CIPP Lining Project Acceptance FY 2013_FY 2014Masterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager Dubuque band AI- America City 1 2007 • 2012 • 2013 SUBJECT: FY 2013 and FY 2014 Sewer Cured -in -Place Pipe (CIPP) Lining Project (CIPs FY 2013 & FY 2014 7101637, 7202332 and 7202333) DATE: February 13, 2014 City Engineer Gus Psihoyos is recommending acceptance of the construction contract for the FY 2013 and FY 2014 Sanitary Sewer Cured -in -Place Pipe (CIPP) Lining Project, as completed by Visu Sewer Clean and Seal, in the final contract amount of $411,181.90, which is 16.2% less than the original bid. I concur with the recommendation and respectfully request Mayor and City Council approval. Mic ael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Gus Psihoyos, City Engineer THE CITY OF DJUi Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer DATE: 10 February 2014 Dubuque hfrd ANUnedcaCily 1I l► I / 2007 • 2012 •2013 RE: FY2013 and FY2014 Sewer Cured -in -Place Pipe (CIPP) Lining Project (CIPs FY2013 & FY2014 7101637, 7202332 and 7202333) INTRODUCTION The enclosed resolution provides for the acceptance of the construction contract for the FY2013 & FY 2014 Sanitary Sewer Cured -in -Place Pipe (CIPP) Lining Project. BACKGROUND The FY2013 & FY 2014 Sanitary Sewer Cured -in -Place Pipe (CIPP) Lining Project was initiated under Resolution No. 165 -13 on June 3rd, 2013. The original scope of the project included 15,297 linear feet of sanitary sewer rehabilitation sewers by method of cured -in -place pipe as identified in the Sewershed 11 and 12 Corrective Action Plans and determined during maintenance activities. As the project was specialized in construction practices including materials and installation, pre - qualification statements were requested prior to the bid letting; the pre - qualification standards followed those listed in SUDAS. The City was successful in pre - qualifying six contractors for CIPP Lining; and Visu Sewer Clean and Seal of Pewaukee, Wisconsin was the successful bidder. The original scope also included sanitary sewer manhole lining, however, only one contractor prequalified for this portion of the work, therefore, to maintain competitive bidding, the manhole lining portion of the bid was removed. The total estimated value of the manhole lining was $25,713.00, and was removed via addendum, prior to bid. DISCUSSION The project was designed, inspected, and project managed by City Engineering staff and was completed on time and within the approved budget. Staff worked closely with the contractor to manage in field changes. One key change was the removal of lining 6 -inch diameter sanitary sewers. During televising, Visu Sewer's camera became lodged in a section of pipe and could not be retrieved without excavation. Based on the condition of the remaining 6 inch diameter lines, it was agreed to by both City Engineering and Visu Sewer that the contract be reduced to remove the 6 -inch diameter sanitary sewer rehabilitative work. This lead to a significant reduction of the contract, minus nominal costs associated with prepping part of a 6 -inch line. An additional section was also removed from the contract, Grove Terrace due to an access /egress conflict. In both situations, full sanitary sewer replacement will be coordinated in future budget years. Due to project savings, a length of sanitary sewer adjacent to the Brunskill Road bridge project was added to the contract. The final sanitary sewer length rehabilitated was 12,637 feet and 213 service reinstallations, with a final construction cost of $411,181.90, 16.2% less than the original bid. BUDGET IMPACT Resolution No. 165 -13 authorizing the FY2013- FY2014 