97% $62,893,760 1.97% $44,025,632 $8,464,342 2025 $1,282,529,558 $24,654,354 1.97% $64,126,478 1.97% $44,888,535 $9,327,245 2026 $1,307,667,138 $25,137,579 1.97% $65,383,357 1.97% $45,768,350 $10,207,060 2027 $1,333,297,414 $25,630,276 1.97% $66,664,871 1.97% $46,665,410 $11,104,120 2028 $1,359,430,043 $26,132,629 1.97% $67,971,502 1.97% $47,580,051 $12,018,761 2029 $1,386,074,872 $26,644,829 1.97% $69,303,744 1.97% $48,512,621 $12,951,331 2030 $1,413,241,939 $27,167,067 1.97% $70,662,097 1.97% $49,463,468 $13,902,178 2031 $1,440,941,481 $27,699,542 1.97% $72,047,074 1.97% $50,432,952 $14,871,662 2032 $1,469,183,934 $28,242,453 1.97% $73,459,197 1.97% $51,421,438 $15,860,148 15 2033 $1,497,979,940 $28,796,005 1.97% $74,898,997 1.97% $52,429,298 $16,868,008 Total $25,070,875,969 $481,943,085 1.97% $1,253,543,800 1.97% $877,480,661 $165,890,329 The City is asking for less than $7 million in sales tax increment in any given year, which allows more sales tax increment to be available for other Iowa communities that may have project funding requests through the Flood Mitigation Program. The City is only asking for 59.37% of the projected City of Dubuque 70% State Sales Tax Increment. This allows the City to construct some phases over time on a pay -as -you go basis; reducing borrowing interest costs and leveraging more dollars for other cities that apply to this program. Table 4 City of Dubuque Requested 70% Sales Tax Increment Compared to Total Available State Flood Mitigation Funds City of Dubuque City of Dubuque Projected 70% Projected 70% Sales Tax Increment Sales Tax Total Available %of Total Available Fiscal Increment State Flood State Flood Year Request Mitigation Funds Mitigation Funds 2014 $332,469 $30,000,000 1.11% 2015 $1,407,664 $30,000,000 4.69% 2016 $2,132,255 $30,000,000 7.11% 2017 $2,871,049 $30,000,000 9.57% 2018 $3,624,322 $30,000,000 12.08% 2019 $4,392,361 $30,000,000 14.64% 2020 $5,175,452 $30,000,000 17.25% 2021 $5,973,893 $30,000,000 19.91% 2022 $6,787,982 $30,000,000 22.63% 2023 $6,944,414 $30,000,000 23.15% 2024 $6,968,288 $30,000,000 23.23% 2025 $6,946,514 $30,000,000 23.16% 2026 $6,957,577 $30,000,000 23.19% 2027 $6,947,487 $30,000,000 23.16% 2028 $6,947,500 $30,000,000 23.16% 2029 $6,500,000 $30,000,000 21.67% 2030 $6,000,000 $30,000,000 20.00% 2031 $5,500,000 $30,000,000 18.33% 2032 $3,260,000 $30,000,000 10.87% 2033 $2,824,951 $30,000,000 9.42% Total $98,494,178 $600,000,000 The multi - phased Bee Branch Watershed Flood Mitigation Project maximizes the use of multiple funding sources. The City of Dubuque has applied for and been awarded financial assistance from eight agencies from both the State of Iowa and Federal government. The City of Dubuque has issued General Obligation (GO) Bonds, plans to issue additional GO Bonds, and has allocated funds from the local Stormwater Utility to help fund this project. The local financial assistance received by the City from private 16 donations also shows the continued support from the community for this project. Table 5 shows the Bee Branch Watershed Flood Mitigation Project federal and local funding. Table 5 Bee Branch Watershed Flood Mitigation Project Federal and Local Match Funding Sources Sales Tax Project Funding Source Federal $ Local $ Increment Adjustment Total Federal: U.S. EPA Clean Water SRF $7,766,500 $7,766,500 Federal: U.S. EPA Clean Water SRF $1,827,000 $1,827,000 Federal: U.S. EPA Clean Water SRF $9,416,795 $9,416,795 Federal: U.S. EPA Clean Water SRF $1,187,757 $1,187,757 Federal: U.S. EPA Clean Water SRF $28,823,000 $28,823,000 Federal: U.S. Economic Development $1,227,138 $1,227,138 Administration Disaster Relief Grant Local: U.S. DOT TIGER Grant $5,600,000 $5,600,000 Local: I -Jobs II Grant $3,965,500 $3,965,500 Local: RECAT Grant $2,250,000 $2,250,000 Local: U.S. DOT National Scenic Byways $1,000,000 $1,000,000 Grant Local: State Recreational Trail Grant $100,000 $100,000 Local: DMATS $640,000 $640,000 Local: General Obligation Bonds $48,227,604 $48,227,604 Local: Private Donations $165,244 $165,244 Local: Sale of Assets and Land $336,358 $336,358 Local: Stormwater Utility Fees $14,394,096 $14,394,096 Federal: U.S. EPA Clean Water SRF loan $24,491,634 $24,491,634 repayment State: Sales Tax Increment $74,002,544 $74,002,544 Table adjustment for SRF loan repayment $(24,491,634) $(24,491,634) Total Project Funding Source $50,248,190 $76,678,802 $98,494,178 $(24,491,634) $200,929,536 Percent of Total Cost 25.01% 38.16% 49.02% - 12.19% 100% There are two separate Iowa Code sections in chapter 418 for the Flood Mitigation Program that cover the federal financial assistance requirement and the local match requirement. Iowa Code chapter 418.4 subsection 3(b) requires that a City "has been approved to receive financial assistance in an amount equal to at least twenty percent of the total project cost or thirty million dollars, whichever is less, under a financial assistance program administered by the United States environmental protection agency, the federal Water Resource Development Act, the federal Clean Water Act as defined in section 455B.291, or other federal program providing assistance specifically for hazard mitigation." Iowa Code chapter 418.9 subsection 2(d) requires that "the board shall not approve a project unless at least fifty percent of the total cost of the project, less any federal financial assistance for the project, is funded using local matching funds..." Table 5 is a copy of a table in the Iowa Flood Mitigation Project Application (Tab A in table C on page 4) which combines the requirement of having "federal financial assistance of at least 20% of the total project cost or $30 million, whichever is less" and the requirement of having a "local match of at least 50% of the total cost of the project less any federal financial assistance." This requires the "Adjustment" column in the table for any city that is using federal financial assistance in the form of a low 17 interest loan to reduce interest costs for the State Flood Mitigation Grant. Specifically in the City of Dubuque's Flood Mitigation Project Application, the City was awarded federal financial assistance from U.S. EPA Clean Water SRF of $24,491,634 for the Upper Bee Branch phase. The U.S. EPA Clean Water SRF federal financial assistance will be repaid by the projected 70% of sales tax increment and must be listed in the "Federal $" column. The $24,491,634 of sales tax increment that will repay the U.S. EPA Clean Water SRF must also be listed in the "Sales Tax Increment" column. Having to list the amount of $24,491,634 twice, once to show federal financial assistance and once to show the requested sales tax increment, incorrectly inflates the total project cost by $24,491,634 since the formula adds them both. In other words, this amount is double counted. For this reason, it is necessary to have an "Adjustment" column to reduce the total funding by the $24,491,634 in U.S. EPA Clean Water SRF federal financial assistance paid by sales tax increment so that the total project cost is calculated as $200,929,536. The City of Dubuque has a total estimated project of $200,929,536 and has a requested projected 70% sales tax increment of $98,494,178. The local funding of $76,678,802 and federal financial assistance of $50,248,190 reduced by the adjustment of $24,491,634 results in total local and federal financial assistance of $107,135,358, which is 50.98% of the total project cost. While it could be argued that interest cost on the debt issued that is paid with stormwater user fees is a project cost, the City of Dubuque did not include the interest cost of $12,257,826 on previously issued debt and interest cost of $11,168,742 on future debt that is paid by stormwater fees. This interest cost would increase the total project cost from $200,929,536 to $224,356,104 if it was included. Table 6 shows the various funding sources for the project budget reflected in the City's application. Table 6 Bee Branch Watershed Flood Mitigation Project Funding Source Project Funding Source Total Amount U.S. DOT TIGER Grant $5,600,000 I -Jobs II Grant $3,965,500 RECAT Grant $2,250,000 U.S. DOT National Scenic Byways Grant $1,000,000 State Recreational Trail Grant $100,000 U.S. Economic Development Administration $1,227,138 Dubuque Metropolitan Area Transportation Study $640,000 U.S. EPA Clean Water SRF Federal Financial Assistance $49,021,052 General Obligation Bonds $48,227,604 Private Donations $165,244 Stormwater Utility Fees $14,394,096 Sales of Assets and Land $336,358 State of Iowa Sales Tax Increment *$98,494,178 Total Funding $200,929,536 18 *Sales Tax Increment Revenue will be paying for a portion of the Upper Bee Branch Creek Restoration U.S. EPA Clean Water SRF Federal Financial Assistance. Funding Source Descriptions U.S. Dept. of Transportation Investment Generating Economic Recovery (TIGER) Grant In 2010, the City of Dubuque was awarded a $5,600,000 Transportation Investment Generating Economic Recovery (TIGER) Grant by the US Department of Transportation as part of the federal government's American Recovery and Reinvestment Act of 2009. The grant was established to enhance mobility and improve the safety and condition of the streets in the Historic Millwork District (Phase 3). This money was drawn down and expensed in full by Fiscal Year 2012. The improvements included the installation of pervious pavement and storm sewer catch basins to provide flood mitigation in the Historic Millwork District. 1 -Jobs 11 Grant In 2010, the Iowa Legislature appropriated $30 million from Fiscal Year 2011 revenue bonds to the I -Jobs Board for a Disaster Prevention Grant program. The Lower Bee Branch Creek Restoration (Phase 4) was awarded $3,965,500 from this I -Jobs II appropriation. This amount was received and expensed in full by Fiscal Year 2012 for the Lower Bee Branch Creek Restoration phase. River Enhancement Community Attraction and Tourism (RECA T) Grant The Vision Iowa Board granted the Bee Branch Creek Restoration (Phases 4 and 7) $2,250,000 to help fund amenities along the open waterway. These amenities include overlooks, bridge enhancements, hike /bike trails, a floating island, amphitheater, trees and landscaping. $189,142 has been received for architectural enhancements on the 16th and Sycamore Street bridges that were completed in the Lower Bee Branch Creek Restoration (Phase 4) of the project. The remaining amount of the award will be used for amenities that are included in the Upper Bee Branch Creek Restoration (Phase 7) of the project, and the remaining elements in the Lower Bee Branch Creek Restoration (Phase 4). U.S. Dept. of Transportation National Scenic Byways (NSB) Grant The Upper Bee Branch Creek Restoration (Phase 7) was awarded a National Scenic Byways grant in the amount of $1,000,000. This grant will be used to help fund the bike /hike trail that will be part of the Dubuque County Heritage Trail that connects Dyersville to Dubuque. The funding will be used for the landscaping, trail markings and signs, lighting, trail clearing, and trail construction and paving which are part of the Upper Bee Branch Creek Restoration (Phase 7) of the project. State Recreational Trail (SRT) Grant The Upper Bee Branch Creek Restoration (Phase 7) was awarded $100,000 from the State Recreational Trails program. The funding helps cover trail lighting, paving, design and parking areas included in the Upper Bee Branch Creek Restoration (Phase 7) of the project. 19 U.S. Economic Development Administration (EDA) Disaster Relief Opportunity Grant The Upper Bee Branch Creek Restoration (Phase 7) was awarded a disaster relief opportunity grant of $1,227,138 from the U.S. Economic Development Administration. This award will aid in funding the open waterway, sanitary sewer and water main construction, roadway construction, and basic landscaping along the Upper Bee Branch Creek Restoration (Phase 7). Dubuque Metropolitan Area Transportation Study (DMATS) DMATS had a $1,000,000 grant set aside for another project in the City of Dubuque. Under new legislation, the money had to be used before the project could be completed. The Iowa DOT requested that the reallocation of the funds be used on a project that has an impact at gateways. The overlook at 16th Street as part of the Lower Bee Branch Creek Restoration (Phase 4) of the project qualified for the reallocation of $640,000. U.S. Environmental Protection Agency Clean Water SRF Federal Financial Assistance The Clean Water SRF is a federal financial assistance program administered by the U.S. Environmental Protection Agency as required by the Federal Clean Water Act as defined in Section 455B.291. The West 32nd Street Detention Basin (Phase 2) of the Bee Branch Watershed Flood Mitigation Project was awarded $1,827,000 in U.S. EPA Clean Water SRF Federal Financial Assistance for construction. The loan funds have been drawn down and the City has begun repayment of the loan. The Lower Bee Branch Creek Restoration (Phase 4) of the project was awarded U.S. EPA Clean Water SRF Federal Financial Assistance in the amount of $7,761,500. There is $5,000 of the federal financial assistance that will be held until the final loan closing documents have been submitted at the end of the project, and the remaining portion of the loan was used for issuance fees. Due to construction cost increases and legal fees, the City of Dubuque applied for supplemental Clean Water SRF Federal Financial Assistance in the amount of $1,187,757 for the remaining qualifying elements in the Lower Bee Branch Creek Restoration (Phase 4). The Upper Bee Branch Creek Restoration (Phase 7) of the project was approved for U.S. EPA Clean Water SRF Federal Financial Assistance in the amount of $28,823,000. This funding will be used to complete the open waterway, culvert, amphitheater, landscaping, level control facility, sanitary sewer, water main, and irrigation along the trail. The Impervious Surface Reduction (Phase 6) of this project was awarded $9,416,795 from U.S. EPA Clean Water SRF Federal Financial Assistance. The City of Dubuque has begun drawing funds from this award for construction. General Obligation Bonds Costs already incurred for completed phases of the Bee Branch Watershed Flood Mitigation project were partially funded by the issuance of General Obligation Bonds by the City of Dubuque. The Carter Road Detention Basin (Phase 1) was funded by the 20 issuance of $1,063,568 in General Obligation Bonds abated by stormwater utility fees. The West 32nd Street Detention Basin (Phase 2) required $2,295,347 in General Obligation Bonds abated by stormwater utility fees. The Historic Millwork District (Phase 3) required $205,787 General Obligation Bonds abated by stormwater user fees, $455,935 General Obligation Bonds abated by sanitary sewer utility fees, $861,952 General Obligation Bonds abated by water utility fees, and $350,828 Urban Renewal General Obligation Bonds abated by Greater Downtown Tax Increment Financing (TIF). $1,837,502 of the bonds for the Historic Millwork District (Phase 3) was used towards engineering and construction, with the remainder used for bond issuance fees. The Upper and Lower Bee Branch Creek Restoration (Phases 4 and 7) required $11,307,187 in General Obligation bonds abated by stormwater utility fees. The City of Dubuque will also be issuing General Obligation Bonds in the future to complete the Bee Branch Watershed Flood Mitigation Project in the amount of $30,800,000. Private Donations The America's Rivers III Campaign is a program designed to give third -party donors the opportunity to fund aspects of the Bee Branch Watershed Flood Mitigation Project. Private donations have been pledged to the Bee Branch Creek Restoration (Phases 4 and 7) in the amount of $165,244. Stormwater Utility /Assessments/Fees The City of Dubuque assesses a Stormwater Utility Fee. The City of Dubuque also assesses abutting property owners of pervious alleys a portion of the cost of the project. The current rate for Fiscal Year 2014 stormwater utility fee is $5.60 per 2,917 square feet of impervious surface, per month. The 2,917 square feet is the average for a single family home in Dubuque, and serves as the base unit for the stormwater utility fee. This rate provides approximately $3.2 million to maintain and make improvements to the City of Dubuque stormwater systems. $2,613,925 has been collected and used to fund the early phases of the Bee Branch Watershed Flood Mitigation Project. The City has budgeted another $11,780,171 of the stormwater utility to the Bee Branch Watershed Flood Mitigation Project. This commitment is projected to raise the City's stormwater utility rates incrementally to $9.00 per month over the twenty year period. Sale of Assets and Land Residential property was acquired due to the need to complete the construction within the property boundaries for the Upper and Lower Bee Branch Creek Restoration (Phases 4 and 7). The land needed for the waterway was separated from the land the dwelling resided on, and then the dwellings were renovated and sold by the City. This has generated $336,358 of revenue that was placed back into the project to acquire other land needed to complete the open waterway. Table 7 shows the amount and type of debt financing for the Bee Branch Watershed Flood Mitigation Project. 21 Table 7 Bee Branch Watershed Flood Mitigation Project Debt Financing Future Debt Issued Issuance Amount General Obligation Bonds $16,503,604 $31,724,000 $48,227,604 U.S. EPA Clean Water SRF $19,010,295 $30,154,872 $49,165,167 Sales Tax Increment Revenue Bond $28,257,938 $28,257,938 Total Debt Financing $35,513,899 $90,136,810 $125,650,709 Grants $14,142,638 Stormwater Utility Fee $14,394,096 Other Funding* $46,742,093 Total Project Funding $200,929,536 *Other funding includes funding from Dubuque Metropolitan Area Transportation Study (DMATS), private donations, sale of assets and land and sales tax increment. * *The Sales Tax Increment Revenue Bonds may be further secured by stormwater revenues or a pledge of debt service taxes. The City of Dubuque has contracted with several consulting and engineering firms to provide estimated costs for the Bee Branch Watershed Flood Mitigation Project. The estimates were also reviewed by the City's engineers and compared with other projects the City has completed to make sure the cost estimates were an accurate depiction of the project. A conservative 2% construction inflation per year was used to calculate estimates for phases to be completed in fiscal year 2015 and beyond. Due to the nature of construction and varied inflation rates per year, the estimates provided in this application may be higher or lower than bid at the time of construction. The detailed estimated budget for each phase of the Bee Branch Watershed Flood Mitigation Project is shown in Table 8. A communication plan is under development to keep residents informed of the impacts associated with the construction of the various phases of the Bee Branch Watershed Flood Mitigation Project. Implementation and operation of the plan is estimated to cost $100,000 per year for the first five years when the most disruptions are expected. The communication plan will be funded using the available portion of the contingency funds, if any, outlined in Table C -8 of the Project Plan. Financing for the project was reviewed by the City's financial advisor, Piper Jaffray, so that the City of Dubuque could provide the most accurate financing costs for the project; however, until the bonds are sold, financing fees and interest rates may fluctuate. The City has also selected an underwriter, R.W. Baird. The selected underwriter will be providing suggestions with respect to structure, timing and marketing of the bonds being sold in order to sell the bonds with the best possible structure and at the lowest interest 22 cost. The City's bond counsel, Ahlers and Cooney, has reviewed the Flood Mitigation statute in regard to what is allowed to be pledged for sales tax increment debt and are of the opinion that the City's financing plan is in compliance with that statute. Table 8 Bee Branch Watershed Flood Mitigation Project Detailed Estimated Budget Debt Projected Interest, Const., Issuance Start/ Phase Property Design / 10% Fees & Phase Complete Description Acquisition Engineering Construction Contingency Reserve Total 1 2003/ Carter Road $140,833 $186,420 $749,062 $1,076,315 2004 Detention Basin 2 2008/ West 32 "d Street $2,144,713 $302,040 $1,711,836 $4,158,589 2009 Detention Basin 3 2011/ Historic $728,239 $7,249,072 $7,977,311 2012 Millwork District 4 2010/ Lower Bee $4,038,430 $2,719,433 $14,316,822 $200,000 $323,824 $21,598,509 2014 Branch Creek Restoration 5 2014/ Flood Mitigation $175,000 $1,749,000 $175,000 $1,986,704 $4,085,704 2015 Gate Replacement 6 2009/ Impervious $4,800,000 $47,820,000 $4,800,000 $57,420,000 2033 Surface Reduction 7 2014/ Upper Bee $12,977,167 $7,230,469 $40,130,000 $4,486,000 $19,569,472 $84,393,108 2016 Branch Creek Restoration 8 2019/ 22nd Street $280,000 $2,820,000 $280,000 $3,380,000 2020 Storm Sewer Improvements 9 2018/ Flood Mitigation $360,000 $3,640,000 $360,000 $4,360,000 2020 Maintenance Facility 10 2016/ North End Storm $96,000 $968,000 $96,000 $1,160,000 2019 Sewer Improvements 11 2019/ Water Plant $310,000 $3,180,000 $310,000 $3,800,000 2020 Flood Protection 12 2019/ 17th Street $630,000 $6,260,000 $630,000 $7,520,000 2020 Storm Sewer Improvements Total $19,301,143 $17,817,601 $130,593,792 $11,337,000 $21,880,000 $200,929,536 If sales tax increment is not realized as projected per fiscal year, or costs associated with the phases increase from the estimates provided to date, the City will adjust the timing of the Impervious Surface Reduction phase of the project and complete this phase as funding becomes available. If the interest rates or construction costs are higher than anticipated, the City of Dubuque will request an amendment to the Flood Mitigation Sales Tax Increment contract to increase the sales tax increment funding, 23 should there be City of Dubuque sales tax increment available and the Flood Mitigation Board has sales tax increment capacity. If the bonds or debt financing have lower interest cost or the project bids come in at lower cost than projected, the City will accelerate the project phases and /or reduce the need for debt. This may also create an opportunity to moderate the impact of the stormwater fee on homes and businesses in Dubuque. The City of Dubuque has been fortunate to secure local, state, and federal financial assistance to the extent that the Bee Branch Watershed Flood Mitigation Project is eligible for funding through the State Flood Mitigation Program. The total commitment in the combination of local and federal funding will provide for 50.98% of the total project cost. The City has secured more than the requisite $30 million in federal financial assistance, with $49 million in financial assistance through the federal Clean Water Act and $1.2 million U.S. Economic Development Administration disaster relief grant, which is a federal program providing assistance specifically for hazard mitigation. And yet, even with the existing outside financial assistance, the cost of implementing all phases of the flood mitigation project is too steep for Dubuque citizens and businesses. Of the more than 30 stormwater utilities across Iowa, Dubuque residents currently pay the second highest rate in the state. And even with the requested Sales Tax increment, a rate increase will be necessary. But to construct the Bee Branch Watershed Flood Mitigation Project without the requested Sales Tax Increment, the rate would need to be increased by 248% which is not feasible as it would significantly burden Dubuque citizens and businesses. The State of Iowa's Flood Mitigation Program will allow for the balance of the Bee Branch Watershed Flood Mitigation Project to be fully implemented, removing Dubuque citizens and businesses from harm's way. Because of the public support for the Bee Branch Watershed Flood Mitigation Project, the stated commitment of the City of Dubuque City Council to implement the various phases of the project, and because the City has already started implementing some of the improvements, non - public investment in the Bee Branch Watershed has already eclipsed $139 million since 2008 with an additional $215 million expected to follow in the next five years for a combined total of $354 million in non - public investment. With the exception of the planned improvements to protect the Water Plant which is outside the Bee Branch Watershed from flooding that would result from a breach or overtopping of the Mississippi River levee, implementation of all the improvements associated with the Bee Branch Watershed Flood Mitigation Project is necessary to mitigate the flash flooding predicted and witnessed in the Bee Branch Watershed. There is no question that the existence of the Carter Road Detention Basin that has been functional since 2003 mitigated to some extent the flooding that occurred in 2004, 2006, 2008, 2010, and 2011. And yet, the damage that resulted from these rainstorms and ensuing flash flooding still proved beyond the resources of the City and State of Iowa, prompting Presidential Disaster Declarations. But it is also true that with the completion of each subsequent phase, the threat of flash flood damage is lessened and the resulting damage will be mitigated. 24 BUDGET IMPACT In order to provide the required local match for the Bee Branch Watershed Mitigation Project and construct the improvements according to the schedule outlined herein, the City will need to adjust the stormwater utility rates accordingly. However, the increases will be more gradual and peak at $9.00 in Fiscal Year 2022 versus the rate schedule adopted previously with the Fiscal Year 2013 Budget (Ordinance 21 -12) which outlined that the rate would peak at $9.00 already in Fiscal Year 2017. Table 9 below shows the rate schedule adopted with the FY2013 budget (Ordinance 21- 12) compared to the rates that adopted with the FY2013 budget. Table 9 Comparison of Previously Adopted Stormwater Utility Rate to Projected Rate Required to Provide Local Match for Bee Branch Watershed Flood Mitigation Project Previously Adopted Projected Stormwater Stormwater Utility Rate Utility Rate to Provide (Ordinance 21 -12) Local Match FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 FY2022 FY2023 $7.00 $7.50 $8.00 $8.50 $9.00 $9.00 $9.00 $9.00 $9.00 $9.00 $9.00 ** $5.60* $5.60* $5.98 $6.38 $6.81 $7.27 $7.76 $8.29 $8.85 $9.00 $9.00 ** *The rates established by Ordinance 21 -12 were modified with the passing of Ordinance 9 -13 which established a rate of $5.60 in anticipation of the availability of State Flood Mitigation state sales tax increment funds for the Bee Branch Watershed Project. **The rates reach their peak at $9.00. Note that in order to provide the required local match of $76,678,802, the City can and will include previous local monies already expended implementing project elements 25 such as the Carter Road Detention Basin, the W. 32nd Street Detention Basin, the Historic Millwork District, Impervious Surface Reduction (Green Alleys), and the Bee Branch Creek Restoration. The Bee Branch Watershed Flood Mitigation Project will prevent an estimated $582 million in damages over the 100 -year design life of the project, with a return on investment of roughly $3 for each $1 spent. RECOMMENDATION I recommend City Council approval of the following actions: 1. Submit an application to the State Flood Mitigation Program Board for $98,494,178 in state sales tax increment funding for the for the Bee Branch Watershed Flood Mitigation Project, with approval of the application in its entirety, which includes but is not limited to, the Project Plan that describes the 12 phases and their projected schedule, and the proposed issuance of debt to support the Plan. 2. Establish the City's authorized representatives for the grant as the City Manager and the Budget Director regarding the grant application and grant administration for the Bee Branch Watershed Flood Mitigation Project. 3. Provide the local match for the Bee Branch Watershed Flood Mitigation Project in the amount of $76,678,802.00, which comes from 3 sources: the Stormwater Utility fee, grants that the City already has acquired, and assessments on pervious alleys. ACTION REQUESTED I respectfully request that the City Council adopt the attached resolutions: 1) Approving the City's application for $98,494,178 in State Flood Mitigation Program sales tax increment grant funding for the Bee Branch Watershed Flood Mitigation Project; 2) Agreeing to provide and make available the local funding required by the grant in the amount of $76,678,802; and 3) Establishing the City Manager and the City Budget Director as the City's authorized representatives regarding the grant. Attach. cc: Barry Lindahl, City Attorney Jenny Larson, Budget Director Ken TeKippe, Finance Director Teri Goodman, Assistant City Manager Gus Psihoyos, City Engineer 26 Laura Carstens, Planning Services Manager Don Vogt, Public Works Director Bob Green, Water Department Manager 27 Prepared by: Deron Muehring, City Hall, 50 W 13th Street, Dubuque IA 52001 563- 589 -4270 RESOLUTION NO. 336 -13 APPROVING APPLICATION FOR STATE OF IOWA FLOOD MITIGATION PROGRAM FUNDING FOR THE BEE BRANCH WATERSHED FLOOD MITIGATION PROJECT WHEREAS, Six Presidential Disaster Declarations have been issued for flooding, severe storms and tornados between 1999 and 2011 due to flash flooding; and WHEREAS, the Bee Branch Watershed, which includes the City of Dubuque's most developed areas where over 50% of city residents either live or work, has experienced flooding impacting thousands of properties and over seventy businesses; and WHEREAS, the City Council of the City of Dubuque has adopted a drainage basin master plan authored by HDR Engineering that outlines improvements collectively referred to as the Bee Branch Watershed Flood Mitigation Project; and WHEREAS, the State Flood Mitigation Program was created in 2012 establishing a Sales Tax Increment Fund which is to consist of state sales tax increments from impacted areas; and WHEREAS, the City of Dubuque has completed The City of Dubuque's Iowa Flood Mitigation Program Flood Mitigation Project Application (the Application) requesting the use of $98,494,178.00 in sales tax increment funds for the Bee Branch Watershed Flood Mitigation Project, a copy of which Application is on file in the Office of the City Clerk; and WHEREAS, the Application requires that the City Council agree to provide and make available up to $76,678,802.00 in local monies to be used to meet the local match requirement of the State Flood Mitigation Program; and WHEREAS, the City must establish an authorized representative able to execute on behalf of the City of Dubuque the Bee Branch Watershed Flood Mitigation Project for the purpose of obtaining financial assistance through the State Flood Mitigation Program. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA AS FOLLOWS: Section 1. The City of Dubuque's Iowa Flood Mitigation Program Flood Mitigation Project Application for the State of Iowa Flood Mitigation Program state sales tax increment funding for the Bee Branch Watershed Flood Mitigation Project is hereby approved. Section 2. The City Manager and the City Budget Director are hereby approved to serve as authorized representatives to execute on behalf of City of Dubuque the Bee Branch Watershed Flood Mitigation Project for the purpose of obtaining financial assistance through the State Flood Mitigation Program. Passed, approved and adopted this 18th day of November, 2013. Attest: Roy D. Buol, Mayor RESOLUTION NO. 337 -13 LOCAL MATCH RESOLUTION FOR THE FLOOD MITIGATION PROGRAM WHEREAS, City of Dubuque (hereinafter called "Applicant "), County of Dubuque, has made application through the Iowa Homeland Security and Emergency Management Division (HSEMD) for funding from the Flood Mitigation Program in the amount of $200,929,536 for the total project cost. THEREFORE, the Applicant agrees to provide and make available up to $76,678,802 (seventy -six Million, six hundred seventy -eight thousand, eight hundred two dollars) of local monies to be used to meet the match requirement for this flood mitigation project application. The resolution was passed and approved the 18th day of November, 2013. Signatures of Council or Board Members: te.4f Roy D. uol, Mayor Connors, Council Member Kevin J. Lynch, ' ouncil Member n V. Sutton, Council Member 0 K g, ouncil M ber ar a A. Braig, Ric W. J -•' s, Council Member David T. Resnick, Council Member / Attest evin S. Fi'rns ah, City Clerk I submit this form for inclusion with the Flood Mitigation Project Application. Michael C. Van Milligen, City Manager (Print Name of Authorized Representative) (Autl ed Representative Signatur and ate) Iowa Homeland Security & Emergency Management 7105 NW 70th Avenue Camp Dodge, Bldg W -4 Johnston, IA 50131 Iowa Flood Mitigation Program (FMP) Flood Mitigation Project Application What is the Iowa Flood Mitigation Program? Authorized under the Flood Mitigation Bill, (Senate File 2217) the Flood Mitigation Program is funded by the Flood Mitigation Fund or the use of Sales Tax Revenues to provide funding to governmental entities to implement long -term flood mitigation projects. Eligibility: 1) An eligible applicant is a governmental entity as defined under the Code of Iowa section 418.1, subsection 4. 2) Eligible project types include construction and reconstruction of levees, embankments, impounding reservoirs, conduits or other means that are necessary for the protection from the effects of floodwaters and may include the deepening, widening, alteration, change, diversion, or other improvement of watercourses if necessary for the protection of such property from the effects of flood waters. A project may consist of one or more phases of construction or reconstruction that are contracted for separately if the larger project is a part, otherwise meets the requirements under the Code of Iowa section 418.1, subsection 5. 3) For the project to be eligible for sales tax increment funding it is required to have been approved to receive federal financial assistance under the Water Resources Development Act (WRDA), Environmental Protection Agency (EPA), or other federal program providing assistance specifically for hazard mitigation. The federal award must be in an amount equal to at least twenty percent (20 %) of the total project cost or thirty million dollars ($30,000,000), whichever is less. Code of Iowa section 418.4, subsection 3b. 4) For the project to be eligible for flood mitigation funding or sales tax increment funding, the governmental entity shall provide a local match of at least fifty percent (50 %) of the total cost of the project less any federal financial assistance. Code of Iowa section 418.9, subsection 2d. The sales tax increment shall fund a maximum of 50% of the total project cost. The federal share of the total project cost shall be a minimum of 20% of the total project cost or $30 million, whichever is less. The local match, when combined with the federal share, shall fund a minimum of 50% of the total project cost. The governmental entity shall provide funding for the local match. For example: Federal share: $ 20 (meets the minimum of 20 percent of the total project cost) Local match: $ 30 (federal plus local meets the mimimum of 50% of project total) Sales tax increment: $ 50 (meets the maximum of 50% of the total project cost) Total project cost: $ 100 5) The project must result in nonpublic investment in the governmental entity's area as defined in Code of Iowa section 418.11, subsection 3, of an amount equal to fifty percent (50 %) of the total cost of the project. For purposes of this paragraph, "nonpublic investment" means investment by nonpublic entities consisting of capital investment or infrastructure improvements occurring in anticipation of or as a result of the project during the period of time between July 1, 2008, and ten years after the board approves the project. Code of Iowa section 418.9, subsection 2d. Flood Mitigation Project Application Project Application Tab A, Page 1 6) Projects are not eligible if: (Code of Iowa section 418.4, subsection 4) a) Entity previously had a project approved under the Iowa Flood Mitigation Program pursuant to Code of Iowa section 418.9 or b) Refinancing an existing project or pay principal and interest expense of previous obligations. c) Project is eligible for state financial assistance in the Hazard Mitigation Grant Program or Public Assistance Program as a result of a presidential disaster declaration (Iowa section 29C.6, subsection 17. Code of Iowa section 418.4, subsection 5.) Application Process: This application is designed to capture the necessary information to meet program requirements. 1) A governmental entity shall submit a completed application to Iowa Homeland Security and Emergency Management to be submitted to the Flood Mitigation Board for approval of the project prior to January 1, 2016. 2) Governmental entity shall attach to the application a project plan adopted under Code of Iowa section 418.4, subsection 2. See Tab B - Project Plan 3) The application shall specify whether the governmental entity is requesting financial assistance from the flood mitigation fund or approval for the use of sales tax revenues, but not both. a) Applications for financial assistance from the flood mitigation fund shall describe the type and amount of assistance requested. b) Applications for the use of sales tax revenues shall state the amount of sales tax revenues necessary for completion of the project and shall contain a report from the Iowa Department of Revenue, as requested by the governmental entity, that provides recent historical data on sales tax revenue and trends in sales tax revenue growth. 4) Project Applications must be completed in this MS Excel format and emailed to: hsemd.mitigation @iowa.gov. Save as "Applicant Name FMP Type of Project" Your State Mitigation Project Officer will work with you to ensure your application is complete, which may require multiple revisions. When you and your State Mitigation Project Officer deem your application packet to be complete, mail 2 paper copies of the final application packet and all required attachments and supporting documentation, to: Iowa Homeland Security and Emergency Management (HSEMD) Attn: Mitigation Section 7900 Hickman Rd Ste 500 Windsor Heights, Iowa 50324 Flood Mitigation Board Process: 1) Review the application and adopted project plan. 2) Consult with the Iowa Economic Development Authority. 3) Approve, defer, or deny the application under the Code of Iowa section 418.9. Flood Mitigation Project Application Project Application Tab A, Page 2 11 -13 -13 Iowa Flood Mitigation Program (FMP) Flood Mitigation Project Application A. Applicant /Community Name B. Address City, State, Zip Code u °= 50 West 13th Street Dubuque, IA 5 20 01 -480 5 C. Point of Contact (POC) Name for Project POC Title POC Agency POC Email Deron Muehring I Civil Engineer City of Dubuque II dmuehrinQcityofdubuque.orq ■ Code lirPOC PO Box and Zip POC Street Address Alt POC Agency POC City, State, Zip Code Teri Goodmann POC Phone 52001 -4805 50 West 13th St II Dubuque, IA 52001 -4805 ■ 563 - 589 -4276 Alternate POC Name or Authorized Representative Alt POC Title Alt POC Agency Alternate POC Email Teri Goodmann Asst City Manager City of Dubuque tgoodmantacityofdubuque.orq 130,593,792 Alt POC PO Box and Zip Code Alt POC Street Address Alt POC City, State, Zip Code Alt POC Phone 52001 -4805 50 West 13th St Dubuque, IA 52001 -4805 563- 690 -6060 D. Federal Tax ID # / FEIN E. County Name F. US Congressional Districts] State Legislative Districts Senate House 42- 6004596 1 Dubuque 1 50 99 G. Is the Applicant /Community participating in the National Flood Insurance Program (NFIP)? Community's CID Number YES 195180 A. Identify the requested funding source: B. Project Budget Summary Sales Tax Increment Engineering /Contractual Services $ 17,817,601 Property Acquisition & Easement $ 19,301,143 Construction $ 130,593,792 Contingency $ 11,337,000 Financing Interest $ 17,430,000 Financing Reserve $ 4,450,000 Total Project Budget Summary $ 200,929,536 Flood Mitigation Project Application Project Application Tab A, Page 3 11 -14 -13 C. Project Funding Source Identify all anticipated funding sources for the project and the amounts. Code oflowa, section 418.4, subsection 2 State that you have applied for and /or received approved federal financial assistance. Code oflowa 418.4, subsection 3b. Please insert additional rows as needed. Identify source Applied/ Received Federal $ Local $ Sales Tax Increment Table Adjustment TOTAL Federal: U.S. EPA Clean Water SRF Received $ 7,766,500 $ 7,766,500 Federal: U.S. EPA Clean Water SRF Received $ 1,827,000 $ 1,827,000 Federal: U.S. EPA Clean Water SRF Received $ 9,416,795 $ 9,416,795 Federal: U.S. EPA Clean Water SRF Received $ 1,187,757 $ 1,187,757 Federal: U.S. EPA Clean Water SRF Received $ 28,823,000 $ 28,823,000 Federal: U.S. EDA Disaster Relief Grant Received $ 1,227,138 $ 1,227,138 Non - Federal: U.S. DOT TIGER Grant $ 5,600,000 $ 5,600,000 Non - Federal: I -Jobs II Grant $ 3,965,500 $ 3,965,500 Non - Federal: RECAT Grant $ 2,250,000 $ 2,250,000 Non - Federal: U.S. DOT National Scenic Byways Grant $ 1,000,000 ■ $ 1,000,000 Non - Federal: State Recreational Trail Grant $ 100,000 $ 100,000 Non - Federal: DMATS $ 640,000 111 $ 640,000 Non - Federal: General Obligation Bonds $ 48,227,604 $ 48,227,604 Non - Federal: Private Donations $ 165,244 $ 165,244 Non - Federal: Sale of Assets and Land $ 336,358 1 $ 336,358 Non - Federal: Stormwater Utility Fees $ 14,394,096 1 $ 14,394,096 Federal: U.S. EPA Clean Water SRF (repayment) $ 24,491,634 $ 24,491,634 Non - Federal: Sales Tax Increment I __■ 74,002,544 $ 74,002,544 Table adjustment for SRF payoff $ (24,491,634) $ (24,491,634) Total Project Funding Source $ 50,248,190 $ 76,678,802 $ 98,494,178 $ (24,491,634) $ 200,929,536 % of Total Cost 22.29% 34.02% * - See the Bee Branch Watershed Flood Mitigation Plan, Section C for detailed description of project financing. 43.69% Flood Mitigation Project Application Project Application 100% Tab A, Page 4 A. Provide a brief description of the project. Identify separately each component of construction or reconstruction included in the project. This is a summary of Tab B - Project Plan. Code oflowa section 418.4, subsection 2 The Bee Branch Watershed Flood Mitigation Project is a multi- phased approach to address the severe and frequent flash flooding experienced in the Bee Branch Watershed in the City of Dubuque. As outlined in the Drainage Basin Master Plan, the engineering report by HDR Engineering (Omaha, NE), the improvements associated with the Bee Branch Watershed Flood Mitigation Project will mitigate the flooding experienced over the past twelve years in four ways: reduce the volume of floodwaters, reduce the flow of floodwaters, increase floodwater conveyance capacity through watershed, and providing barriers between critical facilities and floodwaters. This multi- faceted, holistic approach includes the following phases: Phase Description 1 Carter Road Detention Basin 2 West 32nd Street Detention Basin 3 Historic Millwork District 4 Lower Bee Branch Creek Restoration 5 Flood Mitigation Gate Replacement 6 Impervious Surface Reduction 7 Upper Bee Branch Creek Restoration 8 22nd Street Storm Sewer Improvements 9 Flood Mitigation Maintenance Facility 10 North End Storm Sewer Improvements 11 Water Plant Flood Protection 12 17th Street Storm Sewer Improvements See the Bee Branch Watershed Flood Mitigation Project Plan, Section B for a detailed description of each phase. B. How will the project mitigate future flooding of property that has sustained significant flood damage and is likely to sustain significant flood damage in the future? Code oflowa, section 418.9, subsection 10, 2a Explain: Dubuque County has received 6 flood - related Presidential Disaster Declarations since 1999 that directly impacted the Bee Branch Watershed. Flood events today impact 1,301 residential households occupied by 3,190 residents and 72 businesses including their 1,669 employees. These flood events cause flooded basements necessitating the replacement of furnaces, water heaters, electrical equipment, wall and floor coverings. The wastewater utility is lost for varying periods of time. Street closures occur. Families suffer mental anguish with every storm event, regardless of the severity. Residents miss work in larger storm events. Businesses experience property damages similar to residences. Business disruptions result in lost revenues as a result of closures due to flooding; be it streets, property damages, lack of employees, and fear of customers to go into the flooded area for days following a storm event. In total, the estimated damages incurred due to the six disasters since 1999 total an estimated $69.8 million. The Bee Branch Watershed Flood Mitigation Project will prevent an estimated $582 million in damages over its design life. See the Bee Branch Watershed Flood Mitigation Project Plan, Section E. IC. How does the project address the impact of flooding both upstream and downstream from the project area? Code oflowa, section I 4189, subsection 10, 26 Explain: The project improvements are based on a watershed approach with improvements throughout the watershed that will provide benefits to properties upstream and downstream of the flood -prone area. The benefit of reduced floodwater flow provided by upstream detention will be realized by the properties within the flood prone area as well as all of the properties along the Bee Branch Creek between the flood prone area and the detention basins. The pervious pavement systems will benefit downstream properties by reducing the floodwater volume that will flow to the Mississippi River. The increased conveyance through the flood prone area realized as a result of the Bee Branch Creek Restoration has a positive impact on downstream properties. The restored natural creek and floodplain area will result in reduced runoff volumes and slow the discharge of floodwaters downstream in contrast to a concrete lined channel or the existing underground storm sewer that are designed to rapidly convey floodwaters downstream as quickly as possible. While the Bee Branch Watershed Flood Mitigation Project involves improvements to the floodwall /levee system gate through which floodwaters from the Bee Branch Watershed will flow into the Mississippi River, the size of the culverts and the pumps will not change. As a result of this project, the peak flow of floodwaters from the Bee Branch Watershed into the Mississippi River will not increase and the volume of floodwaters will actually be decreased. The project will also benefit downstream properties through the reduction of sediment loads, fertilizer, road surface chemicals, etc. See the Bee Branch Watershed Flood Mitigation Project Plan, Section F. Flood Mitigation Project Application Project Application Tab A, Page 5 D. Describe how the project conforms to any applicable floodplain ordinance and identify the ordinance. Code of Iowa, section 418.9, subsection 10, 2b Ordinance 27 -13 was adopted by the Dubuque City Council on May 20, 2013 and is the current Dubuque Floodplain Ordinance. The previous phases of the Bee Branch Creek Watershed Flood Mitigation Project that have been completed or are currently under development have been done in conformance with the City's Floodplain Management Ordinance that was in effect at the time of the improvements. In addition, Floodplain Development Permits were also obtained from the Iowa Department of Natural Resources when applicable. See the Bee Branch Watershed Flood Mitigation Project Plan, Section G. E. Describe how the project is sufficiently valuable to the economic viability of the state or is of sufficient historic value. Code of Iowa, section 418.9, subsection 10, 2c Economic Viability Based on information from ReferenceUSA®, a leading provider of business and consumer research, there are 72 businesses located within the proposed flood plain limits that combined employ over 1,400 people with annual sales over $500 million. As can be expected, the repeated flood losses have impacted businesses and depressed property values. From 2004 to 2009 the assessed value of all residential property in the City grew by 21 %. During that same period, the assessed value of the residential property in the flood prone area grew by only 14 %. During the same time period, the assessed value of all commercial property in the City grew by 39% while the assessed value of the commercial property in the flood prone area actually decreased by 6 %. The efforts to address the flash flooding has already spurred private investment and reinvestment. Because of the public support for the Bee Branch Watershed Flood Mitigation Project, the stated commitment of the City of Dubuque City Council to implement the various phases of the project, and because the City has already started implementing the improvements, non - public investment has already eclipsed $139 million since 2008 with an additional $215 million expected to follow in the next five years for a combined total of $354 million in non - public investment. See the Bee Branch Watershed Project Plan, Section D. Historic Value The Bee Branch Watershed Flood Mitigation Project will help retain two of the oldest historic neighborhoods in the State. Dubuque is the oldest incorporated City in Iowa, founded in 1833. The housing and businesses in the Bee Branch Watershed flood prone area include the Old Town Residential Historic District comprised of 316 buildings and the Washington and East 22nd Street Historic District comprised of 31 buildings. These oldest documented buildings date back to the early 1830s. Based on information from the City Assessor's Office, eighty -five percent (85 %) of the impacted properties have buildings that are potentially eligible for listing on the National Register of Historic Places, the official list of the Nation's historic places worthy of preservation. The Bee Branch Creek flowed through this area. See the Bee Branch Watershed Flood Mitigation Project Plan, Section H. F. How is this project essential to meet the necessary expenses or serious needs of the governmental entity related to the flood Litigation? Code of Iowa, section 418.9, subsection 10, 2h Explain: Of the more than thirty (30) stormwater utilities across Iowa, Dubuque residents and businesses currently pay the second highest rate in the state. Dubuque's rate is sixty three percent (63 %) higher than the average community in Iowa. The annual Stormwater Utility Fee payment would need to increase by 248% to construct the Bee Branch Watershed Flood Mitigation Project without State Flood Mitigation Funding which would result in significant and detrimental impacts to citizens, businesses and economic development. See the Bee Branch Watershed Flood Mitigation Project Plan, Sections D, F and H for more detail. IG. Provide the extent of nonfinancial support committed to the project from public and nonpublic sources. Code of Iowa, section 418.9, I subsection 10, 2e Dubuque residents as well as the City of Dubuque and the consultants have worked hard to come up with solutions throughout the Bee Branch Watershed to address the flooding problems and to make the project acceptable to the community and in particular those impacted by the restoration of the Bee Branch Creek to its daylight status. The plan has been developed with input from citizens and private organizations every step of the way. A 26- member Citizen Advisory Committee helped establish the City's stormwater utility which is being utilized to provide local financial support for the project. The Stormwater Utility fee was established in 2003. Another citizen advisory committee, the Bee Branch Citizen Advisory Committee worked with the City's consulting engineer to establish the location, look, and functionality of improvements. The committee also helped with the exchange of information about the improvements with other citizens and the City Council. In 2004 the Bee Branch Creek Alignment Study was completed. Public workshops were held to gather additional citizen input on the final design of the Bee Branch Creek Restoration. The public was asked to identify their hopes and fears and provide input on various potential landscape features, bridges, and secondary uses. Based on that input, conceptual drawings were presented to the public. The project has proceeded with wide public support. The City worked hard to serve the people displaced by the project. Paying strict adherence to the Federal Uniform Relocation Act, the City has been able to acquire over 100 properties for the Bee Branch Watershed Flood Mitigation Project without ever completing condemnation. Local nonfinancial support is demonstrated for the Bee Branch Watershed Flood Mitigation Project through the letters of support from local civic organizations. See the Bee Branch Watershed Flood Mitigation Project Plan, Section I for more detail on nonfinanical support of the project. Flood Mitigation Project Application Project Application Tab A, Page 6 IH. Describe the coordination with other watershed management measures as applicable. Code of Iowa, section 418.9, subsection 10, 2f I The improvements associated with the Bee Branch Watershed Flood Mitigation Project are consistent with the improvements outlined in the Drainage Basin Master Plan which was developed to ensure that efforts to solve flooding problems within the watershed are efficient, cost - effective and address the flooding in a manner that does not create flooding issues elsewhere in the watershed. Even though the Bee Branch Watershed is completely contained within the jurisdictional boundary (Corporate Limits) of the City of Dubuque, the City of Dubuque has collaborated and fostered partnerships with Dubuque County, state agencies (Iowa Department of Natural Resource and Iowa Department of Agriculture and Land Stewardship), and federal agencies (U.S. Environmental Protection Agency, U.S. Economic Development Administration, and U.S. Department of Transportation). The City has also partnered with fifty seven (57) other communities up and down the Mississippi River as part of the Mississippi River Cities & Towns Initiative. The City of Dubuque is also represented on the Steering Committee of the America's Watershed Initiative. This initiative is a collaboration that seeks solutions for meeting the multiple demands placed on the vast and complex Mississippi watershed system by integrating issues, partners and ideas at the full watershed scale and supports the effective resolution of issues that span multiple regions— issues including energy, transportation, water quality and floodplain management. See the Bee Branch Watershed Flood Mitigation Project Plan, Section J. II. Describe how this project is consistent with applicable comprehensive, countywide emergency operations plan in effect and other I applicable local hazard mitigation plans. Code of Iowa, section 418.9, subsection 10, 2g The Dubuque County Multi - Jurisdictional Hazard Mitigation (MJHM) Plan, which includes Dubuque County and all of its incorporated cities, was approved by FEMA on May 7, 2013. The MJHM Plan is incorporated into the Dubuque Countywide Emergency Operations Plan. The Dubuque Countywide Emergency Operations Plan was adopted by the Dubuque County Emergency Management Commission and approved by the Iowa Homeland Security and Emergency Management in July 2013. The MJMH Plan mitigates the impacts of various disasters that could adversely affect the health, safety and /or general welfare of its citizens. The improvements associated with the Bee Branch Watershed Flood Mitigation Project are in conformance with the MJHM Plan as outlined below: 1. The MJHM Plan identifies flash flooding as the highest ranked hazard for the City of Dubuque. See page #52 of the MJHM Plan. 2. The MJHM Plan discusses improvements associated with the Bee Branch Watershed Flood Mitigation Project stating that "localized street flooding and basement flooding experienced in the North End of Dubuque ... is the focus of drainage basin improvements like the Bee Branch Creek (Watershed) Restoration Project. This multi -year project replaces an underground storm sewer with an open waterway and other public amenities, reducing the risk of flood damage to 1,150 properties ... in some of Dubuque's oldest neighborhoods. See page #26 of the MJHM Plan. 3. The MJHM Plan identifies the "(restoration) of the Bee Branch Creek with open channel from the 24th St. neighborhood to East 16th Street retention basin, including the acquisition of approximately 70 homes and businesses" as a top ranked mitigation action. See page #125 of the MJHM Plan. 4. The MJHM Plan identifies the "(implementation) of the storm water management and flood control improvements outlined in the Drainage Basin Master Plan" as a top ranked mitigation action. See page #126 of the MJHM Plan. Please see the Bee Branch Watershed Flood Mitigation Project Plan, Section L and Appendix B. 1 J Description of Project Location (i.e. Latitude and Longitude (minimum 6 digits after the decimal), Neighborhood, Subdivision, Geographic Boundaries, Driving Directions, etc.) The project improvements are located throughout the Bee Branch Watershed as detailed in Bee Branch Flood Mitigation Project Plan, Section B. See Bee Branch Flood Mitigation Project Plan, Appendix C - Project Area Map for latitude and longitude coordinates of each phase of the project. K. Number of people and properties protected as a result of the completion of the entire proposed project: # of People # of Residential Properties # of Commercial Properties # of Public Properties # of Critical Facilities Total # of Properties: 3,190 1,301 72 5 9 1,387 Flood Mitigation Project Application Project Application Tab A, Page 7 11 -13 -13 A. List the major milestones for this project. Task Months /Years from Award Responsible Party Start * Complete * Receive Grant Agreement from HSEMD 0 2 HSEMD, City Carter Road Detention Basin 0 0 City, Consulting Engineer, Construction Contractor W. 32nd Street Detention Basin 0 0 City, Consulting Engineer, Construction Contractor Historic Millwork District 0 0 City, Consulting Engineer, Construction Contractor Lower Bee Branch Creek Restoration 0 18 City, Consulting Engineer, Construction Contractor Flood Mitigation Gate Replacement 6 18 City, Consulting Engineer, Construction Contractor Impervious Surface Reduction 0 240 City, Consulting Engineer, Construction Contractor Upper Bee Branch Creek Restoration 0 36 City, Consulting Engineer, Construction Contractor 22nd St. Storm Sewer Impr. 66 78 City, Consulting Engineer, Construction Contractor Flood Mitigation Maint. Facility 42 78 City, Consulting Engineer, Construction Contractor North End Storm Sewer Impr. 18 48 City, Consulting Engineer, Construction Contractor Water Plant Flood Control 66 78 City, Consulting Engineer, Construction Contractor 17th St. Storm Sewer Impr. 66 84 City, Consulting Engineer, Construction Contractor Project Closeout Activites ) 240 246 j City, HSEMD Total Project Duration: 246 months * - The dates provided above are estimated major milestones associated with this project. The milestone dates may be adjusted forward or backward if necessary due to changes in financing costs, sales tax increment funds available, construction timelines and costs and other factors. The City will report changes, if applicable, to the Flood Mitigation Board in its annual reporting. Flood Mitigation Project Application Project Application Tab A, Page 8 O U To the best of my knowledge and belief, l certify that all data In this application packet Is complete, true and correct. The governing body of the applicant has duly authorized this document and hereby applies for assistance as documented In this application. The applicant understands that the project shall not proceed until Flood Mitigation I3oard approval Is granted. Sig )f(ilure of the Chief Executive Officer Roy 0. 8uol Name of the Chief Executive Officer Mayor Slgna un• o1 th,• Aulhorizrd Itrprrarn I.itiv' Michael C. Van MlllIgcn Name of Authorized itepresentative City Manager Title 'Title City of Dubuque Organization /7••f3 Date 563 -589 -4110 City of Dubuque Orl;aulzaliun Date 50 West 13th Street Phone Number 1'0 box / Street Address Dubuque, IA 52001 City, State and Zip Code 563- 589 -4110 Phone' Number ctymgr@cityofdubuque.org Email Address Flood Mitigation Project Application Project Application Tab A, Page 9 STATE OF IOWA DESIGNATION OF APPLICANT'S AUTHORIZED REPRESENTATIVE Jennifer M. Larson is hereby authorized to execute on behalf of City of Dubuque this mitigation project and to file it with Iowa Homeland Security and Emergency Management (HSEMD) for the purpose of obtaining financial assistance under the Flood Mitigation Bill, Senate File 2217. Signed: (Date) Rov D. Buol, Mayor Chief Executive Officer (Print Name and Title) (Signature) Jennifer M. Larson, Budget Director Applicant's Authorized Representative (Print Name and Title) (Signature) Attested: Kevin S. Firnstahl, Citv Clerk (Print Name and Title) (Signature) STATE OF IOWA DESIGNATION OF APPLICANT'S AUTHORIZED REPRESENTATIVE Michael C. Van Milligen is hereby authorized to execute on behalf of City of Dubuque this mitigation project and to file it with Iowa Homeland Security and Emergency Management (HSEMD) for the purpose of obtaining financial assistance under the Flood Mitigation Bill, Senate File 2217. Signed: (Date) Rov D. Buol, Mayor Chief Executive Officer (Print Name and Title) (Signature) Michael C. Van Milligen, Citv Manager Applicant's Authorized Representative (Print Name and Title) (Signature) Attested: Kevin S. Firnstahl, Citv Clerk (Print Name and Title) (Signature) ORDINANCE NO. 21 -12 AMENDING CITY OF DUBUQUE CODE OF ORDINANCES SECTION 13 -4 -5 (D) SFU RATE, CHARGES; UTILITY REVENUES. NOW, THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That City of Dubuque Code of Ordinances Section 13 -4 -5 (D) is amended to read as follows: (d) The SFU rate to be applied to residential and nonresidential properties shall be as follows: (1) For the period July 1, 2012 through June 30, 2013 the SFU rate shall be $7.00 per SFU; (2) For the period July 1, 2013 through June 30, 2014 the SFU rate shall be $7.50 per SFU; (3) For the period July 1, 2014 through June 30, 2015 the SFU rate shall be $8.00 per SFU. (4) For the period July 1, 2015 through June 30, 2016 the SFU rate shall be $8.50 per SFU. (5) For the period July 1, 2016 through June 30, 2033 the SFU rate shall be $9.00 per SFU. Passed, approved and adopted this 7th day of Attest: Kevin Firnstah March 2012. D. Boul, Mayor t(u\kta -fu Ott/ (30/,(t-/ cArvi-v-ika Pit6li`er DUBUQUE CITY COUNCIL MAYOR Roy D. Buol 2640 Becker Ct. Dubuque, Iowa 52001 Phone: (563) 564 -5455 rdbuol @cdyofdu buqu e. org Term Expires: Dec. 31. 2017 AT -LARGE Ric W. Jones 1270 Dunleith Ct. Dubuque, Iowa 52003 Phone: (563) 556 -3490 riones@cityordubuque.org Term Expires: Dec. 31, 2017 AT -LARGE David T. Resnick 375 Alpine St. Dubuque. Iowa 52001 Phone: (563) 582 -9217 dresnick@cityotdubuque.org Term Expires: Dec. 31, 2015 FIRST WARD Kevin J. Lynch 749 Brookview Sq. Dubuque, Iowa 52002 Phone: (563) 582 -2655 klynch @cityofdubuque.org Term Expires: Dec. 31. 2017 SECOND WARD Karla A. Braig 1795 bras Blvd. Dubuque. Iowa 52001 Phone: (563) 582 -0595 kbraig @cityoldubuque.org Term Expires: Dec. 31, 2015 THIRD WARD Joyce E. Connors 660 Edith St. Dubuque, Iowa 52001 Phone: (563) 582 -3843 jconnors@cityofdubuque.org Term Expires: Dec. 31. 2017 FOURTH WARD Lynn V. Sutton 876 Yale CI, #1 Dubuque, Iowa 52001 Phone: (563) 585 -0129 Isutton@cityofdubuque.org Term Expires: Dec. 31. 2015 CITY COUNCIL MEETINGS The Dubuque City Council meets on the first and third Monday of each month in the City Council Chambers on the second floor of the Historic Federal Building at 350 West Sixth Street. Meetings begin at 6:30 p.m. and are broadcast live on CityChannel, Dubuque's local government access channel (85.2 digital, 8 analog) on the Mediacom cable system. Meetings are also streamed live and archived on the City website, www.cityofdubuque.org /media. For agenda and minutes information, visit www.cityofdubuque. org /citycouncil or contact the City Clerk's Office at (563)589 -4120 or cityclerk @cityofdubuque.org. CITY COUNCIL OtliA iJ T �ilj y tl•� �. Each year, the Dubuque City Council completes its annual goal - setting sessions. Over the course of two days in August, City Council members reaffirmed the 15 -year vision statement, mission statement, and developed priorities for a 2013 -2015 policy agenda. 2028 VISION STATEMENT The city of Dubuque is a progressive, sustainable city with a strong diversified economy and expanding global connections. The Dubuque community is an inclusive community celebrating culture and heritage and has actively preserved our Masterpiece on the Mississippi. Dubuque citizens experience healthy living and retirement through quality, livable neighborhoods with an abundance of fun things to do; and are engaged in the community, achieving goals through partnerships. Dubuque City government is financially sound and is providing services with citizens getting value for their tax dollar. CITY MISSION STATEMENT The City's mission is to deliver excellent municipal services that support urban living and a sustainable city plan for the community's future and facilitate access to critical human services which result in financially sound government and citizens getting services and value for their tax dollar. FIVE -YEAR COMMUNITY GOALS FOR A SUSTAINABLE DUBUQUE • Economic Prosperity • Social /Cultural Vibrancy • Environmental Integrity FIVE -YEAR CITY GOALS • Planned and Managed Growth • Partnering for a Better Dubuque • Improved Connectivity — Transportation and Telecommunications FIVE -YEAR ORGANIZATIONAL GOAL • Financially Responsible City Government and High Performance Organization POLICY AGENDA 2013 -2015 Top Priorities (in alphabetical order) • Annexation: Direction on specific actions a) study implementation, b) corridor to Airport • Arts and Culture organizations city support: Evaluation, potential projects review and priority, overall direction, funding level • Dubuque welcoming, inclusive community: Action plan • Four Mounds Foundation /HEART program city support • Management and Employee Succession Planning and Funding • Master Plan for Chaplain Schmitt Island: Development • Safe Community Initiative: Monitoring, future direction, specific actions • Washington Neighborhood Strategy: Business attraction, HEART program, update housing stock, homeownership, promotion, police substation High Priorities (in alphabetical order) • Bee Branch Project: Specific projects, direction, funding • Clean Air Attainment Strategy • Greater Dubuque Development Corporation support • Historic Millwork District: Development, project monitoring • Indoor Aquatic Center: Direction • Riverfront Leases: Agreement • Smarter City: Smarter health and wellness, smarter travel, smarter discards • Southwest Arterial Project: Design, land acquisition, intersecting roads MANAGEMENT AGENDA 2013 -2015 Economic Prosperity Goal • Dubuque Initiatives: Next Step • Workforce Market -Rate Housing • Marina Store: Operational • Project HOPE Environmental /Ecological Integrity Goal • Sustainability Purchasing Policy and Procedures • Automatic Vehicle Location (AVL) for Transit • Grand River Center Electric Meters Project • City Operations: Sustainability Performance Measures • Sustainable Dubuque Community Grant • America's River III Task Force • Plastic Bag Reduction Strategy: Implementation • Fats /Oils /Grease: Policy, Program and Enforcement • Dubuque Metropolitan Area Solid Waste Agency (DMASWA) 28E Agreement: Evaluation • Community Climate Action & Resiliency Plan - 50% Greenhouse Gas Reduction by 2030: Implementation Social /Cultural Vibrancy Goal • City Workforce Diversity: Recruitment and Selection • Territory Accountability Design: Targeted Actions • Multicultural Family Center Building Expansion • Intercultural Competency Program within City Government: Self Assessment, Training • Intercultural Competency Program for the Community: Marketing to School District, Nonprofit and. Community Organizations, Businesses • Police /Race Dialog • City Life: Implementation • Local ADA Compliance Program • Leadership Enrichment After School Program (LEAP) • Firefighter Internship for Recruitment of Diverse Workforce • Racial Profiling: Problem Analysis, Action Plan • Community Engagement Strategy: City Actions Planned & Managed Growth Goal • Inflow and Infiltration Program /Home Inspections: EPA Consent Decree Implementation • City Comprehensive Plan: Update • Flood Wall: Funding, Evaluation, Cell Protection • Statewide Urban Design and Specification City Engineering Standards (SUDAS) City Engineering Standards: Update • Washington Street Row House Units: Sale • Historic Preservation Program: Evaluation, Update • Downtown Loan Program: Implementation • West Third Street Reservoir Study • Housing Choice Voucher Program • Water and Sewer Service Extension to City Residents and Businesses THE CITY OF Dubuque DUB E 1111• E1 Masterpiece on the Mississippi m,,.,,,.x„ For more information, call 563.589.4120 or visit www.cityofdubuque.org /councilgoals Partnering for a Better Dubuque Goal • Parks /Schools Joint Projects and Services: City Actions • City Volunteer Program: Development • Sister City Program: Delegation to Potential City • Veterans Memorials: Direction • Handicap Accessibility for Parks: Direction • Bridges Out of Poverty Program: City Support fif3 Improved Connectivity: Transportation and Telecommunications • Smart Transportation Program • Traffic Signal Synchronization: Citywide • Amtrak Train Platform (Port of Dubuque): Funding • Roundabout: ROW Acquisition a) University /Asbury b) Radford /Pennsylvania • Intermodal Transportation Facility in Historic Millwork District • Air Traffic Control Tower: Funding Financially Responsible City Government and High Performance Organization • Website Content Management (CivicPlus) • 900 MHz Data System: Expansion • Employee Wellness Program: Five -Year Goals, City Internet Posting • Employee Involvement Teams: Expansion • Healthcare Cost Containment • Police Officer Recruitment and Retention • Records Management and Retention • City Hall Protocol and Safety • New Computer -Aided Drafting (CAD) Software • Emergency Police Dispatch and Emergency Fire Dispatch • New Fire Pumper • Disaster Preparedness and Recovery Plan: Discussion • Environmental Sustainability Management System (ESMS): ISO 14001 Model Program • Affordable Care Act: Analysis of Impacts Major Projects • State Revolving Fund (SRF) Green Alley Projects • Port of Dubuque Park: Development • City Greenhouse Project • Water & Resource Recovery Center Project • Locust and Iowa Ramps: Renovation Project • North Softening Basin Renovation Project • Comiskey Park Improvements • Northwest Arterial Trail — Bergfeld Recreation Trail Connection • Bunker Hill Golf Course Irrigation Improvements • Airport Terminal Project • Elm Street Reconstruction Project • One Way — Two Way Conversion Project • Cedar Cross Road: Design • Wacker and JFK Traffic Signalization Project • North Cascade Road: Design • White Street Traffic Signal and Improvements Reconstruction (at 14th and 20th) • US 20 /Fremont Avenue Traffic Signal: Upgrades • NW Arterial/Chavenelle Intersection Improvement Project Rev. 11/13 FAQs What is the Iowa Flood Mitigation Program and what is the source of the $98 million? Authorized under the Flood Mitigation Bill in 2012, the Flood Mitigation Program is administered by the Iowa Department of Homeland Security on a competitive basis by a citizen board that began accepting applications in November 2013. It is funded by a portion of state sales tax revenues. The program provides funding to cities and counties to implement long -term flood mitigation projects. Specifically, the funds are an annual sales tax increment, or a percentage of the increase in state sales tax revenue generated within the city or county. How will the Bee Branch Watershed Project impact stormwater utility fees? Dubuque's current rate is $5.60 per month for the average single - family home in Dubuque. (Properties that are exempt from property taxes, such as non- profits, only pay 50% of the stormwater fee, as do low- income individuals. Farms within the city receive a 75% discount.) Due to the costs associated with maintaining the current stormwater management system and implementing the Bee Branch Watershed Project over the next 20 years, the City is projecting annual increases to the stormwater utility rate to reach $9.00 per month on July 1, 2021. Prior to the state grant program, the rate was projected to rise to $9.00 per month on July 1, 2016, and the improvements would have taken 50 years or more. With the state grant, they will be completed in 20 years with most completed over the next six years. What is the difference between the Bee Branch Watershed Project and the Bee Branch Creek Restoration? The Bee Branch Watershed Project is a 12- phase, 20 -year construction project to address stormwater management issues throughout the entire Bee Branch Watershed area, which approximately stretches from the Mississippi River west past John F. Kennedy Road, north to the Northwest Arterial, and south to West Fifth Street. The Bee Branch Creek Restoration is two of the phases of the watershed project and is scheduled to be completed in 2016. For more information on the Bee Branch Watershed Project, visit www.cityofdubuque.org/beebranch or call 563.589.4210. W. Locust Street - Alleys scheduled for reconstruction Phase 6, "Impervious Surface Reduction," will involve the reconstruction of 240 alleys within the watershed. These alleys will be converted to be pervious surfaces (pavers) to allow stormwater to filter back into the ground instead of creating run -off to surrounding properties and downstream in the watershed. Approximately 70 alleys will be completed in the first three years of the project, with the remainder completed over the next 11 years. (Abutting property owners will be assessed for a portion of these costs. The average paving assessment portion is estimated to be $800 per residential property. These assessments can be paid over 15 years at an estimated 3% interest. Financial assistance is available for income - qualified, owner - occupied properties.) before Masterpiece on the Mississippi BEE BRANC ERS ED FLOOD MITIGATIONROJEC A multi - phased, fiscally responsible investment to mitigate flooding, improve water quality, stimulate investment, and enhance quality of life within the Bee Branch Watershed. Imagine waiting out a tornado warning with your family in the safety of your basement when, suddenly, heavy rains produce flash flooding and water starts pouring into the basement around you. Do you continue to seek shelter from the tornado in your basement at the risk of electrocution, fire or drowning or go upstairs and risk the tornado? Bee Branch Watershed residents have faced this difficult decision. DRAFT 11 - NOV. 18 The Bee Branch Watershed area encompasses historic neighborhoods offering some of the community's most affordable workforce housing. This area is also hit the hardest with flash flooding during significant rain events and it is NOT "just a little water in the basement." Too frequently, it is flooding that inundates water heaters, furnaces, and electrical boxes, and can cause fires; it rushes down streets from curb to curb -- stalling vehicles, stranding motorists, displacing manhole covers, and damaging pavement and other public infrastructure like water mains and stormwater and sanitary sewers. The Dubuque City Council has made infrastructure projects a high priority and the the City of Dubuque is committed to the Bee Branch Watershed Flood Mitigation Project, a multi- faceted approach to addressing the severe -and frequent flash flooding experienced in the watershed. The City of Dubuque is requesting over $98 million* from the Iowa Flood Mitigation Board in the form of state sales tax increment financing spread over the next 20 years. If this request is approved and combined with other state and federal grants and local donations, the City will have received $127,288,855 to help fund the project. Additional funding sources are being explored. Flood disasters have repeatedly impacted residents and employees of the businesses within the watershed. Six Presidential Disasters directly impacting the Bee Branch Watershed due to flash flooding as a result of rainstorms were issued between 1999 and 2011, with damage estimates totaling almost $10 million. The flooding in the Bee Branch Watershed also has a major impact on public infrastructure and City services both within and outside the flood- impacted area. Direct public sector costs include emergency response activities, street and utility infrastructure repairs, and debris clean -up and removal. The disruption of essential City services and street closures due to flooding and damage has a negative economic impact on the entire community. Based on a 2009 Federal Emergency Management Agency (FEMA) study, 1,313 homes and businesses in the watershed are prone to flooding, including 70 businesses that, combined, employ over 1,400 and have over $500 million in annual sales. The Bee Branch Watershed Flood Mitigation Construction Project will prevent an estimated $582 million in damages over the 100 -year design life of the project and create an incentive for individuals and businesses to reinvest in this vital area of our community. 'This would be the largest amount ever awarded to the City of Dubuque and would enable the City to implement a comprehensive flood mitigation plan much quicker than previously possible. Bee Branch Watershed Flood Mitigation Project Phases I l ir•Pi?' Phase 1: Carter Road Detention Basin Completed in 2003 Phase 2: West 32nd Street Detention Basin Completed in 2009 Phase 3: Historic Millwork District Complete Streets Completed in 2012 Phase 4: Lower Bee Branch Creek Restoration Est. Completion - 2014 $1,076,315 $4,158,589 $7,977,311 $21,274,685 Phase 5: Flood Mitigation Gate Replacement Phase 6: Impervious Surface Reduction (Alley Reconstruction) Phase 7: Upper Bee Branch Creek Restoration Phase 8: 22nd St. Storm Sewer Capacity Improvements Phase 9: Flood Mitigation Maintenance Facility Phase 10: North End Storm Sewer Capacity Improvements Phase 11: Water Plant Flood Protection Phase 12: 17th St. Storm Sewer Capacity Improvements Est. Completion - 2015 Est. Completion - 2033 Est. Completion - 2016 Est. Completion - 2020 Est. Completion - 2020 Est. Completion - 2019 Est. Completion - 2020 Est. Completion - 2020 Total cost, excluding interest on debt: $2,099,000 $57,420,000 $64,823,636 $3,380,000 $4,360,000 $1,160,000 $3,800,000 $7,520,000 $179,049,536 Bee Branch Watershed A watershed is an area of land that drains to the same place. The Bee Branch Watershed drains to the Bee Branch Creek. The Bee Branch Watershed is located entirely within the city limits of Dubuque and covers approximately 6.5 square miles of Dubuque's total area of 29 square miles. This watershe sae _ . g e o .. ; where over 50% of esidents either live or work. • The combined phases will reduce the volume of stormwater, slow the rate of stormwater through the upper watershed, increase the safe conveyance of stormwater through the flood -prone area, and provide floodwater protection to the City's water treatment plant on Hawthorne Street. s • Bee Branch Watershed • Bee Branch Creek Restoration Area (Phases 4 & 7) City Limits • Masterpiece on the Mississippi - - Application for State Flood Mitigation Program Fundin Bee Branch Watershed Mitigation Project g for the Flood Dubuque Floodin Summary of Presidential Disaster Declarations in 1999 - 2011 Presidential Disaster Declaration: May 21, 1999 Disaster # 1277 Reason for Declaration Flooding, severe storms, tornadoes Cause of Damage 3 inches of rain in 1.5 hours Summary of Presidential Disaster Declarations in 1999 - 2011 Presidential Disaster Declaration: May 21, 1999 Disaster # Ream' fnr Caus Disaster # 1420 Reason for Declaration Flooding and storms Cause of Damage 4.9 inches of rain in 24 hours flar•Inrntinr, 1277 Clnnrlinrr catiara ctnrrnc tr'rr»rinac Presidential Disaster Declaration: ne 19, 2002 Summary of Presidential Disaster Declarations in 1999 - 2011 Presidential Disaster Declaration: May 21, 1999 Disaster # 1277 Reas"ri fr,r nent-1-r-+Thr‘r, Caus GI ""r1 rir en%Inrn c+"rrt-se Presidential Disaster Declaration: June 19, 2002 Disaster # Rease,r, &sr- rtrw-1-1,--11-;"r% Caus 1420 I r, r4 ; ern -1 r,r4 ri-rsrert Presidential Disaster Declaration: June 2, 2004 Disaster # 1518 Reason for Declaration Flooding, severe storms, tornadoes 3.9 inches of rain in 48 hours Cause of Damage Summary of Presidential Disaster Declarations in 1999 - 2011 Presidential Disaster Declaration: May 21, 1999 Disaster # 1277 Reas"ri feNr Caus rlrT re..tarn ci-"rrirsc +"rri nri"nc Presidential Disaster Declaration: June 19, 2002 Disaster # Reas— fr"" Caus 1420 Cl""Alir.rs et el Presidential Disaster Declaration: June 2, 2004 Disaster # 1518 Reas"rt f"r flinrinrn+i"rt Cl""clit-trs Caus entrnrn c+"rrete fr,rt-In rinac Presidential Disaster Declaration: May 27, 2008 Disaster # 1763 Reason for Declaration Flooding, severe storms, tornadoes Cause of Damage Record 15.7 inches of rain in 2 months Summary of Presidential Disaster Declarations in 1999 - 2011 Presidential Disaster Declaration: May 21, 1999 Disaster # 1277 Reasrrr, frrr nar•I�r� +irrr, Caus Glr•r•rlir►rs ca.►arc5 c +r•rrrtc +r rr»ri"enc Presidential Disaster Declaration: June 19, 2002 Disaster # Real"r% few nnr•I- rr- ti +inrl Caus 1420 C l rr n eI i rti ry w rti el c +rr r rrr r Presidential Disaster Declaration: June 2, 2004 Disaster # Reas" Caus frrr 1518 Clr�r�r�l i►-�rs C 6116 ra C +^ rrrtC +rrrrN rinac Presidential Disaster Declaration: May 27, 2008 Disaster # Reas ^r, frrr nrw- - ,r -, +il r, Caus 1763 C I rr rr r'i i r, rr rr»Inrn r +nrr -r tnrr�- �rInnr Presidential Disaster Declaration: August 14, 2010 Disaster # 1930 Reason for Declaration Flooding, severe storms, tornadoes Cause of Damage 4.8 inches of rain in 12 hours Summary of Presidential Disaster Declarations in 1999 - 2011 Presidential Disaster Declaration: May 21, 1999 Disaster # 1277 Reason► fr r flarinrn +inrt Glnnrlir►rs ca►►ara c +nrrnc +nrr►'rinac Presidential Disaster Declaration: June 19, 2002 1420 Clnnelir,rs c +nrrnr Presidential Disaster Declaration: June 2, 2004 Reasr,r, fr,r nar•Inrn+ir,r, 1518 Glnnrdir►rs ca►►ara eft., r rin c +nrr►nrinac Presidential Disaster Declaration: May 27, 2008 Disaster # Reason, few nnr,I- .,i0- , +inr, Caus 1763 Clnnelir►rs n►rnrn c +nrw,c +nrr- ,rinnc Presidential Disaster Declaration: August 14, 2010 _ Disaster# Reasn'" fr r flarinrn +inn, Caus 1930 Glr,r,rlir►rs ca►►ara c +nrrr,c +r,rr►nrinac Presidential Disaster Declaration: August 30, 2011 Disaster # Reason for Declaration 4018 Flooding, severe storms, tornadoes 10.2 inches of rain in 12 hours Cause of Damage Estimated damages due to disasters in the past twelve y $69.8 millio the six ars totals Locust -St / �pennsylvania Ave p - - -- 0.25' 0.5- -- - Watershed Hydrology... Watershed Hydrology... Watershed Hydrology... Watershed Hydrology... Watershed Hydrology... Watershed Hydrology... olt2oloip/tH pagsialeArr-- In 1998 the development of the Drainage Basin Master Plan begins... 'U it 4. • •!, A: w err t iL- • 'r k 1,155 Homes/ Washinton Street Sub Area 100 -yr Flood Inundation Existing conditions flooding depths (feet) 0.1 - 0.5 0.5 - 1 1 -2 2 -3 3 -4 - 4 -5 MI 5* 1000 0 1000 2000 Feet Businesses jiw Predicted Floodi Predicted Flooding...FEMA FEMA Floodplain, Proposed in 2009 Zone A, 100-year floodplain Zone X (Protected by Levee) Bee Branch Watershed Flood Mitigation Project ennsylvania Ave p 0.25" - 0.5 — - - -- Bee Branch Watershed Flood Mitigation Project Bee Branch Watershed Flood Mitigation Project Bee Branch Watershed Flood Mitigation Project Millwork District Street Detention /Conveyance System r" f? y Pennsylvania Ave -----6725 0.5 Bee Branch Watershed Flood Mitigation Project air r .J Lower Bee Branch Creek & Floodplain Restoration Kauirna9prr tit 3:Ctr � I / ennsylvania Ave Miles p Bee Branch Watershed Flood Mitigation Project N { �VPennsylvania Ave p 0.25" 0.5 — — - Miles i ■ Pervious Alley Detention /Conveyance Systems Bee Branch Watershed Flood Mitigation Project Upper Bee Branch Creek & Floodplain Restoration ennsylvania Ave Bee Branch Watershed Flood Mitigation Project - e# 22nd Street Conveyance Improvements Porfifir i N ti ennsylvania Ave - -_ -0_— 0.25 0.5 - - - - -- 1 - hal c Miles I' Phase 8 Bee Branch Watershed Flood Mitigation Project BEE BRANCH ', Flood Mitigation ' ,r • ' - -- Maintenance Facility ennsyrlv_aniaAve !� W —0- 0. 25 o —s 1 Miles Phase 9 Bee Branch Watershed Flood Mitigation Project ,, r- ,PS'' �• S North End Conveyance Improvements Kzu#tnann Ave i I; ennsylvania Ave -- - - - -0" 0.25 0.5 1 T-TIR I .w KMiles 7 Phase 10 Bee Branch Watershed Flood Mitigation Project ; Potable Water is Treatment Plant ti•- •—•-'- Flood Protection r fir , ' ennsylvania Ave 0.25 0.5 7 ` Miles N Phase 11 Bee Branch Watershed Flood Mitigation Project 17th Street Conveyance Improvements W ie Pennsylvania Ave 0.5 1 Watershed Solutions... Watershed Solutions... Bee Branch Watershed Flood Mitigation Project Phases Phase Description Est. Completion Est. Cost 1 Carter Road Detention Basin Completed 2004 $1.076.315 2 West 32nd Street Detention Basin Completed 2009 $4,158,589 3 Historic Millwork District Completed 2012 $7,977,311 4 Lower Bee Branch Creek Restoration 2014 $21,274,685 5 Flood Mitigation Gate Replacement 2015 $2.099,000 6 Impervious Surface Reduction 2034 $57,420,000 7 Upper Bee Branch Creek Restoration 8 22nd Street Storm Sewer Improvements 9 Flood Mitigation Maintenance Facility 2016 2020 2020 $64,823,636 $3,380,000 $4,360,000 10 North End Storm Sewer Improvements 2019 $1,160,000 11 Water Plant Flood Protection 2020 $3,800,000 12 17th Street Storm Sewer Improvements 2020 $7,520,000 Total $179,049,536 Application for State Flood Mitigation Program Funding forth: Bee Branch Watershed Flood Mitigation Project Conformance with City ; priorities, policies, and ini oals, tiatives SUSTAINABLE DUBUQUE viable • liveable • equitable Environmental/ Ecological Integrity Economic Social /Cultural Prosperity Equitable Vibrancy • V • rr • Iand advances the following City Cow cil Goals & 2028 Vision Statement: quality, livable neighborho • ••• • ▪ • ▪ • Five -year community goals for a sustainable D • Economic Prosperity • Social /Cultural Vibrancy ods u Duque: • Environmental Integrity Policy Agenda 2013 -15 Top Priorities: • Safe Community Initiative • Washington Neighborhood Strategy Policy Agenda 2013 -15 High Priorities: • Ree Branch Project: Specific projects, direction, funding • Historic Millwork District Management Agenda 2013 -15 Economic Prosperity Goal: Workforce Market -Rate Housing Management Agenda 2013 -15 Environmental /Ecological Integrity Goal: • America's River III Task Force • Community Climate Action & Resiliency Plan onsistent with iorities: ent and High onsistent with iorities: • 1 • • • • • • - - - • - - - and advances the following City Council Goals & 1 Management Agenda 2013 -15 Social /Cultural Vibrancy Goal: • Local ADA Compliance Program • Community Engagement Strategy Management Agenda 2013 -15 Planned & Managed Growth Goal: • EPA Consent Decree Implementation • City Comprehensive Plan • Flood Wall • Historic Preservation Program Management Agenda 2013 -15 Financially Responsible City Governm Performance Organization: Disaster Preparedness and Recovery Plan Management Agenda 2013 -15 Major Projects: • Green Alley Projects • Comiskey Park Improvements Watershed Sol I V . . . T an • a • vances e o owing: Dubuque Comprehensive Plan Every Child I Every Promise I. Places) Dubuque County Multi - Jurisdictional Hazard Mitigation Plan Dubuque County Comprehensive Emergency Management Plan City of Dubuque Flood Plain Ordinance onsistent with Application for State Flood Mitigation Program Funding forth: Bee Branch Watershed Flood Mitigation Project a e 00' 'iiga ion [VANAGEM IOWA HOMELAND ECURITY ANAGEM ogram EmERGENCY ENT � F -'- • Funding to address Floo Citizen Advisory Corn mitte • 33 Representatives • • • Seven (7) Public Input Sessions for General Public Representation: Neighborhoods; Tax - Exempt Propert churches, universities); Business; Hospitals; Impacted Eight (90+ minute) meetings between June 2002 and Consensus Opinion: The City needs to address the i • • • • • ing... e ies (schools, Residents anuary 2003 entified ossible Consensus Opinion: The City should implement a stormwater utility Funding to address Floo Outside Funding Secured to Date for Bee Branch Creek Watershed Flood Mitigatio U.S. DOT TIGER Grant -Jobs II Grant RECAT Grant U.S. DOT National Scenic Byways Grant State Recreational Trail Grant U.S. Economic Development Administration Dubuque Metropolitan Area Transportation Study U.S. EPA Clean Water SRF Forgivable Loan U.S. EPA Clean Water SRF Sponsorship Program (Green Alleys) Private Donations ing... Project $5,600,000 $3,965,500 $2,250,000 $1,000,000 $100,000 $1,227,000 $640,000 $4,400,000 $9,416,000 $165,000 r X3011 ICUt!r 'S gjT°rT- ASTFiUGTURE INVESTMENT INTUATF#E SRF IOWA filFederal Highway e Administration U.S. Department of Transportation OA Iowa Department WO Transportation Masterpiece on the Mississippi TREES FOREVER Together We Grow ramgc-?trT 4104' Dupaeo ZObank, 444CALLI 444. k > IOWA 4EMRTlIENTOi AGCLRE v WAIIL N;RT FO UNDATION a UYn s71W1:4 SHIP ECIA E*D*A U.S. ECONOMIC DEVELOPMENT ADMINISTRATION PREMIER BANK ••r North End Neighborhood Association oa rd The Flood MitigE created by General Assem signed into law Code, Chapter Governor Brans The board is chic ation Board the Iowa bly and (Iowa 418) by tad in 2012. a rged with creating a flood mitigation program for Iowa. This program will allow certain governmental entities to submit flood mitigation projects to the Board for review and possible approval for funding. The funding will come from either sales tax increments or funds appropriated by the General Assembly. The Board itself is composed of four members from the public, five members from state agencies, as well as four ex- officio members from the General Assembly. ∎1 1rs�7F1T�L Taxer iiT�"iTii IowA HOMELAND SECURITY IVANAGEM nding EmERGENCY ENT ROAD L00DED Application for State Flood Mitigation Program Funding forth: Bee Branch Watershed Flood Mitigation Project Financial Details State Sales Tax Increment F State Share Sales Tax Collected in 3 State Sales Tax Increment F State Share Sales Collect State Share les Tax lected in ure Year State Sales Tax Increment F State Share Sales Collect State Share I le ted in ure Year State Share Sales Tax Increment State Sales Tax Increment F State Share Sales Collect State Share I le ted in ure Year State Share Sales Tax Increment State Sales Tax Increment F nding State Share State Share Sales .x S:I: Collecte• in Co le ure Year State Share Sales Tax Increment 70% Sales Tax Increment Available for Flood Mitigation Projected Sales Tax Gro Fiscal Annual Retail Year Sales 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 $1,035,951,177 $1,056,255,820 $1,076,958,435 $1,098,066,820 $1,119,588,930 $1,141,532,873 $1,163,906,917 $1,186,719,492 $1,209,979,194 $1,233,694,787 $1,257,875,204 $1,282,529,558 • • Retail Sales Growth ($) $19,914,322 $20,304,643 $20,702,614 $21,108,385 $21,522,110 $21,943,943 $22,374,044 $22,812,576 $23,259,702 $23,715,592 $24,180,418 $24,654,354 Annual Retail Sales Growth % 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% Gross Sales Tax Revenue $51,797,559 $52,812,791 $53,847,922 $54,903,341 $55,979,446 $57,076, 644 $58,195,346 $59,335,975 $60,498,960 $61,684,739 $62,893,760 $64,126,478 Annual Sales Tax rowth % 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 7 2027 $1,333,297,414 2028 $1,359,430,043 2029 $1,386,074,872 2030 $1,413,241,939 2031 $1,440,941,481 2032 $1,469,183,934 2033 $1,497,979,940 $25,630,276 $26,132,629 $26,644,829 $27,167,067 $27,699,542 $28,242,453 $28,796,005 Tntal fi"ic f17n R7c Qr Q <Q.R1 (14. nRc 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1 Q7% $66,664,871 $67,971,502 $69,303,744 $70,662,097 $72,047,074 $73,459,197 $74,898,997 <1 ')c' 54.' Ann 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1.97% 1 Q7 %% th %of City of buque State Sales Tax 36,258,291 36,968,954 37,693,545 38,432,339 39,185,612 39,953,651 40,736,742 41,535,183 42,349,272 43,179,317 44,025, 632 44,888,535 45,768,350 $46,665,410 $47,580,051 $48,512,621 $49,463,468 $50,432,952 $51,421,438 $52,429,298 <R77 aAI) Maximum Projected 70% Sales Tax Increment $332,469 $1,407,664 $2,132,255 $2,871,049 $3,624,322 $4,392,361 $5,175,452 $5,973,893 $6,787,982 $7,618,027 $8,464,342 $9,327,245 $10,207,060 $11,104,120 $12,018,761 $12,951,331 $13,902,178 $14,871,662 $15,860,148 $16,868,008 fit Ac gin /7c) ►014 ►015 ►016 ►017 ►018 ►019 ►020 ►021 ►022 ►023 ►024 ►025 ►026 Funding Reque Maximum Projected 70% Sales Tax Increment $332,469 $1,407,664 $2,132,255 $2,871,049 $3,624,322 $4,392,361 $5,175,452 $5,973,893 $6,787,982 $7,618,027 $8,464,342 $9,327,245 $10,207,060 $11,104,120 2027 POMP Projected 70% Sales Tax Increment Request $332,469 $1,407,664 $2,132,255 $2,871,049 $3,624,322 $4,392,361 $5,175,452 $5,973,893 $6,787,982 $6,944,414 $6,968,288 $6,946,514 $6,957,577 $ 6,947,487 2028 2029 2030 2031 2032 2033 Total $12,018,761 $12,951,331 $13,902,178 $14,871,662 $15,860,148 $16,868,008 $165 890,329 6,947,500 $6,500,000 $6,000,000 $5,500,000 $3,260,000 $2,824,951 $98,494,178 t Sales Tax Increment Request as % of Total rojected 70% Sales Tax Increment 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 91.16% 82.33% 74.48% 68.16% 62.57% 57.81% 50.19% 43.16% 36.98% 20.55% 16.75% Gran • g Reque Fiscal Projecte Year In 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 $ aximum 70% Sales Tax crement 32,469 ,407, 664 ,132,255 ,871,049 ,624,322 ,392,361 ,175,452 ,973,893 ,787,982 ,618,027 ,464,342 ,327,245 ,207,060 Projected 70% Sales Tax Increment Request $332,469 $1,407,664 $2,132,255 $2,871,049 $3,624,322 $4,392,361 $5,175,452 $5,973,893 $6,787,982 $6,944,414 $6,968,288 $6,946,514 $6,957,577 $6,947,487 2028 2029 2030 2031 2032 2033 12,018,761 $12,951,331 $13,902,178 $14,871,662 $15,860,148 $16,868,008 $6,947,500 $6,500,000 $6,000,000 $5,500,000 $3,260,000 $2,824,951 Total $165,890,329 $98,494,178 t Sales Tax Increment Request as % of Total rojected 70% Sales Tax Increment 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 91.16% 82.33% 74.48% 68.16% 62.57% 57.81% 50.19% 43.16% 36.98% 20.55% 16.75% Grant Funding Reque Requested Sa F 2 2 2 2 2 2 2 2 2 2 2 2 2 2027 scat ear 014 015 016 017 018 019 020 021 022 023 024 025 026 es Tax Increment Compared to Total Available S Request Sales Tax Increment $332,469 $1,407,664 $2,132,255 $2,871,049 $3,624,322 $4,392,361 $5,175,452 $5,973,893 $6,787,982 $6,944,414 $6,968,288 $6,946,514 $6,957,577 $6,947,487 Total Available State Flood Mitigation Funds Flo $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 2028 2029 2030 2031 2032 2033 $6,947,500 $6,500,000 $6,000,000 $5,500,000 $3,260,000 $2,824,951 Total $98,494,178 30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $30,000,000 $ 600,000,000 t ate Funds otal Available State d Mitigation Funds 1.11% 4.69% 7.11% 9.57% 12.08% 14.64% 17.25% 19.91% 22.63% 23.15% 23.23% 23.16% 23.19% 23.16% 23.16% 21.67% 20.00% 18.33% 10.87% 9.42% 16.4% Local, State, & Federal Fundir T Project Funding Source Federal: U.S. EPA Clean Water SRF Federal: U.S. EPA Clean Water SRF I Federal $ Local $ In $7,766,500 $1,827,000 Federal: U.S. EPA Clean Water SRF Federal: U.S. EPA Clean Water SRF Federal: U.S. EDA Disaster Relief Grant Local: U.S. DOT TIGER Grant Local: I -Jobs II Grant Local: RECAT Grant Local: U.S. DOT National Scenic Byways Grant Local: State Recreational Trail Grant Local: DM ATS Local: General Obligation Bonds Local: Private Donations Local: Sale of Assets and Land $1,187,757 $28,823,000 $1,227,138 IIIF$5,600,000 $3,965,500 $2,250,000 $1,000,000 $100,000 $640,000 $48,227,604 $165,244 $336,358 Local: Stormwater Utility Fees State: Sales Tax Increment Table adjustment for SRF loan repayment Total Project Funding Source $14,394,096 g Share es Tax ement $98,494,178 $50,248,190 ( $76,678,802 $98,494,178 Total $7,766,500 $1,827,000 $9,416,795 $1,187,757 $28,823,000 $1,227,138 $5,600,000 $3,965,500 $2,250,000 $1,000,000 $100,000 $640,000 $48,227,604 $165,244 $336,358 $14,394,096 $98,494,178 $(24,491,634) $200,929,536 Local, State, & Federal Fundir T Project Funding Source Federal: U.S. EPA Clean Water SRF Federal: U.S. EPA Clean Water SRF I Federal $ $7,766,500 $1,827,000 Local $ In Federal: U.S. EPA Clean Water SRF Federal: U.S. EPA Clean Water SRF Federal: U.S. EDA Disaster Relief Grant Local: U.S. DOT TIGER Grant Local: I -Jobs II Grant Local: RECAT Grant Local: U.S. DOT National Scenic Byways Grant Local: State Recreational Trail Grant Local: DM ATS Local: General Obligation Bonds Local: Private Donations Local: Sale of Assets and Land $1,187,757 $28,823,000 $1,227,138 IIIF$5,600,000 $3,965,500 $2,250,000 $1,000,000 $100,000 $640,000 $48,227,604 $165,244 $336,358 Local: Stormwater Utility Fees State: Sales Tax Increment Table adjustment for SRF loan repayment Total Project Funding Source $14,394,096 g Share es Tax ement $98,494,178 $50,248,190 $76,678,802 $98,494,178 Total $7,766,500 $1,827,000 $9,416,795 $1,187,757 $28,823,000 $1,227,138 $5,600,000 $3,965,500 $2,250,000 $1,000,000 $100,000 $640,000 $48,227,604 $165,244 $336,358 $14,394,096 $98,494,178 Local, State, & Federa Bee Branch Watershed Flood Mitigation Project 95 Phase Description 1 Carter Road Detention Basin 2 West 32nd Street Detention Basin 3 Historic Millwork District ed ed ed Fed 4 Lower Bee Branch Creek Restoration Flood Mitigation Gate Replacement !1 6 Impervious Surface Reduction Loc Loc Loc ILoc Loc Loc Loc Local: Sale of Assets and Land 7 Upper Bee Branch Creek Restoration nd 8 22 Street Storm Sewer Improvements 9 Flood Mitigation Maintenance Facility 10 North End Storm Sewer Improvements 11 Water Plant Flood Protection 12 17th Street Storm Sewer Improvements etion Est. Cost 2004 $1.076,315 2009 $4,158,589 2012 $7,97T311 $21,274,685 $2,099.000 $57,420,000 S64.823,636 $3,380,000 $4,360.000 $1,160,000 S3.800.000 $7.520,000 Est. ComplE Completed Completed 2014 2015 2034 2016 2020 2020 2019 2020 2020 Local: Stormwater Utility Fees State: Sales Tax Increment Table adjustment for SRF loan repayment Total Project Funding Source S u btot $336,358 $14,394,096 al $179,049,536 $98,494,178 $50,248,190 $76,678,802 $98,494,178 00 00 95 57 00 38 0 00 00 00 0 00 04 44 $336,358 $14,394,096 $98,494,178 Est. Completion Completed 2004 Completed 2009 Completed 2012 2014 2015 2034 2016 2020 2020 2019 2020 2020 Subtotal Debt Interest, Issuance Fees & Reserve Local, State, & Federa Bee Branch Fundi Watershed Flood Mitigation Project 95 Phase Description Fed 1 Carter Road Detention Basin Fed 2 West 32nd Street Detention Basin 3 Historic Millwork District Fed Fed Loc Loc, Loc 4 Lower Bee Branch Creek Restoration Flood Mitigation Gate Replacement !1 6 Impervious Surface Reduction 7 Loc. 8 Loc, 9 Loc. 10 Loc. 11 Loc, 12 Upper Bee Branch Creek Restoration nd 22 Street Storm Sewer Improvements Flood Mitigation Maintenance Facility North End Storm Sewer Improvements Water Plant Flood Protection 17th Street Storm Sewer Improvements Loca : ormwa er • i i y ees State: Sales Tax Increment Table adjustment for SRF loan repayment Total Project Funding Source I Est. Cost $1.076,315 $4,158,589 $7,977.311 $21,274,685 $2,099.000 $57,420,000 S64.823,636 •0 $3,380,000 00 $4,360.000 00 $1,160,000 00 S3.800.000 to $7.520,000 00 $179,049,536 44 58 96 $21,880,000 $98,494,178 $50,248,190 $76,678,802 $98,494,178 00 00 95 57 00 38 $98,494,178 Local, State, & Federa Bee Branch 95 Phase Description 1 Carter Road Detention Basin 2 West 32nd Street Detention Basin 3 Historic Millwork District Fed Fed ed Watershed Flood Mitigation Project 4 Lower Bee Branch Creek Restoration Flood Mitigation Gate Replacement PE 6 Impervious Surface Reduction ILoc Loc Loc Loc, Loc Upper Bee Branch Creek Restoration nd 22 Street Storm Sewer Improvements Flood Mitigation Maintenance Facility North End Storm Sewer Improvements Water Plant Flood Protection 17th Street Storm Sewer Improvements Est. Completion Completed 2004 Completed 2009 Completed 2012 2014 2015 2034 2016 2020 2020 2019 2020 2020 Subtotal Loci Stat Table adjustment for SRF loan repayment Total Project Funding Source Est. Cost $1.076,315 $4,158,589 $7,977.311 $21,274,685 $2,099.000 $57,420,000 S64.823,636 $3,380,000 $4,360.000 $1,160,000 S3.800.000 $7.520,000 Debt Interest, Issuance Fees & Reserve 00 00 95 57 00 38 0 00 00 00 to 00 04 $179,049,536 44 58 96 78 $21,880,000 Total $200,929,536 $50,248,190 $76,678,802 $98,494,178 Projected Debt Financi Debt General Obligation Bonds U.S. EPA Clean Water SRF Sales Tax Increment Revenue Bond* Total Debt Financing Grants Stormwater Utility Fee Other Funding ** Total Project Funding Previously Issued $16,503,604 $19,010,295 $35,513,899 Futur Issuan $31,724 $ 30,154, $28,257, $90,136 * The Sales Tax Increment Revenue Bonds may be further secured by or a pledge of debt service taxes. MOW 411=1111F e 000 872 938 810 Amount $48,227,604 $49,165,167 $28,257,938 $125,650,709 $14,142,638 $14,394,096 $46,742,093 $200,929,536 tormwater revenues ** Includes a combination of funding from Dubuque Metropolitan Area Transportation Study (DMATS), private donations, sale of assets and land and sales tax increment. Stormwater Utility Fee Previously Adopted Stormwater Utility Rate Ordinance 21 -12 $7.00 $7.50 $8.00 $8.50 $9.00 $9.00 $9.00 $9.00 $9.00 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 FY2019 FY2020 FY2021 Projected S Utility Rate Local $5. $5. $5. $6. $6. ates ormwater o Provide atch 0* 0* ** 8 8 1 7 6 9 5 ** * The rates established by Ordinance 21 -12 were modified with the passing of Ordinance 9 -13 which established a rate of $5.60 in anticipation of the availability of State Flood Mitigation state sales tax increment funds for the Bee Branch Watershed Project. ** The rates each reach their peak at $9.00. Masterpiece on the Mississippi uestions. it • RI