Loading...
30-Inch Force Main Project Phase I AcceptanceMasterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager Dubuque band AI- America City 1 2007 • 2012 • 2013 SUBJECT: 30 Inch Force Main Relocation Project from 7th Street to 12th Street around the former Public Works Garage Site and the Alliant Energy Site DATE: December 9, 2013 City Engineer Gus Psihoyos is recommending acceptance of the construction contract for Phase I of the 30 Inch Force Main Relocation Project from 9th Street to 11th Street, as completed by Portzen Construction, in the final contract amount of $812,351.43, which is below the original contract amount of $899,622.50. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Gus Psihoyos, City Engineer THE CITY OF Dui E Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer DATE: December 5, 2013 Dubuque kzitzt All-knerica City 11111 f 2007 • 2012 • 2013 RE: 30 Inch Force Main Relocation Project from 7th Street to 12th Street around the former Public Works Garage Site and the Alliant Energy Site INTRODUCTION The enclosed resolution provides for the acceptance of the construction contract for Phase I of the 30 inch Force Main Relocation Project from 9th Street to 11th Street. BACKGROUND In 1969 the existing 30 inch force main was constructed from the Cedar Street lift station to the Terminal Street lift station. The route went through the former A.Y. McDonald site, the former City Public Works site, and the Alliant Energy site. During the early 1990's highway 151/61 was constructed through Dubuque. During the highway construction portions of the 30 inch force main were relocated and the portion running through the A.Y. McDonald site was abandoned. However the portion running through the old Public Works Site and the Alliant Energy site remained in place. In October of 2011, the City experienced a significant failure in the existing force main. Two breaks occurred simultaneously, one at the former Public Works garage site and the other at the Alliant Energy site. After repairs were completed, a third break was experienced at the former Public Works garage site. The cost to repair the breaks, which occurred on the former Public works site, was significant as the site is a super fund site. During the repair work some corrosion of the pipe was noted and it was also found that when constructed the pipe was set on blocking prior to bedding, and the blocking was not removed. The areas of corrosion and the failed sections of pipe were near the old blocking that was found to be still in place. Soil and ground water contamination has been identified on or near the existing 30 inch force main route that may be a contributing factor to its deterioration. The adopted budget for FY 2013- FY2017 includes $849,124.00 for the design of the entire force main relocation, from 7th Street to 12th Street, and constructing the first phase, from 9th Street to 11th Street. A description of the force main relocation is as follows: Construct Phase I: The first phase constructed the force main pipe from Northeast corner of the EIm Street