MEMORANDUM
May 26, 2007
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Third Street Overpass Light Replacement Project
(CIP 1001918: 3rd Street Overpass Light Replacement Project)
City Engineer Gus Psihoyos recommends City Council approval of the plans,
specifications, form of contract and the estimated cost of $31,625 for the Third Street
Overpass Light Replacement Project.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
~;
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
THL- CITY OF C
DUB E
Masterpiece on the Mississippi
MEMORANDUM
May 25, 2007
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer ,
SUBJECT: Third Street Over~ass Light Replacement Project
(CIP 1001918: 3` Street Overpass Light Replacement Project)
INTRODUCTION
The enclosed resolution is in reference to the public hearing on the Third Street
Overpass Light Replacement Project.
BACKGROUND
The existing cast iron light fixtures along the Third Street Overpass are difficult to
maintain due to age and limited available parts. The existing luminaries are yellowing
and brittle, providing minimal lighting.
DISCUSSION
This project provides for the replacement of lights (poles and fixtures) on the Third
Street Overpass. There are 25 existing light locations along the Third Street Overpass
that extends from Main Street to Bell Street. Twenty-four of the 25 lights will be
replaced with new fixtures that will include receptacles for holiday lighting. One light at
the southeast corner of Third and Main has already been replaced as part of the Main
Street Lighting Project currently under construction. The street lighting equipment has
already been ordered due to a 12- to 14-week build time.
BUDGET IMPACT
The estimate of probable costs for the Third Street Overpass Light Replacement Project
is as follows:
Estimate
Construction Cost $25,000
Contingency 2 500
Construction Engineering & Inspection 4,125
Total Project Cost 31 625
The funding summary is as follows:
CIP No. Fund Description
100-1918 3~d Street Overpass Light Replacement Project
Fund Amount
$80,660
Total Project Funding 80 660
RECOMMENDATION
I recommend that the City Council approve the plans, specifications, form of contract
and the estimated cost for the Third Street Overpass Light Replacement Project.
ACTION TO BE TAKEN
The City Council is requested to approve the plans, specifications, form of contract and
the estimated cost for the Third Street Overpass Light Replacement Project.
Prepared by David Ness, Civil Engineer
cc: Jenny Larson, Budget Director
Don Vogt, Public Works Director
John Klostermann, Street & Sewer Maintenance Supervisor
Bob Schiesl, Assistant City Engineer
RESOLUTION NO 331-07
APPROVAL OF PLANS, SPECIFICATIONS, FORM OF CONTRACT, AND
ESTIMATED COST FOR THE THIRD STREET OVERPASS LIGHT REPLACEMENT
PROJECT
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That the proposed plans, specifications, form of contract and estimated cost for
the Third Street Overpass Light Replacement Project, in the estimated amount
$31,625.00, are hereby approved.
Passed, adopted and approved this 4th day of June 2007.
~~
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk