Federal building Renovation Project_Budget Increase RequestTHE CITY OF DUB E MEMORANDUM January 10, 2007 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Dubuque Federal Building Renovation Project Project Manager Steve Sampson Brown is recommending that the Fiscal Year 2007 budget expenditure for the Federal Building Renovation Project be increased from $1,259,785 to $3,194,843. I concur with the recommendation and respectfully request Mayor and City Council approval. Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer Steven Sampson Brown, Project Manager THE CITY OF Dus E MEMORANDUM January 10, 2007 TO: Michael C. Van Milligen, City Manager FROM: Steven Sampson Brown, Project Manager~~" SUBJECT: Dubuque Federal Building Renovation Project INTRODUCTION This memorandum is to seek authorization to increase the Fiscal Year 2007 budget expenditure for the Dubuque Federal Building Renovation Project. BACKGROUND Recognizing that the Federal Building is an historic structure anchoring downtown, on September 6, 2005, the City Council directed City staff (Resolution 427-05) to prepare the formal application to General Services Administration (GSA) for the conveyance of the Federal Building to the City of Dubuque. Based on the building evaluation by Anderson Design that evaluated the existing condition of the building, it was projected that the renovation costs for the next five years would total just over $2.2 million and then another $2.0 million rehabilitation beyond would be required. The sources identified to finance the Federal Building improvements in the Fiscal Year 2007 - 2011 budget were: Use the Capital Improvement Project (CIP) for the renovation of the Housing & Community Development Department at 1805 Central Avenue (General Fund: $438,500; and Section 8: $71,500) Use of Port of Dubuque Property Acquisition CIP (DRA Distribution) Greater Downtown TIF Receipts DRA Distribution Use Cable Franchise fees to cover audiovisual/broadcast expenses Net operating income from the Federal Building (FY 2007 - 2011) Total Capital Sources in Fiscal Year 2007 - 2011 CIP * Amounts to be recovered from Greater Downtown CIP. $ 510,000* 700,000* 684, 500 200,000* 50.000* 55,705 $2,220,205 After the City took possession of the building on July 1, 2006, a determination was made to have the project architect, The Durrant Group, conduct more detailed studies of the existing condition and remaining service life of all mechanical (HVAC), electrical and window systems within the building. Since cost/benefit decisions of a particular mechanical system are interrelated to other supporting mechanical system upgrades, a comprehensive study was the only way to determine how to cost effectively upgrade each system. City staff involved with the operation of the Federal Building reviewed the recently- completed studies with Durrant to update the project's capital improvement plan. DISCUSSION On December 18, 2006, the City Council was provided an update on the overall capital costs based on the most recent study recommendations. The preliminary cost estimates are as follows: 1. Second Floor Renovations As part of this project, the former courtroom and two jury rooms on the second floor will be converted to a public meeting room, a small conference room, and local channel 8 cable TV studio. 2. Third Floor Renovations The City Housing & Community Development Department will move into the west and south areas of the third floor. The area being taken over by the Housing Department will be completely renovated by relocating interior walls, painting, flooring replacement, installation of voice and data systems, new furnishings and two new bathrooms will be constructed. 3. Miscellaneous Phase 1 Improvements - ADA improvements: Automatic door operators, existing door modifications, and bathroom modifications. - Replacement of second and third floor windows in the renovated areas. - Replacement of existing fire alarm system for renovated areas. - Dedication plaque. - Mechanical system improvements to second and third floor renovated areas only. - Exterior building sign and landscaping. - Green roof for the second floor light well. - Paint exterior spandrels. Total Phase I Construction Cost Total Phase I Design Cost Total Phase 1 Project Cost $3,263,328 326, 320 $3,589,848 In addition, the following improvements, with a cost estimate of $5,159,040 were identified for completion in the future years beyond Fiscal Year 2012: - Structural repairs to the loading dock and building foundation. - Building-wide replacement of the mechanical system with a new geothermal system and asbestos removal. - Kiosk on 2"d floor. - Fire alarm for remaining portions of building. - Emergency Operation Center. - Replacement of the existing windows with new steel windows, lead paint abatement, and window frame painting in remaining portion of building. - Reconstruction of rear building parking lot and associated stormwater drainage improvements. I recommend that the Fiscal Year 2007 budget be amended to increase the Dubuque Federal Building Renovation Capital Improvement Project (CIP) from $1,259,785 to $3,194,843 (additional $1,935,058) to cover Phase I improvements. The remaining $394,500 of Phase I costs will be recommended through the Fiscal Year 2008 budget process. BUDGET IMPACT The estimate for the project is as follows: Project Construction and Other Costs (Shown Above) Design Cost Total Estimated Cost $3,263,328 326, 320 $3,589,648 The additional cost of $1,935,058 to be amended in Fiscal Year 2007 is recommended to be funded using: General Fund Cash balance which includes land sale revenue and savings from Fiscal Year 2006 budget. Existing funding sources: Use the Capital Improvement Project (CIP) for the renovation from Housing & Community Development Department at 1805 Central Avenue (General Fund: $438,500; and Section 8: $71,500) Use of Port of Dubuque Property Acquisition CIP (DRA Distribution) Use Cable Franchise fees to cover audiovisual/broadcast expenses Recommended Fiscal Year 2007 Funding * Amounts to be recovered from Greater Downtown CIP. To be recommended through Fiscal Year 2008 Budget process. TOTAL PROJECT COST $1,935,058* 510,000* 700,000* 50,000* $3,195,058 394, 590 $3.589.648 ACTION TO BE TAKEN The City Council is requested to amend the Fiscal Year 2007 budget to increase the Dubuque Federal Building Renovation Project Capital Improvement Project from $1,259,785 to $3,194,843 to continue Phase I renovation. Prepared by Steven Sampson Brown, Project Manager cc: The Durrant Group Cindy Steinhauser, Assistant City Manager Dawn Lang & Jennifer Larson, Budget Directors David Heiar, Economic Development David Harris, Housing & Community Development Gus Psihoyos, City Engineer Rich Russell, Building Services