A.Y. McDonald Park ProjectTHF. Cll'Y OF DUB E ~`~- MEMORANDUM ,, December 21, 2006 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: A.Y. McDonald Park, Phase II Project Project #1703 Leisure Services Manager Gil Spence is recommending acceptance of the A.Y. McDonald Park, Phase II Project, as completed by Portzen Construction, in the final contract amount of $861,760.59. This is $12,106.69 over the original bid amount due to a change order for re-design of the fishing pier and council ring, and overages in project quantities, primarily in the areas of the number of shrubs needed and filter fabric needed in the landscaped areas. I concur with the recommendation and respectfully request Mayor and City Council approval. ~~ `till -'~.t,C~- Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gil D. Spence, Leisure Services Manager THE CITY OF Dus E MEMORANDUM ~-~ December 15, 2006 TO: Michael C. Van Milligen, City Manager FROM: Gil D. Spence, Leisure Services Manager SUBJECT: A.Y. McDonald Park, Phase II Project, Project #1703 INTRODUCTION The purpose of this memorandum is to recommend that the City Council accept the A.Y. McDonald Park, Phase II Project. DISCUSSION The A.Y. McDonald Park, Phase II Project has been completed by Portzen Construction in the final contract amount of $861,760.59. A summary of the project costs is as follows: construction contract change order #1 Bid Amount $ 849,653.90 $ 849,653.90 Final Cost $ 856,928.84 4,831.75 $ 861.760.59 The construction contract is $7,274.94 over the bid amount as a result of an overage in project quantities, primarily in the areas of the number of shrubs needed and filter fabric needed in the landscaped areas. Change order #1 provided for re-design of the fishing pier and council ring and increased the granular backfill required because extra grading was needed to remove topsoil to allow the backfill stone to be placed on sand that makes up the area. continued A.Y. McDonald Park, page two The C.I.P. budget contains $907,154 for this project. The following is a summary of the project costs: construction contract design fees inspection fees pier re-design Estimated $ 849,653.90 27,500.00 30,000.00 0 $ 907,153.90 Actual $ 861,760.59 14,329.00 47,000.00 9,000.00 $ 932,089.59 The project is $24,935.69 over budget which would be covered by using the Retaining Walls Project, $25,000. This project would have constructed retaining walls in areas to make them more level, not to replace existing walls. ACTION STEP The action requested is that the City Council adopt the attached resolutions accepting the improvement and setting the final cost. GDS:et attachments Preparers Gil D. Spence Address: 2200 Bunker Hill Rd Phone: (563) 589-4263 RESOLUTION NO. ACCEPTING IMPROVEMENT WHEREAS, the contractfortheA.Y. McDonald Park Development, Phase II Project has been completed and the City Manager has examined the work and filed his certificate stating that the same has been completed according to the terms ofthe contract, plans and specifications and recommends its acceptance. NOW, THEREFORE, BE IT RESOLVED, BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: 1. That the recommendation of the City Manager be approved and that said improvement be and the same is hereby accepted. BE IT FURTHER RESOLVED that the City Treasurer be and he is hereby directed to pay to the contractor from the General Fund in amount equal to the amount of his contract, less any retained percentage provided for therein. Passed, approved and adopted this day of , 2007. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, City Clerk PK Prepared by Gil D. Spence Address: 2200 Bunker Hill Rd Phone: (563) 589-4263 RESOLUTION NO. 5-07 ACCEPTING IMPROVEMENT WHEREAS, the contract for the A.Y. McDonald Park Development, Phase II Project has been completed and the City Manager has examined the work and filed his certificate stating that the same has been completed according to the terms of the contract, plans and specifications and recommends its acceptance. NOW, THEREFORE, BE IT RESOLVED, BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: 1. That the recommendation of the City Manager be approved and that said improvement be and the same is hereby accepted. BE IT FURTHER RESOLVED that the City Treasurer be and he is hereby directed to pay to the contractor from the General Fund in amount equal to the amount of his contract, less any retained percentage provided for therein. Passed, approved and adopted this 3rd day of January , 2007. Roy D. Buol, Mayor Attest:Jeaanne F. Schneider, City Clerk Prepared Gil D. Spence Address: 2200 Bunker Hill Rd Phone: (5631 589-4263 RESOLUTION NO. 6-07 FINAL ESTIMATE WHEREAS, the contract for the A.Y. McDonald Park Development, Phase II Project has been completed and the Engineer has submitted his final estimate showing the cost thereof including the cost of estimates, notices and inspection and all miscellaneous costs; NOW, THEREFORE, BE IT RESOLVED, BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the cost of said improvement is hereby determined to be $861,760.59, and the said amount shall be paid from the General Fund of the City of Dubuque, Iowa. Passed, approved and adopted this 3rd day of January , 2007. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, City Clerk Preparers Gil D. Spence Address: 2200 Bunker Hill Rd Phone: (563) 589-4263 RESOLUTION NO. FINAL ESTIMATE WHEREAS, the contract for the A.Y. McDonald Park Development, Phase II Project has been completed and the Engineer has submitted his final estimate showing the cost thereof including the cost of estimates, notices and inspection and all miscellaneous costs; NOW, THEREFORE, BE IT RESOLVED, BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the cost of said improvement is hereby determined to be $861,760.59, and the said amount shall be paid from the General Fund of the City of Dubuque, Iowa. Passed, approved and adopted this day of 2007. Attest: Jeanne F. Schneider, City Clerk Roy D. Buol, Mayor PK