and 11th Street intersection to the Southwest corner of the 9th Street and Washington Street intersection. Also, an 8 inch water main was constructed along Elm Street to provide an additional connection between the 20" transmission water main, on 11th Street, and the existing water main on 9th Street. This phase completed the section of pipe adjacent to: the planned intermodal facility, on EIm Street; thru future intersection improvements for the two way conversion of 9th and 11th Streets; and along the future EIm Street reconstruction project. Construct Phase II & III (Future Projects): Phase II is the section of force main on Washington Street, 7th Street to 9th Street. This section is planned to be completed in conjunction with the reconstruction of Washington Street from 7th to 9th Streets. Phase III is the section of force main from the Northeast corner of the 11th Street and EIm Street intersection, to the tie -in point near 12th Street. Phase III would also include the tie -in, at 12th Street and 7th street, and the abandonment of the existing force main through the old Public Works Garage and the Alliant Energy Site. Completing phase II and III will complete the re- routing project. Phase I of the 30 inch force main relocation project will be funded through the FY2013 capital improvement project appropriation in the amount of $849,124.00 and the FY2013 appropriation in the amount of $399,163.00 which will be used as reserves pending actual project costs incurred. Future funding for this project was initially available through CIP 7102413 in the amount of $699,600.00 in FY 2014, but moved to FY 2015. The water main improvements along Elm Street, from 9th Street to 11th Street, will be funded through the FY2013 appropriation in the amount of $430,209.59. DISCUSSION Phase I of the 30 inch Force Main Relocation Project from 9th Street to 11th Street was completed by Portzen Construction, Inc. of Dubuque, Iowa in the final contract amount of $812,351.43 which is below the original contract amount of $899,622.50. This was due to savings realized by; not replacing pavement of Elm Street, which will be reconstructed this spring and utilizing excavated material for backfill when possible. Also, the Engineering was increased due to the development of a soils management plan to deal with any contaminated soils if they were encountered. 2 RECOMMENDATION I recommend the City Council accept the public improvements and authorize the final payment of the contract amount of $812,351.43 to Portzen Construction, Inc. for Phase I of the 30 inch Force Main Relocation Project from 9th Street to 11th Street. BUDGET IMPACT The project cost summary for Phase I of 9th Street to 11th Street is as follows: Construction Contract Pipe Material — Purchased by City Contingency Construction Engineering & Inspection Total Project Cost the 30 inch Force Main Relocation Project from The project funding summary is as follows: CIP No. 7102413 7101899 Fund Description Relocation of 30" Force Main around Old Public Works Garage Southfork Interceptor 7402261 Watermain Extension with Elm St Total Project Funding Award Final $899,622.50 $812,351.43 150,198.00 150,198.00 85,416.48 0.00 140,937.18 181,659.72 $1,080,518.41 $1,144,209.15 Fund Amount $782,182.74 $185,411.93 $176,614.48 $1,144,209.15 Remaining funds from CIP 7102413 and 7101899 will be used for Phase II and III of the 30 inch Forcemain Relocation Project. ACTION TO BE TAKEN I respectfully request the City Council adopt the attached resolution to accept the public improvements for and to authorize the final payment of the contract amount of $812,351.43 to Portzen Construction, Inc. for Phase I of the 30 inch Force Main Relocation Project from 9th Street to 11 th Street. Prepared by Todd Irwin, Engineering Technician cc: Jenny Larson, Budget Director Jonathan Brown, Water Pollution Control Manager Tim Horsfield, Parking Division Manager Ken TeKippe, Finance Director John Klostermann, Street and Sewer Maintenance Supervisor Nate Steffen, Engineering Technician 3 RESOLUTION NO. 355 -13 ACCEPTING PHASE I OF THE 30 INCH FORCE MAIN RELOCATION PROJECT FROM 7TH STREET TO 12TH STREET AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR Whereas, the Public Improvement Contract for Phase I of the 30 Inch Force Main Relocation Project from 7th Street to 12th Street (the Project) has been completed and the City Engineer has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and that the City Engineer recommends that the Project be accepted; and NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor from the Relocation of 30" Force Main around Old Public Works Garage, Southfork Interceptor and Watermain Extension with Elm Street capital improvement appropriations for the contract amount of $812,351.43 less any retained percentage provided for therein as provided in Iowa Code chapter 573, and to pay such retainage only in accordance with the provisions of Iowa Code chapter 573. Passed, approved and adopted this 16th day of December, 2013 Attest: Kevin S Firnstahl, MC 4'�Clerk OZ.,/ Roy D. Buol, Mayor CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF PHASE I OF THE 30 INCH FORCE MAIN RELOCATION PROJECT FROM 7TH STREET TO 12TH STREET The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected Phase I of the 30 Inch Force Main Relocation Project from 7th Street to 12th Street, and that said Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $1,144,209.15. Dated this day of 2013. Gus Psihoyos, City Engineer Filed in the office of the City Clerk on the / day of 2013. Ke n S. Firnsta I, CMC City Clerk LINE NO. THE CITY OF DUB E Masterpiece on the Mississippi PROJECT NAME: ITEM NUMBER CONTRACTOR: ADDRESS: CITY, STATE, ZIP: City of Dubuque - Engineering Division Project Close Out Form 30 Inch Sanitary Sewer Force Main Relocation PH I - 9TH ST to 11TH ST Portzen Construction, Inc. 205 Stone Valley Drive Dubuque, IA 52003 BID ITEM DESCRIPTION AMOUNT OF CONTRACT AMOUNT: $ TOTAL CHANGE ORDERS TO DATE: $ 20,564.50 REVISED CONTRACT AMOUNT: $ 920,187.00 899,622.50 CONTRACT QUANTITY UNIT UNIT COST PREVIOUS TOTAL TO DATE QUANTITY AMOUNT CURRENT QUANTITY AMOUNT COUNCIL ACCEPTANCE DATE: 16- Dec -13 TOTAL TO DATE QUANTITY AMOUNT COMP. Division 1 1 1010 -103 Mobilization 1.00 LS $ 34,000.00 $ 1.00 $ 34,000.00 Sub Total $ 34,000.00 Sub Total $ Division 2010 - Earthwork, Subgrade, and Subbase 2 2010 - 108 -D -1 Topsoil, On -site 275.00 CY $ 8.00 $ - $ $ - 3 2010 - 108 -1 -0 Subbase, Granular Subbase - Gradation 12a 1720.00 TON $ _ _ 8.50 $ 532.08 $ 4,522.68 532.08 $ 4,522.68 30.93% 4 2010- 108 -F -0 Below Grade Excavation (Core Out) 500.00 TON $ 10.00 $ - $ - $ - 5 2010 - 108 -K -1 Filling and Plugging of Known Pipe Culverts, Pipes, and Conduits 6.00 CY $ 200.00 $ 2.50 $ 500.00 2.50 $ 500.00 41.67% Sub Total $ 5,022.68 Sub Total $ - Sub Total $ 5,022.68 Division 3010 - Trench Excavation and Backfill 6 3010 - 108 -D-0 Bedding Material, Clean Stone, 1" . 1860.00 TON $ 9.50 $ 1,351.76 $ 12,841.72 1351.76 $ 12,841.72 72.68% 7 3010 - 108 -0-0 Replacement of Unsuitable Backfill Material Gradation 12a 8000.00 TON $ 8.50 $ 4,356.00 $ 37,026.00 4356.00 $ 37,026.00 54.45% Sub Total $ _ 49,867.72 Sub Total $ Sub Total $ 49,867.72 Division 4010 - Sanitary Sewers 8 4010 - 108 -A -1 Sanitary Sewer Gravity Main, Trenched, 24" DIP 40.00 LF $ 260.00 $ 30.67 $ 7,974.20 30.67 $ 7,974.20 76.68% 9 4010 - 108 -C-1 Sanitary Sewer Force Main, Trenched, 30" DIP 1025.00 LF $ 163.00 $ 970.41 $ 158,176.83 970.41 $ 158,176.83 94.67% 10 4010 - 108 -0-2 Sanitary Sewer Force Main with Casing Pipe, Trenchless, 30" DIP 158.00 LF $ 425.00 $ 155.90 $ 66,257.50 155.90 $ 66,257.50 98.67% 11 5010 - 108 -C-2 Fittings by Weight, DI 12000.00 LBS $ 8.00 $ 10,720.00 $ 85,760.00 10720.00 $ 85,760.00 89.33% 12 4010. 108 -G -0 Sewage Air Release Valve and Pit 1.00 EA $ 9,500.00 $ 1.00 $ 9,500.00 1.00 $ 9,500.00 100.00% 13 5010- 108 -C -1 Joint Restraint - Retainer Gland 28.00 EA $ 800.00 $ 32.00 $ 25,600.00 32.00 $ 25,600.00 114.29% 14 5010 - 108 -C -1 Joint Restraint - Joint Hamess 2.00 EA $ 1,500.00 $ 1.00 $ 1,500.00 1.00 $ 1,500.00 50.00% 15 4010 - 108 -E -0 Sanitary Sewer Service Stub, 4" DIP 37.00 LF $ 90.00 $ - $ - $ 1.00 $ 34,000.00 100.00% Sub Total $ 34,000.00 Division 4020 - Storm Sewers Sub Total $ 354,768.53 $ $ Sub Total $ 354,768.53 16 4020- 108 -A -1 Storm Sewer Gravity Main, Trenched,18" RCP 80.00 LF $ 75.00 $ 80.00 $ 6,000.00 80.00 $ 6,000.00 100.00% 17 4020- 108 -C-0 Removal of Storm Sewer, Under 36" Dia. 80.00 LF $ 18.00 $ 185.00 $ 3,330.00 185.00 $ 3,330.00 231.25% Sub Total $ 9,330.00 $ $ - Sub Total $ 9,330.00 Division 5010 - Pipe and Fittings 18 5010 - 108 -A -1 Water Main, Trenched, DIP, 12" 55.00 LF $ 114.50 $ $ - $ 19 5010 - 108 -A -1 Water Main, Trenched, DIP, 8" 775.00 LF $ 69.00 $ 962.97 $ 66,444.93 962.97 $ 66,444.93 124.25% 20 5010 - 108 -A -1 Water Main, Trenched, DIP, 6" 75.00 LF $ 80.00 $ 57.83 $ 4,626.40 57.83 $ 4,626.40 77.11% 21 5010 - 108 -C -2 Fittings by Weight, DI 1200.00 LBS $ 6.00 $ 1,152.00 $ 6,912.00 1152.00 $ 6,912.00 96.00% 22 5010 - 108 -C -1 Fittings, Mega lug, 6" 13.00 EA $ 75.00 $ 11.00 $ 825.00 _ 11.00 $ 825.00 84.62% 23 5010 - 108 -C-1 Fittings, Mega lug, 8" 46.00 EA $ 105.00 $ 61.00 $ 6,405.00 61.00 $ 6,405.00 132.61% 24 5010 - 108 -C-1 Fittings, Mega lug, 12" 5.00 EA $ 200.00 $ - $ - $ - 25 5010- 108 -D -0 Water Service Stub, Copper, 3/4" 80.00 LF $ 60.00 $ 73:50 $ 4,410.00 73.50 $ 4,410.00 91.88% 26 5010-108-G-0 Removal and Salvage - Water Main Fittings and Appurtenances 1.00 LS $ 7,500.00 $ - $ $ 27 5010. 108 -E -0 Water Service Relocation, Copper, 2 ", Inc New Tap & Saddle 30.00 LF $ 70.00 $ $ $ - 28 5010 - 108 -C -1 Fittings, DI Sleeve, 6" . 4.00 EA $ 650.00 $ - $ - $ 29 5010 - 108 -C-1 Fittings, DI Sleeve, 8" 1.00 EA $ 725.00 $ 1.00 $ 725.00 1.00 $ 725.00 100.00% 30 5010- 108 -C-1 Fittings, DI Sleeve, 10" 1.00 EA $ 850.00 $ - $ - _ $ - Sub Total $ 90,348.33 $ $ Sub Total $ 90,348.33 Division 5020 - Valves, Fire Hydrants, and Appurtenances 31 5020 - 108 -A -0 Valve, Gate, DIP, 12" 32 5020- 108 -A -0 Valve, Gate, DIP, 8" 33 5020-108-A-0 Valve, Gate, DIP, 6" 34 5020- 108 -C-0 Fire Hydrant Assembly 35 5020-108-D-0 Flushing Device (Blowoff), 3/4" 36 5020. 108 -13-0 Tapping Valve Assembly, 8" Division 6010 - Structures for Sanitary and Storm Sewers 37 6010- 108 -A -0 Manhole Type, PC, 48" SW -303 1.00 EA $ 3,600.00 $ 1.00 $ 3,600.00 38 6010- 108 -G -0 Connection to Existing Intake 2.00 EA $ 900.00 $ 2.00 $ 1,800.00 Sub Total $ 5,400.00 Sub Total $ 1.00 EA $ 2,600.00 $ $ 4.00 EA $ 1,700.00 $ 7.00 $ 11,900.00 4.00 EA $ 1,400.00 $ 2.00 $ 2,800.00 2.00 EA $ 2,800.00 $ 2.00 $ 5,600.00 2.00 EA $ 1,250.00 $ 1.00 $ 1,250.00 1.00 EA $ 6,000.00 $ 1.00 $ 6,000.00 Sub Total $ 27,550.00 Sub Total $ Division 7010 - Portland Cement Concrete Pavement 39 7010-108-A-0 Pavement, PCC, 9" (Thickness) 1015.00 SY $ 46.00 $ 1,298.24 $ 59,719.04 40 7010- 108 -E -0 Curb and Gutter, 18" (Width), 6" (Thickness) 520.00 LF $ 22.00 $ 199.00 $ 4,378.00 Sub Total $ 64,097.04 Sub Total $ Division 7030 - Sidewalks, Shared Use Paths, and Driveways 41 7030- 108 -A -0 Removal of Sidewalk Division 7040 - Pavement Rehabilitation 65.00 SY $ 12.00 $ 86.49 $ 1,037.88 Sub Total $ 1,037.88 Sub Total $ 7.00 $ 11,900.00 175.00% 2.00 $ 2,800.00 50.00% 2.00 $ 5,600.00 100.00% 1.00 $ 1,250.00 50.00% 1.00 $ 6,000.00 100.00% Sub Total $ 27,550.00 1.00 $ 3,600.00 100.00% 2.00 $ 1,800.00 100.00% Sub Total $ 5,400.00 1298.24 $ 59,719.04 127.91% 199.00 $ 4,378.00 38.27% Sub Total $ 64,097.04 86.49 $ 1,037.88 133.06% Sub Total $ 1,037.88 42 7040- 108 -H -0 Removal - Pavement 2650.00 SY $ 8.00 $ 2,842.30 $ 22,738.40 2842.30 $ 22,738.40 107.26% 43 7040- 108 -A -0 Full Depth Patches PCC 45.00 SY $ 85.00 $ 182.00 $ 15,470.00 182.00 $ 15,470.00 404.44% 44 7040-108-A-0 Full Depth Patches PCC 170.00 SY $ 95.00 $ - $ - $ - 45 7040-108-L-1 Removal - Railroad Track 100.00 TLF $ 20.00 $ 57.00 $ 1,140.00 57.00 $ 1,140.00 57.00% 46 7040- 108 -A -0 Full Depth Patches HMA 1550.00 SY $ 30.00 $ 787.96 $ 23,638.80 787.96 $ 23,638.80 50.84% 47 7040 - 108 -K -1 Removal and Salvage - Historic Brick Paver 300.00 SY $ 15.00 $ 58.67 $ 880.05 58.67 $ 880.05 19.56% Sub Total $ 63,867.25 Sub Total $ Sub Total $ 63,867.25 Division 8030 - Traffic Control 48 1070 - 206 -A -0 Traffic Control 1.00 LS $ 60,000.00 $ 1.00 $ 60,000.00 1.00 $ 60,000.00 100.00% Sub Total $ 60,000.00 Sub Total $ - Sub Total $ 60,000.00 Division 9010 - Seeding 49 9010-108-A-0 Conventional Seeding, Seeding, Fertilizing, and Mulching 1350.00 SY $ 4.00 $ Sub Total $ - Sub Total $ - Sub Total $ Division 9040 - Erosion and Sediment Control 50 9040- 108 -A -1 SWPPP Preparation 1.00 LS $ 3,000.00 $ - $ 51 9040 - 108 -A -2 SWPPP Management 1.00 LS $ 1,500.00 $ 1.00 $ 1,500.00 52 Silt Fence or Silt Fence Ditch Check 1200.00 $ 3.00 $ - $ - Sub Total $ 1,500.00 Division 8010 - Traffic Equipment, lighting, Signals 53 8010- 108 -N.5 Removal - Street Light Pole 54 8010- 108 -N.4 Removal - Abandonment of CIP or PC Concrete Base 55 8010-108-N.2 Removal - Relocate Existing Light Pole and Precast Concrete Base 56 8010 - 108 -N.1 Removal - Existing Handhole 4.00 EA $ 800.00 $ 5.00 $ 4,000.00 5.00 EA $ 500.00 $ 5.00 $ 2,500.00 1.00 EA $ 2,500.00 $ - $ - 6.00 EA $ 500.00 $ 5.00 $ 2,500.00 Sub Total $ 9,000.00 Sub Total $ 1.00 $ 1,500.00 100.00% Sub Total $ 1,500.00 5.00 $ 4,000.00 125.00% 5.00 $ 2,500.00 100.00% Sub Total $ 5.00 $ 2,500.00 83.33% Sub Total $ 9,000.00 BASE AMOUNT EARNED TO DATE: $ 775,789.43 86.23% C.O. NO. CHANGE ORDER DESCRIPTION / EXTRA WORK ITEMS 1 Unloading of City Purchased Pipe - Portzen Inv # 0011496 -IN 2 101 -B Intake 3 2" Tap w/ Reconnect to Existing 4 1" Tap w/ Reconnect to Existing 5 Deduct: Repair of damaged casing pipe - Permalok Inv #707881 6 101 B Intake Inc Removal of Existing Intake 7 6" DIP Sanitary Sewer Lateral Stub 8 Credit Permalok Inv #707881 9 Pavement Striping and Sign Installation 10 Mulching Disturbed Area 11 4" PCC Sidewalk 12 Subqrade excavation on 9th street 13 14 15 LINE NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 CHANGE ORDER QUANTITY UNIT UNIT COST MATERIALS STORED ON -SITE (Invoice No & Supplier Name) 1307072 -IN J &R Supply 8307072 -IN J &R Supply 1308628 -IN J &R Supply 1308578 -IN J &R Supply 24" DIP CI 51 30" Retainer Gland 30" Joint Hamess 30" MJ 22.5 Bend 30" MJ 11.25 Bend 12x10 MJxMJ Reducer 6' Y95 Yard Hydrant 30" MJ Nitrile Gasket 1 LS $ 1,057.25 1 EA $ 2,500.00 1 LS $ 1,600.00 1 LS $ 1,300.00 1 LS $ (3,280.00) 1 LS $ 2,500.00 25 LF $ 93.00 1 LS $ 3,280.00 1 LS $ 1,200.00 5325 Sy_ $ 0.55 398 SF $ 5.00 167.5 Ton $ 15.00 $ $ - $ - PREVIOUS QUANTITY AMOUNT CHANGE ORDER QUANTITY UNIT UNIT COST 1.00 1.00 1.00 1.00 25.50 2.00 1.00 1.00 2.00 1.00 1.00 4.00 LS LS LS LS LF EA EA EA EA EA EA EA $ 100,697.00 $ 39,143.50 $ 3,260.00 $ 2,761.00 $ 93.00 $ 925.00 $ 1 395.00 $ 3,190.00 $ 2,870.00 $ 178.00 $ 595.00 $ 169.50 $ 1 $ 1,057.25 1 $ 2,500.00 1 $ 1,600.00 1 $ 1,300.00 $ 1 $ (3,280.00) $ 1 $ 2,500.00 $ 32 $ 2,976.00 $ 1 $ 3,280.00 $ 1 $ - 1,200.00 _ $ 5325 $ 2 928.75 $ 398 $ 1,990.00 $ 167.5 $ 2,512.50 $ CURRENT QUANTITY AMOUNT PREVIOUS QUANTITY AMOUNT TOTAL TO DATE QUANTITY AMOUNT Comp. 1 $ 1,057.25 100.00% 1 _$ 2,500.00 100.00% 1 $ 1,600.00 100.00% 1 _$ 1,300.00 100.00% 1 $ (3,280.00) 100.00% 1 $ 2,500.00 100.00% 32 $ 2,976.00 128.00% 1 $ 3,280.00 100.00% 1 $ 1,200.00 100.00% 5325 $ 2,928.75 100.00% 398 $ 