Sewer Cured -In -Place Pipe (CIPP) Lining Project showed an estimated project cost including construction, contingency, and engineering of $615,000.00, the project was reduced significantly due to the above changes. The final costs versus the award for the FY2013 and FY2014 Sanitary Sewer Cured -in- Place Pipe (CIPP) Lining Project are as follows: Phase Construction (Visu- Sewer, Inc) Contingency (10 %) Engineering (15 %) Total Project Cost Award $490,792.20 $ 49,079.22 $ 73,618.83 $613,490.25 Final $411,181.90 $ 0.00 $ 61,677.29 $472,859.19 The project funding is as follows: CIP Funding Source Amount 7101637 Sanitary Sewer Lining program $409,710.39 (FY13 &FY14 Combined) 7202333 FY2014 Storm I &I Prevention Program 7202332 FY2013 Storm water l&I Brick MH Elimination Total Project Funding $ 38,148.80 $ 25,000.00 $472,859.19 RECOMMENDATION and ACTION respectfully request City Council accept the improvement in the final amount of $411,181.90 to Visu Sewer Clean and Seal of Pewaukee, Wisconsin for the FY2013 and FY2014 Sewer Cured -in -Place Pipe (CIPP) Lining Project by adoption of the attached resolution. cc: Denise Ihrig, Environmental Engineer Deron Muehring, Civil Engineer II Jenny Larson, Budget Director 2 RESOLUTION NO. 34 -14 ACCEPTING THE SANITARY SEWER CURED -IN -PLACE PIPE LINING PROJECT AND AUTHORIZING THE PAYMENT TO THE CONTRACTOR WHEREAS, the public improvement contract for the Sanitary Sewer Cured -in -Place Pipe Lining Project (the Project) has been completed has been completed by the Contractor, Visu Sewer Clean and Seal (Contractor), the City Engineer has examined the work and recommends that the Project be accepted; and WHEREAS, the final contract amount for the Project is $411,181.90; WHEREAS, the Contractor has previously been paid $390,622.81, leaving a balance of $20,559.09; and WHEREAS, the City Council finds that the recommendation of the City Engineer should be accepted. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor the balance of the retainage of $20,559.09 as provided in Iowa Code chapter 573, and to pay such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa Code chapter 26.13. Passed, approved and adopted this 17th day of February, 201 Attest: Ke /in S. Firnsta I, Ci" Clerk Roy D. f ol, Mayor CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE SANITARY SEWER CURED -IN -PLACE PIPE (CIPP) LINING PROJECT The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the Sanitary Sewer Cured -in -Place Pipe (CIPP) Lining Project, that the Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $472,859.19. Dated this day of rha €01, 2014. Filed in the office of the City Clerk on the/l day of C , 2014. Gus Psihoyos, City Engineer 4dOr / Kevi . Firnstah rte7City Clerk THSCTR OF DUB Mr- Mfio'n on the Miooissilpi PROJECT NAME: ITEM NUMBER CONTRACTOR: ADDRESS: CITY, STATE, 211a : City of Dubuque - Engineering Division Project Close Out Form FY13 8 FY14 (CIPP) Sewer Lining Project waS ewer, Inc. W230 94855 Betker Dr. Peweukee, WI. 53072 B10 ITEM DESCRIPTION 1310slon 4050 -Pipe Rehabilitation 1 4050-108-A-0 Pipe Legg. CIPP.5 2 4050.108,4-0 Pare Laing. CIPP, B' 3 4050-1088-0 Pipe 100. CIPP. 12- 4 4050.108-4-0 Pipe LrS., CIPP.24' 5 4050- 108 -B-0 Bu3dug5anitary Sewer Sere. Rocon,eciun 6 4050 - 108-0 -1 Chore., GroiA. of Sanary Sewer Ores FINAL CONTRACT AMOUNT: $ CONTRACT QUANTITY UNIT UNIT COST 011PLSIon 8030 -Tra Mc Control 7 1170T252804-A Traffic Control 411 181.00 PREVIOUS TOTAL TO DATE QUANTITY AMOUNT CURRENT QUANTITY AMOUNT COUNCIL ACCEPTANCE DATE: 17- Feb -14 TOTAL TO DATE QUANTITY AMOUNT COMP. 1176.00 15 6 3200 0 - 0 - 120700 LF 0 25.60 $ 10.89400 0 278.888.40 16000 LF S 3560 0 749.00 $ 27.338.50 71400 LF 0 7800 $ 704.00 0 54,91200 297.00 EA 0 12500 0 21300 0 26,82500 10000 GAL $ 4500 E - 0 - SubTntat S 387,781.00 Sub Total 0 100 LS 0 50000 $ 100 $ 50000 MANGE ORDER DESCRIPTION /EXTRA WORX ITEMS 1 Addition of 6' prepping 190LF(Cooper A. Maiden In_ Custer St.) 2 404400 d8 - propping =4H, (Grove Terrace) 3 Ackfitton of 8' prepping = 8 H0701 Marys St) 4 Addtio5 of 18' Laifg 11 0681F (Brussb8 Rd) CEWI i ORDER OUANTIIY UNIT UNIT COST Sub Total 0 500.00 PREVIOUS QUANTITY AMOUNT 100 LF 0 203 190 $ 38000 4 Ws $ 23500 4 0 910.00 8 His 0 23500 8 $ 1.88000 290 LF 0 8800 290 0 19,72800 1089400 74900 1000 21300 278,88840 80.43% 21.338 9855% 5491200 9860% 26.62500 71.72% Sub Total 0 Sub Total 1.00 Sub Total BASE AMOUNT EARNED TO DATE: CURRENT QUANTITY AMOUNT 387,16190 500.00 100.00% 50000 S 368.261.90 TOTAL TO DATE QUANTITY /9A01846 PAYMENTS PREVIOUSLY APPROVED: 1 $ 327.$0709 8 $ - 2 $ 03,115.72 0 $ - 3 $ - 10 $ - 4 $ - 11 1 - 6 $ - 12 0 - 8 $ - 13 0 - 7 0 - 14 3 - Re91sar3e $ 20559.09 TOTAL PAYMENTS FORWARDED: Is 411,181.901 19000 E 400 E 800 $ 290.00 Change Order Amount Earned to Data: 7001 Amount Inc. Charge Orders Earned to Date: 0.43% Comp. $ 380.00 100.00% $ 940.00 100.00% 0 1.880.00 1o0.00% 0 19.72000 100.00% I s 22,920.001 1 $ 411,181.901 Project Summary DIP Earned to Data 00010aq Ref. Release Amount to Date 00dn00Ant. 7101837 7202312 7202333 356.269.00 0 17,81350 0 - S 338,45841 21,739.13 0 1.08898 0 0 20,65218 33,112.87 0 1,65884 0 0 31,51422 3 - $ - $ 0 - $ - 0 _ - 0 - 0 - $ - - 0 - $ - - $ - 0 435.10020 21.84600 27.84800 Total 411,181.00 $ 20,559.10 $ - 3 390,62281 490,792.20 Project Engineering Cost Summary Project Engineering Costs Total Erg CIP 5856 Consultant Cost 7101537 $ 53,440.49 + $ 53.44049 7202332 $ 3260.87 + S 32H1.87 7202333 $ 4,97593 4.97593 $ $ $ • - 5 $ $ E 5 Total: 3 68677.29 $ 61.6 Final Project Cost Summary Total Amount Earned: $ 411,181.00 Stored Materiels: $ Total Due Contractor: $ 411,18190 Total Engineering: 5 01,877.29 Total Project Cost: $ 472,859.19 CERTIFICATEAF THE CITY MANAGER: I hereby certify that the above statement shows in APPROVED: APPROVED: correct amount of all work required to complete the above improvement. Michael Van Milligan, City Manager _ City of Dubuque, Iowa Gus PsRgyos, City Engineer City of Dubuque, Iowa CERTIFICATE OF THE CONTRACTOR: The undersigned, Visu - Sewer, Inc. contractor for the above improvement, does hereby accept the above "Total Due Contractor, as full settlement for all claims for said improvement. CONTRACTOR: BY: TITLE: DATE: Project Cost I Funding Summary CIP Construction Costs Stored Materials Total Eng. Total Project OOS4s Cost Cost CIP F000g 7101637 $ 356269.90 $ - 6 53,44049 409,71039 $ 440,00000 7202332 $ 21,739.13 $ - 6, 3.26087 25,000.00 $ 25.00000 7202333 5 33.17287 5 - $ 4,97583 38,14820 5 150.00000 $ $ 5 - - $ - $ - 5 - 5 - - $ - $ - 5 - $ - - 5 - 5 - 5 - $ - - $ $ - $ - $ - $ - $ 5 - $ - - 5 - $ - $ - $ - - $ Total: 5 411,181.90 $ - 8 61,67729 5 472,859.19 $ 616000.00 Final Project Cost Summary Total Amount Earned: $ 411,181.00 Stored Materiels: $ Total Due Contractor: $ 411,18190 Total Engineering: 5 01,877.29 Total Project Cost: $ 472,859.19 CERTIFICATEAF THE CITY MANAGER: I hereby certify that the above statement shows in APPROVED: APPROVED: correct amount of all work required to complete the above improvement. Michael Van Milligan, City Manager _ City of Dubuque, Iowa Gus PsRgyos, City Engineer City of Dubuque, Iowa CERTIFICATE OF THE CONTRACTOR: The undersigned, Visu - Sewer, Inc. contractor for the above improvement, does hereby accept the above "Total Due Contractor, as full settlement for all claims for said improvement. CONTRACTOR: BY: TITLE: DATE: