Loading...
Eagle Point Concrete Change Order~~ ~ ~ THE CITY OF DuB E ~-~-~ MEMORANDUM January 26, 2007 TO: Michael C. Van Milligen, City Manager FROM: Gil D. Spence, Leisure Services Manag SUBJECT: Eagle Point Concrete Replacement Project Attached is the second change order for the Eagle Point Park Concrete Replacement Project. I had sent a previous memo explaining the need for the first three items. We discovered the 4" x 6" support around the entire Riverfront Pavilion to be rotted and in need of replacement. The last item powder coats the new railing and will reduce maintenance in the long run. The first change order at the Shiras Memorial pavilion was $2,983.53 so change orders total $31,452.75. There was an $18,300 contingency and there was $1,861 in added design fees that reduces the contingency to $16,439. This means the project is $15,013.75 over budget and I recommend funds be taken from Eagle Point Stone Work to cover this overrun. Please sign the change order and return to me. Thanks. GDS:et attachment ;" /~ . CHANGE ORDER Distribution to: Owner • Architect Contractor Field _~ Other ,:.-:. ..rii.$::.i:4':iirr'f.+/.•:?:: ~:ii:??G: R: iiii:?•ii:4 :•ri?•isG%•ii:~}'I.C!6'F..iif+ii~:i:?+l•4:?ri'r.+fl.!4i::!•: i:•::+i::1i.?•iiiii:+.•iri!?!•iii::+i.•:~~:^:?^:+.4if.4:4:?{?+ririiii +•: is ~:•ii'/.: ;r:+., rOw .. r .. .... ... .. .......:.. PROJECT: Eagle Point Concrete replacement CHANGE ORDER #1 TO DATE: 01/08/07 City of Dubuque PROJECT NO: Leisure Services Attention: Gil Spence CONTRACT FOR: CONTRACT DATE: VARIATION IN REQUIRED WORK OR MATERIALS FROM THAT SPECIFIED IN THE PROJECT DOCUMENTS SHOULD HE BROUGHT TO THE ARCHITECT'S AND THE GENERAL CONTRACTOR'S IMMEDIATE ATTENTION. ADJUSTMENT IN CONTRACT PRICE SHALL BE AGREED UPON IN WRITING BEOFRE ANY INSTALLATION IS MADE. OTHERWISE THE OWNER SHALL ASSUME THAT NO PRICE ADJUSTMENT WILL BE NECESSARY. River Front East Side: Remove and replace 5'-6' Concrete Walk in front of Pavilion Bid $6,652.00 Bond 133.04 $6,785.04 Remove rotted 4'x 6's, 4" siding, Jack up ceiling and roof. To put in new walminized 4'x 6's. Bid $2000.00 Bond 40.00 $2,040.00 Remove and replace the concrete out 5'-6" , Rotted 4x6's and siding on the North, South and West side Of Pavilion Bid $12,592.00 Bond 251.84 $12,843.84 Additional Saw cutting, rope caulk, and Caulking change from original plan to new plan layout Dated November 13, 2006. 420'-6" Bid $2,103.00 Bond 42.06 $2,145.06 Clean and Powder coat Railing in lieu of Painting. Powder Coat $3,050.00 Sand Blast $1,514.00 Bond 91.28 $4,655.28 Total Amount of Change Order # 1 Add: $28,469.22 SIGNATURE OF THE CONTRACTOR IIIDICATES THIS AGREEMENT HEREWITH, INCLUDING ANY ADJUSTMENT IN THE CONTRACT SUM OR CONTRACT TIME. Authorized: Kluck Construction, Inc. Contractor er 14285 Hwv 20 West A ess Y Date: JAN-25-2007 THU 03 16 PM KLUCK CONSTRUCTION, INC. FAX N0. 563 556 2285 P, 03 CHANGE Distribution to: ORpER Owner E" Architect <'" Contractor ~"` Field Other ""' P120JECT: Eagle Point 6ew.*ete replacement CHANGE O~.tpER #fi ~I~G~ TO City of Dubuque Leisure Services Attention: Cril Spence DATE' 01/08/07 FROJECT NO: CONTRACT FOR: Eagles nest COI~T1tACT DATE: VARIATI02V IIJ 1tfltlU1RED WORK ~7R MA78RLALS r'AOM THAT BPHOIRJED 7N THE IntOJJiCT DOCUMENTS SIiOUI.D SE BROUGHT 70 THE ARCHITECT'S AND THE GRNrRA1. CONTRACT'OR'S DrA~DfATii ATTma'ciOrT. ADJUSTMENT IN CANTR ACT PRICE 9HAJ.L $B ACiRBBD UPON A~ WRITIIQO HSOF72B ANY• IIISTALLATION IS ~. o1~iBRWJSE THE OwNmt SHALL A99~IAvffi THAT NO PRTCB ADIU3TMFiNT WQ.L J3E NECB$SARY. Remove and replace rotted 2 x 6" $500.00 Remove plywood and framing, Frame and install new teinpercd sky litcs. $4,962.52 Total Amount of Change Order # 1 Add: $5,462,52 4TCNATVRS OF Ttlti CONTRACTOR JPiDICATES TH[3 AGREEMENT HBRLRVITFL INCL1.mJN4 ANY ApJt]STtv18N7' JN THb CONTRACT 9UM CR CONTRACT TIIvffi. `L ~ er ess y; Date: ..~«rs;,aa~w;l~,~k:a~nzs~:r:~wv#~~c~:4t~:r~st~rrr^~~'~,~wazK.s~s~rax, .: z~;~~~ark'~i~~, Authorized: Kluck Construction, lnc. Contractor