1,990.00 100.00% 167.5 $ 2,512.50 100.00% Change Order Amount Eamed to Date: Total Amount Inc. Change Orders Eamed to Date: STORED MATERIALS CHANGE QUANTITY AMOUNT $ 20,564.50I $ 796,353.93 TOTAL TO DATE QUANTITY AMOUNT CIP NO. $ $ $ $ - $ $ 25.50 $ 2 371.50 25.50 $ 2,371.50 25.50 $ 2,371.50 7102413 2.00 $ 1,850.00 2.00 $ 1,850.00 2.00 $ 1,850.00 7102413 1.00 $ 1,395.00 1.00 $ 1,395.00 1.00 $ 1,395.00 7102413 1.00 $ 3,190.00 1.00 $ 3,190.00 1.00 $ 3,190.00 7102413 2.00 $ 5,740.00 2.00 $ 5 740.00 2.00 $ 5,740.00 7102413 1.00 $ 178.00 1.00 $ 178.00 1.00 $ 178.00 7402261 1.00 $ 595.00 1.00 $ 595.00 1.00 $ 595.00 7402261 4.00 $ 678.00_ 4.00 $ _ 678.00 4.00 $ 678.00 7102413 $ $ $ - Total Materials Stored to Date: $ $ $ 15,997.50 PAYMENTS PREVIOUSLY APPROVED: 1 $ 183,495.82 8 $ 2 $ 227,347.46 9 $ 3 $ 166,386.49 10 $ 4 $ 112,022.96 11 $ 5 $ 83,281.01 12 $ 6 $ - 13 $ 7 $ 14 $ Retainage $ TOTAL PAYMENTS FORWARDED: 39,817.70 $ 812,351.43 Project Summary CIP Earned to Date Retainage Ret. Release Amount to Date Contract Amt. 7102413 $ 484,562.91 $ 24,228.15 $ 24,228.15 $ 484,562.92 $ 553,948.90 7101899 $ 159,054.72 $ 7,952.74 $ 7,952.74 $ 7402261 $ 152,736.30 $ 7,636.81 $ 7,636.81 $ $ - $ $ $ $ $ $ - $ $ $ $ - $ $ $ - $ - $ $ $ $ - $ $ $ $ $ Total $ 796,353.93 $ 39,817.70 $ 159,054.72 $ 173,617.00 152,736.29 $ 172,056.60 39,817.70 $ 796,353.93 $ 899,622.50 Project Engineering Cost Summary Project Engineering Costs Total Eng. CIP Staff Consultant Cost 7102413 $ 38,731.00 + $ 91 310.33 $ 130 041.33 Bond Allocation $ 3,234.00 + $ 3 234.00 7101899 $ 9,632.31 + $ 16 724.90 $ 26 357.21 7402261 $ 9,280.68 + $ 12,746.50 $ 22 027.18 $ + $ $ + $ $ + $ $ + $ $ + $ $ + $ Total: $ 60,877.99 $ 120,781.73 $ 181,659.72 Project Cost / Funding Summary Construction Materials Total Eng. Total Project CIP CIP Costs Stored On -Site Cost Cost Funding 7102413 $ 484,562.91 $ 15,224.50 $ 130,041.33 $ 629,828.74 $ 850,767.00 Materials $ 150,198.00 $ $ 150,198.00 $ - 7101899 $ 159,054.72 $ $ 26,357.21 $ 185,411.93 $ 397,314.37 7402261 $ 152,736.30 $ 773.00 $ 22,027.18 $ 175,536.48 $ 430,209.59 Bond Allocation $ - $ - $ 3,234.00 $ 3,234.00 $ $ - $ - $ - $ - $ $ - $ - $ - $ - $ $ $ $ - $ - $ $ - $ $ $ $ $ $ - $ - $ - $ Total: $ 946,551.93 $ 15,997.50 $ 181,659.72 $ 1,144,209.15 $ 1,678,290.96 Final Project Cost Summary Total Amount Earned: $ 796,353.93 Stored Materials: $ 15,997.50 Total Due Contractor: $ 812,351.43 Purchased Materials: $ 150,198.00 Total Engineering: $ 181,659.72 Total Project Cost: $ 1,144,209.15 CERTIFICATE OF THE CITY MANAGER: I hereby certify that the above statement shows in detail e correct amount of all work required to complete the above improvement. APPROVED: APPROVED: Michael Van Milligen, City Manager City of Dubu. u Gus Psihoyos, City Engineer City of Dubuque, Iowa CERTIFICATE OF THE CONTRACTOR: The undersigned, Portzen Construction, Inc. contractor for the above improvement, does hereby accept the above "Total Due Contractor", as full settlement for all claims for said improvement. CONTRACTOR: yortzen Cbonstru ion Inc. BY: Z " G • TITLE: Z Q� DATE: