Contracts Signed - Floodwall Chg Ord. 3 '. D~~~E ~</k.~ MEMORANDUM November 27,2006 TO: Michael C. Van Milligen, City Manager Don Vogt, Public Works Director ~ SUBJECT: Floodwalllmprovement Projects - Change Order #3 FROM: INTRODUCTION The purposes of this memorandum are to convey information and recommend your action regarding the attached change order for the Floodwalllmprovement Projects currently underway, BACKGROUND The Floodwalllmprovement Projects, providing auxiliary power to the Maus Lake and Hawthorne Street pumping stations, along with numerous infrastructure enhancements at the Bee Branch pumping station, are currently underway. The total budget appropriation for the projects is $555,766.00 - $446,420.80 for the construction contract, $66,400.00 for engineering fees, and, $42,945.20 for contingencies. DISCUSSION A memorandum from Street and Sewer Maintenance Supervisor John Klostermann regarding change order #3 is attached. Also attached is change order #3 in triplicate. The work associated with the change order is considered essential for the improvements at the Bee Branch pumping station. The cost of this change order is $5,463.50, When added to the previous two change orders, total change order costs to date would equal $14,389.41. This would leave a contingency fund balance of $28,555.79. The additional cost of the three change orders equals 3% of the original construction contract for the projects. ACTION STEP Your endorsement of the attached change order is recommended and requested. Attachments D~~~E ~ck~ MEMORANDUM November 27, 2006 TO: Don Vogt, Public Works Director FROM: John Klostermann, Street/Sewer Maintenance superviso4t- SUBJECT: Floodwall improvement Projects - Change Order # 3 Introduction The purpose of this memorandum is to request your approval to change order # 3 for the Floodwalllmprovement Projects. Discussion Change order # 3 is for various types of necessary construction related changes associated with the improvements being made at the Bee Branch Floodwall Pumping Station. These changes include pouring a thickened edge along the sidewalk and installing an additional concrete slab next to the new steps. The remainder of the change order is for work related to the screen wall. I have reviewed the change order as submitted with Charles Cate of IIW and we both feel that the change order is fair and just. Action Required I am requesting that you review change order #3 and recommend payment. 'I' 'I' CHANGE ORDER Change Order No: 3 Date: November 21, 2006 Agreement Date: August 21,2006 Owner: Project: City of Dubuque Hawthorne Street, Bee Branch and Maus Lake Flood Wall Pumping Facilities Generator Installation Kluck Construction, Inc, No. 05036-01 Contractor: Description of Change: 1. a) Additional Concrete 4 YD@ $109.25 b) Additional Labor 12 HRS @50.00 c) Additional Forming Material 1 LS @ 172.50 2. Additional Paving stairs/slab/slope 1 LS @ 500.00 3. Reduce wall height to control bldg 1 LS @ 969.00 4. Replace chain link w/concrete block at control bldg 1 LS @ 2,785.00 Total Increase $437.00 600.00 172.50 500.00 969.00 2.785.00 $5,463.50 Justification for Change: 1. To form and pour additional concrete for 40 feet sidewalk with approximately 18-inch thickened edge 2. Slope is too great for clean stone to maintain 3. To present a more pleasing and uniform appearance at control building 4. To screen equipment fully from view at the control building Change in Contract Price: The amount of the contract will be Increased by this change order by the sum of Five Thousand Four Hundred Sixty Three and 50/100 Dollars ($5,463.50) Adjustment in Amount of Contract: 1. Amount of Original Contract 2. Net Addition due to all previous change orders 3. Amount of contract not including this change order 4. Addition to contract due to this change order 5. Amount of contract including this change order Change Order Conditions: $446,420.80 $8,925.91 $455,346.71 $5,463.50 $460,810.21 The contract completion period established by the original contract and previous change orders will remain unchanged. 1-1 . Change Order Page 2 . . '.. Work performed under this change order will be subject to all the requirements as stated herein and in the contract documents and all change orders. The Contractor expressly agrees that he will place under coverage of his Contractor's Improvement Bond and insurance all work covered by this change order. All work performed under this change order shall be performed in accordance with the requirements of this change order, the plans, the specifications, and the contract documents. Recommended for Acceptance: .C. BY NAME Signature Charles A. Cate, P.E. Type or Print TITLE President DATE 1 [ /'2'2 htJl)0 I I BY CONTRACTOR Kluck Construction, Inc. BY c;}:JJjr!h/J/' lJ'ff / I / 16 / Signature NAMEvLL/IB l;J!hP Accepted and/or Requested: Attest: Signature TITLE afI'eL j// lljr DATE IICl;) (){; Type or Print NAME Type or Print TITLE Approved and/or Requested: OWNER !ll~a BY ~ Jv;, Attest: BY Signature NAME Michae~ C. Van Mi~~iqen Signature Type or Print NAME TITLE City Manager Type or Print TITLE DATE 1-2