Loading...
Five Year Street Program FY 08_12THE CITY OF DUB E ~-~~ MEMORANDUM January 30, 2007 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Five-Year Street Construction Program for Fiscal Years 2008-2012 City Engineer Gus Psihoyos is recommending City Council approval of the Annual Five- Year Construction Program for Fiscal Years 2008-2012. This will allow the Engineering Department to initiate the bidding process for the Fiscal Year 2008 (Calendar Year 2007/2008) Annual Street Construction Program beginning in February 2007, when contractors are aggressively pursuing work for the upcoming construction season. I concur with the recommendation and respectfully request Mayor and City Council approval ~ ~~~~ Michael C. Van Milligen MCVM/jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Gus Psihoyos, City Engineer THE CITV OF DuB E MEMORANDUM ~-~~ February 1, 2007 TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer , ~ _ _ SUBJECT: Five-Year Street Construction Program for Fiscal Years 2008-2012 INTRODUCTION The enclosed resolution provides for the City Council approval of the Annual Five-Year Street Construction Program for Fiscal Years 2008-2012. DISCUSSION The Five-Year Street Construction Program for Fiscal Years 2008-2012, which is part of the Five-Year Capital Improvement Projects, includes the estimated costs for the street construction work and the anticipated year during which each project will be undertaken. The Five-Year Street Construction Program is considered annually by the City Council as part of the budget process. The Iowa Department of Transportation (IDOT) provides annual projections on the amount of Road Use Tax (RUT) Funds the City of Dubuque will receive over the next five years based on a per capita amount. In FY2007, the IDOT estimates were revised causing a decrease in RUT funds from the prior year of $1,111,696 over five years. In December 2006, the IDOT impact was reduced $92,298 more over five years. Because of this anticipated funding shortfall, the Five-Year Street Construction Program has been developed with this funding reduction in mind. In this year's street program the Foye/Merchant/Gold Reconstruction Project from West Locust to Napier has been moved through the budget process to Fiscal Year 2009; it was originally scheduled for Fiscal Year 2011. This change was possible through the elimination of the Fiscal Year 2009 Hodgdon Street Steps Project. Further information on the Fiscal Year 2008 - 2012 Street Construction Program will be provided at the Engineering budget presentation. Because the winter months are the most opportunistic for soliciting competitive bids and contractors are aggressively pursuing work for the upcoming construction season, the Engineering Department would like to initiate the bidding process for the FY2008 (Calendar 2007-2008) Annual Street Construction Program beginning February, 2007. The City Council is requested to adopt the Five-Year Construction Program for Fiscal Years 2008-2012 prior to the Fiscal Year 2008 budget approval in March. RECOMMENDATION recommend that the City Council accept the Annual Five-Year Construction Program for Fiscal Years 2008-2012. ACTION TO BE TAKEN The City Council is requested to approve this resolution for the acceptance of the Five-Year Construction Program for Fiscal Years 2008-2012. Prepared by Robert Schiesl, Assistant City Engineer cc: Jenny Larson, Budget Director Don Vogt, Public Works Director John Klostermann, Public Works Bob Green, Water Plant Manager Jon Dienst, Civil Engineer Greg Doeden, Civil Engineer Deron Muehring, Civil Engineer Dave Ness, Civil Engineer RESOLUTION NO. 71-07 ADOPTING THE FIVE-YEAR STREET CONSTRUCTION PROGRAM FOR FISCAL YEARS 2008-2012 Whereas, a recommended Five-Year Street Construction Program for the Fiscal Years 2008-2012 beginning July 1, 2007, and ending June 30, 2012, for the City of Dubuque has been prepared and submitted to the City Council; and Whereas, the Five-Year Street Construction Program: 1) describes specific capital improvement projects; 2) provides estimated costs for those projects; 3) proposes sources of funding; and 4) schedules the fiscal/calendar year during which each project will be undertaken; and Whereas, the capital improvement projects for the first year of such five- year program are. included in the Fiscal Year 2008 budget; and Whereas, the adoption of the Five-Year Street Construction Program is a prudent measure to provide continuity of programs and is in the best interest of the City of Dubuque. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. That the Five-Year Street Construction Program for Fiscal Years 2008-2012 beginning July 1, 2007, set out in the Fiscal Years 2008-2012 recommended Capital Improvement Budget, is hereby approved and adopted as the proposed allocation of City resources for capita! improvements as scheduled in the years shown, subject to annual review and revision. Passed, approved and adopted this 5th day of February , 2007. Roy D. Buol, Mayor Attest: Jeanne F. Schneider, CMC, City Clerk STREET CONSTRUCTION PROGRAM 2008-2012 SUMMARY CALENDAR YEAR 2007 / 2008 FISCAL YEAR 2008 Street From To Construction Tvoe Estimate Funding Assistance Rush Bryant Ylla PC Concrete Reconstruction $ 1,481,000 Special Assessments ; $ 162,000 5th Alpine Hill PC Concrete Reconstruction $ 574,000 Special Assessments ~ $ 70,000 Almond Ellis Foye HMA Resurfacing $ 115,000 Ellis West Locust Almond HMA Resurfacing $ 74,000 Preliminary Cost Estimate -Annual Street Construction Program $ 2,244,000 Total:;_$ _232,000 j PROPOSED BUDGET FY 2008 $ 2 244 000 PROGRAM FINANCING: ANNUAL STREET PROGAM $ 2,012,000 SPECIAL ASSESSMENTS $ 232,000 TOTAL PROGRAM FINANCING: $ 2 244 000 THE CI'T'Y OY DUB E C/P History No Change Shifted Back from 2007 No Change No Change STREET CONSTRUCTION PROGRAM 2008-2012 SUMMARY CALENDAR YEAR 2008 / 2009 FISCAL YEAR 2009 Street From To Construction Tvne Estimate Funding Assistance Cleveland Bryant Vlla PC Concrete Reconstruction $ 1,465,000 Special Assessments _$ _204,000 Locust 5th 17th HMA Resurfacing $ 611,000 r'-------------- Preliminary Cost Estimate -Annual Street Construction Program ~ 2,076,000 Total:l $ 204,000 PROPOSED BUDGET FY 2009 $ 2 076 000 PROGRAM FINANCING: ANNUAL STREET PROGAM $ 1,872,000 SPECIAL ASSESSMENTS $ 204,000 TOTAL PROGRAM FINANCING: $ 2 076 000 rr`s cm or DUB E `'~' CIP History No Change Shifted Back from 2008 STREET CONSTRUCTION PROGRAM 2008-2012 SUMMARY TOTE ~sn of CALENDAR YEAR 2009 / 2010 LUB E FISCAL YEAR 2010 ~~„~,~A_ Street From To Construction Tvae Estimate Funding Assistance C/P History Cedar Cross Starlite Cedar Cross Ct PC Concrete Reconstruction $ 1,635,000 Special Assessments $ _212,000 ~ No Change Asbury St. Ambrose University HMA Resurfacing $ 225,000 No Change r--'---'-------~ Preliminary Cost Estimate -Annual Street Construction Program $ 1,860,000 Total:. $ _212,000 PROPOSED BUDGET FY 2010 $ 1 860 000 PROGRAM FINANCING: ANNUAL STREET PROGAM $ 1,648,000 SPECIAL ASSESSMENTS $ 212,000 TOTAL PROGRAM FINANCING: $ 1 860 000 STREET CONSTRUCTION PROGRAM 2008-2012 SUMMARY CALENDAR YEAR 2010 / 2011 FISCAL YEAR 2011 Street From To Construction Tvae Estimate Funding Assistance Sunset Ridge Wartburg PI. End PC Concrete Reconstruction S 660,000 Special Assessments _$ __ 89,000 Kaufmann Chaney Bonson HMA Resurfacing $ 993,000 r-------------- Preliminary Cost Estimate -Annual Street Construction Program S 1,653,000 Total: ~ $ 89,000 PROPOSED BUDGET FY 2011 $ 1 653 000 PROGRAM FINANCING: ANNUAL STREET PROGAM $ 1,564,000 SPECIAL ASSESSMENTS $ 89,000 TOTAL PROGRAM FINANCING: $ 7 653 000 THE CITY OF DUB E ~irwyy. ~-,~~ C/P History From Deferred List Shifted Back from 2010 STREET CONSTRUCTION PROGRAM 2008-2012 SUMMARY CALENDAR YEAR 2011 / 2012 FISCAL YEAR 2012 Street From To Construction Tvae Estimate Funding Assistance 5th Bluff White PC Concrete Reconstruction $ 620,000 Special Assessments _$ __ 80,000 i ---------------- Asbury Road Reconstruction JFK St. Ambrose HMA Resurfacing $ 1,400,000 Special Assessments ; $ 210,000 9th/Hill Street Intersection Spruce Bluff HMA Resurfacing $ 200,000 Special Assessments ~ $ 10,000 Preliminary Cost Estimate -Annual Street Construction Program ~ 2,020,000 Total:; $ 300,000 PROPOSED BUDGET FY 2012 $ 2 020 000 PROGRAM FINANCING: ANNUAL STREET PROGAM $ 1,720,000 SPECIAL ASSESSMENTS $ 300,000 TOTAL PROGRAM FINANCING: $ 2 020 000 THE CITY OP DUB E `'f~ CIP History Shifted Back from 2006 Shifted Up from 2008 Shifted Back from 2006