Loading...
Grand River Center FloorSettlement Remediation Project AcceptanceMasterpiece on the Mississippi TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Grand River Convention Center Floor Settlement Remediation Project (CIP 3501991) DATE: February 11, 2014 Dubuque band AI- America City 1 2007 • 2012 • 2013 Assistant City Engineer Bob Schiesl recommends acceptance of the construction contract for the Grand River Convention Center — Floor Settlement Remediation Project, as completed by Hayward Baker, in the final contract amount of $454,902.97, which is an 81.6% increase from the original estimated contract amount of $250,500. The primary reason for the additional cost for the Floor Settlement Remediation Project was the increased number of working days that were used. Initially, Hayward Baker estimated a daily production rate of 10 deep compaction points per day based on past experience, for an estimated 27 total working days. However, based on the challenges encountered due to the variable subsurface conditions, crews were only able to achieve an average of 5 production grout columns per day, resulting in a total of 51 working days required to complete the deep compaction remediation work. The total cost for the 24 additional working days was $134,000. Additional costs of $68,000 were incurred due to the increased quantity of high density polyurethane foam grout that was used to raise and re -level the main floor areas. I concur with the recommendation and respectfully request Mayor and City Council approval. Mic ael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Gus Psihoyos, City Engineer Robert Schiesl, Assistant City Engineer 2 Masterpiece on the Mississippi TO: Michael C. Van Milligen, City Manager Gus Psihoyos, City Engineer FROM: Robert Schiesl, Assistant City Engineer R03 SUBJECT: Grand River Convention Center Floor Settlement Remediation Project (CIP 3501991) DATE: February 11, 2014 Dubuque AI-America city 2007 • 2012 • 2013 INTRODUCTION The enclosed resolution provides for the acceptance of the construction contract for the Grand River Convention Center - Floor Settlement Remediation Project. BACKGROUND During the February 2012 monthly visit, the Grand River Center (GRC) showed signs of accelerated floor slab settlement in the escalator area, but the settlement had also moved laterally outward to the administrative offices, lobby and pre- functions areas. A request was immediately made to Assistant City Engineer, Bob Schiesl, to have him inspect the concerned area because he had worked with the settlement problem in the prior years. In March 2012, the City's survey crew measured baseline elevation readings throughout the main floor areas of the lobby, pre- function, restroom and offices. Based on the recorded elevations, settlement readings ranged from .25 inches to 2.64 inches, with the most significant settlement occurring at the base of the escalators (2.64 "). During this same time period, the escalator was experiencing operational issues and the escalator service technician was called in to review. Based on the magnitude of the settlement at the base of the escalator and the rotational movement observed at the top of the escalator, the decision was made to turn off the escalator in the interest of public safety and to prevent any further damage from occurring. Upon further inspection of the GRC, it did not appear that any of the building structure that is supported on deep foundation auger cast piling showed signs of distress or movement. This included the second floor conference rooms, the river room, and the underground parking structure. It appeared that the primary main floor areas of the GRC that are experiencing the majority of the settlement are those areas supported by stone column foundations. It should be noted that minor settlement of the GRC was anticipated during the original design of the structure. The original 2002 Terracon report reported the soil conditions beneath the now - existing structure as a fill material to a depth of approximately 15 to 22 feet. This fill material was reported to be highly variable and composed of a combination of sand and clay, cinders, wood chips and fragments, and organics. Based on the pre- existing soil conditions and the geotechnical engineering foundation recommendations, the report indicated the structure could experience long term settlement to the magnitude of 1 inch. What remains uncertain is why over the last 6 months the structure has experienced such a rapid and accelerated degree of settlement at the main floor slab -on -grade areas. Floor Settlement Remediation The geotechnical engineer of record, Terracon, and the deep foundation contractor for the GRC, Hayward Baker, were called in to inspect the observed settlement locations and evaluate non - destructive repairs and remediation alternatives. When the GRC was constructed, the foundation system called for approximately 6 feet of compacted engineered fill to be placed over the stone columns and beneath the main floor slab -on -grade areas. This was confirmed by the 2007 subsurface borings performed around the escalator area which indicated an engineered fill layer was present at the boring locations to depths ranging from about 6 to 7% feet below the floor slab. The subsurface investigation also indicated that the fill material under the floor slab appeared to be of high density and no apparent voids were encountered directly under the slab. As a result of our investigations, it was our opinion that the engineered fill layer directly under the slab is not likely responsible for the larger than expected settlement observed to date. Based on the original 2002 Terracon geotechnical report, the deep soil conditions beneath the now - existing structure are highly variable and consist of miscellaneous fill materials, including sand, clay, limestone and concrete fragments, brick, cinders, wood chips /sawdust and other organic materials, which extended to depths ranging from about 8 to 23 feet beneath the original ground level. Due to the depth and variable composition of the subsurface fill material, both City staff and Terracon felt that the deeper variable fill layers needed to be improved or densified to reduce the risk of future settlements while also stabilizing and supporting the building structure on a more competent soil layer located deep beneath the original ground level. The Hayward Baker remediation methods implemented provided a more technical and comprehensive approach for both Tong -term settlement control and improving the existing slab -on -grade conditions on site in the short-term. The remediation work completed by Hayward Baker included the installation of 242 deep compaction grout locations, to a depth of 21 to 24 feet below the main floor areas of the entrance lobby, pre- function space, restrooms, administrative offices and the rear loading dock area. Approximately 382 cubic yards of compaction grout material was injected to densify and stabilize the variable fill materials and provide additional supplemental support to the existing stone column foundations and improve support under the existing floor slab areas. Approximately 17,200 pounds of high density polyurethane foam grout was used to raise and re -level the main floor areas. To repair the escalators, four (4) micro piles were driven 60 feet below the base of the escalator pit foundation which were used to support the escalator Toad and to hydraulically jack and raise the escalator pit foundations back to the original elevation. DISCUSSION The Grand River Convention Center - Floor Settlement Remediation Project was completed by Hayward Baker of Roselle, IL in the final contract amount of $454,902.97, which is an 81.6% increase from the original estimated contract amount of $250,500. However, the total overall project cost to remediate, repair and restore the Grand River Convention Center main floor settlement areas was $591,233.97, which is a 6.2% increase ($39,633.97) from the original total project estimate amount of $551,600.00. The primary reason for the additional cost for the Floor Settlement Remediation Project was the increased number of working days that were used. Initially, Hayward Baker estimated a daily production rate of 10 deep compaction points per day based on past experience, for an estimated 27 total working days. However, based on the challenges encountered due to the variable subsurface conditions, crews were only able to achieve an average of 5 production grout columns per day, resulting in a total of 51 working days required to complete the deep compaction remediation work. The cost for the 24 additional working days was $134,000. Additional costs were also incurred ($68,000) due to the increased quantity of high density polyurethane foam grout that was used to raise and re -level the main floor areas. Initial quantity estimates were based on the assumption that more lift would be provided by the installed supplemental grout compaction columns, however due to the 6 to 7 feet of highly compacted engineered fill in- placed over the stone columns and beneath the main floor slab -on -grade areas, the final raising and re- leveling the floor was completed using the polyurethane grout material. RECOMMENDATION recommend that the City Council accept the public improvements and authorize the final payment of the contract amount of $454,902.97 to Hayward Baker of Roselle, IL for the Grand River Convention Center - Floor Settlement Remediation Project. BUDGET IMPACT The project cost summary to remediate, repair and restore the Grand River Convention Center main floor settlement areas is as follows: Completed Work Items Estimate Final Floor Settlement Remediation $ 250,000.00 $ 454,902.97 Janitorial Cleaning Service 15,000.00 13,739.50 Escalator Service and Repair 75,000.00 29,764.85 Decorative Concrete Replacement 35,000.00 22,925.00 Carpet Replacement 50,500.00 800.00 Restroom Tile Replacement 10,000.00 4,009.95 Drywall & Ceiling Tile Repair 10,000.00 9,500.00 Painting 10,000.00 2,985.49 Interior Electric / Plumbing Locates & Repairs 9,236.23 GRC - HVAC System Filter Replacement 3,017.14 Contingency 45,550.00 Construction Engineering, Administration & Inspection 50,000.00 $40,352.84 Total Project Cost $ 551.050.00 $ 591,233.97 The project funding summary is as follows: CIP No. Fund Description Fund Amount 3501991 Grand River Center Floor Leveling $ 45,279.00 1002198 Grand River Center Mechanic Room Screen 12,000.00 1022113 Grand River Center Replace Carpet 70,768.00 1002197 Grand River Center Paint Exhibit Hall 70,203.00 1022391 Grand River Center Office Painting 35,000.00 1021214 Veteran's Memorial Ball Field 130,250.00 Total Project Funding $ 363,500.00 In the fall of 2012 staff identified capital improvement project funding sources, including several for the Grand River Center as well as the Veteran's Memorial Ball Field project that could be used for the Floor Settlement Remediation Project. As part of the FY13 budget amendment process, those identified funds were shifted to the Grand River Center Floor Leveling budget, CIP 3501991. Now that the Floor Settlement Remediation Project is completed and all other project related costs are compiled, the total overall project cost is $591,233.97. This final project cost is an increase of $227,733.97 over the adjusted Grand River Center Floor Leveling budget amount of $363,500. To fund the shortfall, staff has identified a revenue source from the future sale of Urban Renewal Bonds that are payable to the Greater Downtown TIF. CIP No. Fund Description Fund Amount 3501991 Grand River Center Floor Leveling $ 363,500.00 Revenue from Greater Downtown TIF Urban Renewal Bond 227,733.97 Total Project Funding $ 591,233.97 ACTION TO BE TAKEN I respectfully request that the City Council adopt the attached resolution to accept the public improvements for and to authorize the final payment of the contract amount of $454,902.97 to Hayward Baker for the Grand River Convention Center - Floor Settlement Remediation Project. cc: Jenny Larson, Budget Director Marie Ware, Leisure Services Manager Chris Lyons, Engineering Technician F: \PROJECTS \GRCC - Grand River Convention Center Repairs \Floor Settlement Repairs 2012 \Council & Staff Documentation\Acceptance \Grand River Center Floor Settlement Repairs - Staff Accept Memo RESOLUTION NO. 35 -14 ACCEPTING THE GRAND RIVER CONVENTION CENTER - FLOOR SETTLEMENT REMEDIATION PROJECT AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR Whereas, the Public Improvement Contract for the Grand River Convention Center - Floor Settlement Remediation Project (the Project) has been completed and the City Engineer has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and that the City Engineer recommends that the Project be accepted; and NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor from the Grand River Center Floor Leveling capital improvement appropriation for the contract amount of $454,902.97 less any retained percentage provided for therein as provided in Iowa Code chapter 573, and to pay such retainage only in accordance with the provisions of Iowa Code chapter 573. Passed, approved and adopted this 17th day of February, 2014. Attest: Kev Firnstahl, CM 3 ity Clerk Roy D. Buol, Mayor CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE GRAND RIVER CONVENTION CENTER - FLOOR SETTLEMENT REMEDIATION PROJECT The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the Grand River Convention Center - Floor Settlement Remediation Project, and that said Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $591,233.97. Dated this 2014. Gus Psihoyos, Cit Filed in the office of the City Clerk on the / day of ngineer 2014. 07-Ar:P" Kevi S. Firnstahl, CMC w ity Clerk LINE NO. 1 2 3 PARTIAL PAYMENT NO: COUNCIL FINAL ITEM NUMBER PROJECT NAME: Grand River Convention Center Floor Settlement Remediation Project City of Dubuque - Engineering Department Project Close Out - Final Payment Form CONTRACTOR: Hayward Baker, Inc. ADDRESS: 1350 W Lake Street CITY, STATE, ZIP: Roselle, IL 60172 BID ITEM DESCRIPTION MOBILIZATION/DEMOBILIZATION AMOUNT OF CONTRACT AMOUNT: $ TOTAL CHANGE ORDERS TO DATE: CONTRACT QUANTITY ADJUSTMENT: $ REVISED CONTRACT AMOUNT: $ CONTRACT QUANTITY UNIT UNIT COST MICROPILES 4 5 GROUTING CREW & EQUIPMENT (Up to 10 -Hrs / Shift) COMPACTION GROUTING MATERIAL POLY GROUT CREW & EQUIPMENT (Up to 10 -Hrs / Shift) 6 POLYURETHANE GROUTING MATERIAL 250,500.00 204,402.97 454,902.97 PREVIOUS TOTAL TO -DATE QUANTITY AMOUNT THE CITY OF DUB Masterpiece on the Mississippi CURRENT PAY PERIOD QUANTITY AMOUNT PAYMENT PERIOD FROM: TO: October 22, 2012 November 3, 2013 FINAL QUANTITY AMOUNT COMP. 1.00 US $ 15,000.00 1.00 $ 15,000.00 $ 1.00 $ 15 000.00 100.0% 4.00 EACH $ 3,750.00 4.00 $ 15,000.00 $ 4.00 $ 15,000.00 100.0% 27.00 Shift $ 5,600.00 50.85 $ 284,760.00 $ 50.85 $ 284,760.00 188.3% 440.00 CY $ 115.00 381.20 $ 43,838.00 $ 381.20 $ 43,838.00 86.6% 10.00 Shift $ 1,000.00 18.30 $ 18,300.00 5.00 $ 5,000.00 23.30 $ 23,300.00 233.0% 4400.00 LBS $ 4.25 16582.94 $ 70,477.50 594.70 $ 2,527.47 17177.64 $ 73,004.97 390.4% AMOUNT EARNED TO DATE: TOTAL DUE CONTRACTOR: JANITORIAL SERVICES: ESCALATOR REPAIRS: DECORATIVE CONCRETE: CARPET REPAIR: RESTROOM TILE REPLACEMENT: DRYWALL REPAIR: PAINTING: ELECTRIC / PLUMBING REPAIR: HVAC FILTER REPLACEMENT: CONSTRUCTION ADMINISTRATION: TOTAL CONSTRUCTION COST: $ 454,902.97 $ 454,902.97 $ 13,739.50 $ 29,764.85 $ 22,925.00 $ 800.00 $ 4,009.95 $ 9,500.00 $ 2,985.49 $ 9,236.23 $ 3,017.14 $ 40,352.84 $ 591,233.97 FINAL PROJECT FUNDING SUMMARY CIP Total Earned to Date 3501991 -73210 $ Previous Total Earned to Date 454,902.97 $ Total Current Amount Earned Less Current Current Amount Current Retainage Earned Less Retainage Retainage Release 425,009.00 $ 29,893.97 $ $ 29,893.97 $ Previous Current Total Final Materials Stored Materials Stored Amount Due $ 29,893.97 TOTAL: $ 454,902.97 $ 425,009.00 $ 29,893.97 $ $ 29,893.97 $ $ - $ $ 29,893.97 CERTIFICATE OF THE CITY MANAGER City of Dubuque - Engineering Department Project Close Out - Final Payment Form PARTIAL PAYMENT NO: COUNCIL FINAL PROJECT NAME: Grand River Convention Center Floor Settlement Remediation Project CONTRACTOR: Hayward Baker, Inc. ADDRESS: 1350 W Lake Street CITY, STATE, ZIP: Roselle, IL 60172 rt- t6 Crri 01' — DUBU- ?vjrrsfer7'iccc nn the Mis$issil AMOUNT OF CONTRACT AMOUNT: $ 250,500.00 PAYMENT PERIOD TOTAL CHANGE ORDERS TO DATE: FROM: October 22, 2012 CONTRACT QUANTITY ADJUSTMENT: $ 204,402.97 TO: November 3, 2013 REVISED CONTRACT AMOUNT: $ 454,902.97 CERTIFICATE OF THE CITY MANAGER To the best of my knowledge and belief, I hereby certify that the above statement shows in detail the correct amount of all work required to APPROVED: / \ APPROVED: Michael Van Milligen, City Manager Gus Psihoyos, City Engineer City of Dubuque, Iowa City of Dubuque, Iowa mplete the above improvement. CERTIFICATE OF THE CONTRACTOR The undersigned, Hayward Baker, Inc. contractor for the above improvement, does hereby accept the above "Total Due Contractor", as full settlement for all claims for said improvement. CONTRACTOR: Hayward Baker, Inc. DATE: BY: TITLE: QvDcLt kC,V\ C C (i/