July 11, 2007
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Star Brewery Drive Construction Project
CIP 7001014
Sealed bids were received on June 3, 2007 for the Star Brewery Drive Construction
Project. City Engineer Gus Psihoyos is recommending award to the one valid bid
proposal that was submitted by Portzen Construction, Inc. in the bid amount of
$529,673.60, which is 0.1 % under the engineer's estimate of probable cost.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
w ~ ''l~
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
THE CITY OF
DUB E
Masterpiece on the Mississippi
MEMORANDUM
July 10, 2007
TO: Michael C. Van Milligen, City Mana
FROM: Gus Psihoyos, City Engineer v ~
SUBJECT: Star Brewery Drive Construction Project
CIP 7001014
INTRODUCTION
The enclosed resolution authorizes the award of the construction contract for the Star
Brewery Drive Construction Project.
DISCUSSION
In an effort to improve access from the Port of Dubuque main campus to the Historic
Shot Tower area and to maximize the developable land area adjacent to the Star
Brewery property, staff has been working with both the Brewery Developer and McGraw
Hill on the improvement plans for the new construction of Star Brewery Drive.
The Star Brewery Drive Construction Project will provide for the construction of a new
25-foot wide concrete roadway extension, north of the existing Bell Street on a new
alignment to the north-east, parallel to the existing railroad tracks and adjacent to the
Star Brewery property. Star Brewery Drive as proposed will extend to the north side of
the train bridge underpass and will terminate at 7th and Commercial Street.
The project streetscape enhancement will compliment the existing Bell Street corridor
with the continuation of the decorative concrete sidewalk, decorative street lighting and
landscape plantings along the new section of roadway.
At the northerly intersection of Bell Street and Star Brewery Drive, a cul-de-sac will be
constructed which will allow larger type vehicles, such as semi-trailers, buses and
emergency vehicles adequate space to turn around.
Due to the height and width restrictions of the train bridge underpass, low clearance
warning signage will be placed at the Bell Street /Star Brewery Drive cul-de-sac to
advise larger type vehicles that they can not use Star Brewery Drive.
Star Brewery Drive as proposed will allow two-way traffic operations up to the train
bridge underpass, at which point drivers will need to yield and alternate vehicles as they
pass through the train bridge underpass. During special events, Star Brewery Drive
could be limited to one-way traffic north bound to facilitate traffic exiting the Port area.
On the north side of the train bridge, there will be directional signage placed to direct
vehicles west on 7th and Commercial Street to the downtown area.
BID RESULTS
One valid bid proposal was received on June 3, 2007, which was submitted by Portzen
Construction, Inc. of Dubuque, Iowa in the bid amount of $529,673.60. This amount is
0.1 % under the engineer's estimate of probable cost. It should be noted that a second
bid proposal was submitted; however the bid was disqualified because the bidder did
not provide the proper bid bond.
REVISED PROJECT SCHEDULE
During the bidding phase, several contractors expressed concerns with the aggressive
project schedule and the ability to complete the electrical work, irrigation and
landscaping by the specified completion date. As a result, a revised project schedule
was issued prior to the bid letting. The revised project schedule is as follows:
Phase 1:
The contractor shall have the proposed sanitary sewer, storm sewer and water
underground utility improvements completed by Friday September 21St, 2007. All
concrete pavement, HMA pavement, concrete driveways and concrete sidewalk
shall be completed by Friday September 21St, 2007.
Phase 2:
The contractor shall have the lighting, irrigation and landscaping completed by
Friday October 19th, 2007.
RECOMMENDATION
I recommend that the contract for the Star Brewery Drive Construction Project be
awarded to Portzen Construction, Inc. in the amount of $529,673.60.
BUDGET IMPACT
The estimate of probable cost for the Star Brewery Drive Construction Project is
summarized as follows:
Construction Contract
Contingency
Construction Engineering & Inspection
Total Project Cost
The project funding summary is as follows:
CIP No. Fund Description
7001014 Port New Street Construction
Total Project Funding
Cost Estimate
$534,000.00
53,400.00
58,740.00
$646,140.00
Bid Award
$529,673.60
53,400.00
58,740.00
$641,813.60
Fund Amount
$646,416.00
$646,416.00
ACTION TO BE TAKEN
I recommend that the City Council adopt the attached resolution awarding the Star
Brewery Drive Construction Project to Portzen Construction, Inc. in the amount of
$529,673.60.
Prepared by Robert Schiesl, Assistant City Engineer
cc: Jenny Larson, Budget Director
David Heiar, Economic Development Director
Don Vogt, Public Works Director
John Klostermann, Public Works
Bob Green, Water Plant Manager
Greg Doeden, Civil Engineer
RESOLUTION NO. 382-07
AWARDING PUBLIC IMPROVEMENT CONTRACT FOR THE STAR
BREWERY DRIVE CONSTRUCTION PROJECT
Whereas, sealed proposals have been submitted by contractors for the Star
Brewery Drive Construction Project (the Project) pursuant to Resolution No. and
Notice to Bidders published in a newspaper published in the City of Dubuque, Iowa on
the 8th day of June, 2007.
Whereas, said sealed proposals were opened and read on the 3~d day of July,
2007 and it has been determined that Portzen Construction, Inc. of Dubuque, Iowa, with
a bid in the amount of $529,673.60, is the lowest responsive, responsible bidder for the
Project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
That a Public Improvement Contract for the Project is hereby awarded to Portzen
Construction, Inc. and the City Manager is hereby directed to execute a Public
Improvement Contract on behalf of the City of Dubuque for the Project.
Passed, approved and adopted this 16th day of 3u1Y ~ , 2007.
Roy D. Buol, Mayor
Attest:
~i
Jeanne F. Schneider, CMC, City Clerk
CITY OF DUBUQUE -ENGINEERING DIVISION -BID TABULATION SHEET
BID TABULATION FOR: STAR BREWERY DRIVE RECONSTRUCTION BID DATE: July 3, 2007 BIDDER:
PoRzen Construction. Inc.
BID ITEM DESCRIPTION UNIT QUANTITY UNIT COST E COSTTE UNIT COST COST
BASE BID:
DEMOLITION•deREMOVALIJ ;. ..
1 Clearing & Grubbing
; ~..,
LS
;._:
1
' ~..
$1,700.00
~ '~--
$1,700.00
$1,800.00
$1,800.00
2 Remove Pavement SY 210 $6.00 $1,260.00 $6.00 $1,260.00
3 Remove Sidewalk SY 6 $5.00 $30.00 $18.00 $108.00
4 Abandon Existing Pipe CY 4 $100.00 $400.00 $110.00 $440.00 '
+EXCAVATION b STONE
5 Excavation, UnGassified
CY
800
$6.50
$5,200.00
$6.50
$5,200.00
6 Excavation, Unsuitable CY 500 $6.50 $3,250.00 $6.50 $3,250.00
7 Excavation, Borrow CY 4,180 $6.50 $27,170.00 $6.50 $27,170.00
8 Backfilt, Limestone Ton 2,660 $7.00 818,620.00 $5.50 $14,630.00
9 Backfill Topsoil SY 3,000 $3.50 $10,500.00 $5.00 $15,000.00
10 Graded Stone Basa Ton 1,100 $13.70 $15,070.00 $15.00 $16,500.00
11 3" Crushed Stone Base Ton 3,645 $10.00 $36,450.00 $10.00 $36,450.00
12 Trench Stabilization Stone Ton 200 $11.80 $2,360.00 $13.00 $2,600.00
PAVEMENT .~~..
13 PC Concrete Pavement, (7") w/Integral Curb, Class "C"
SY
1,525
$30.00 ,
$45,750.00
$30.00
$45,750.00
14 PC Concrete Pavement, (8") w/Int. Curb, Class "C° w1CD Baskets SY 1,805 $35.00 $63,175.00 $34.00 $61,370.00
15 HMA 300k Surface Course, 112" (PG 64-22) - (Headers) Ton 50 $110.00 $5,500.00 $110.00 $5,500.00
16 FixtureAdjusiment EA 8 $190.00 $1,710.00 $250.00 $2,250.00
17 PC Concrete Driveway, 7", Construct SY 240 $40.25 $9,660.00 $32.00 $7,680.00
18 PC Concrete Sidewalk, 4", Buff w/Gray Picture Frame -Light Broom SF 6,405 $7.00 $44,835.00 $6.50 $41,632.50
Finish, #4 Bar 24" O.C.
19 PC Concrete Sidewalk, 7", Integral Buff Textured Finish,
SF
825
$8.00
$6,600.00
$10.00
$8,250.00
#4 Bar 24" O.C.
20 PC Concrete Access Ramp, Detectable
Each
3
$175.00
$525.00
$200.00
$600.00
STORM SEYVER ' .
21 Intake 101-B
Each
4
$1,800.00
$7,200.00 ,., .
$1,800.00
$7,200.00
22 Intake 101-B, Special Each 3 $2,491.78 $7,475.34 $2,200.00 $6,600.00
23 Storm Sewer, intake with R-2563 Beehive, Complete Each 1 $1,600.00 $1,600.00 $1,500.00 $1,500.00
24 Manhole 60" Diameter, R-1642-A Casting, Complete Each 1 $4,250.00 $4,250.00 $4,500.00 $4,500.00
25 Manhole 60" Diameter, R-2501, Casting, Complete Each 1 $4,250.00 $4,250.00 $4,500.00 $4,500.00
26 Storm Sewer, 12" RCP, CL V LF 140 $28.00 $3,920.00 $22.00 $3,080.00
27 Stonn Sewer, 15" RCP, CL III LF 180 $28.00 $5,040.00 $25.00 $4.500.00
28 Storm Sewer, 24" RCP, CL III LF 170 $37.00 $6,290.00 $35.00 $5,950.00
29 Storm Sewer, 36" RCP, CL III LF 30 $57.00 $1,710.00 $55.00 $1,650.00
SANITARY SEWER
30 1 1!2" HDPE Sanitary Sewer Force Main
LF
590
$5.00
$2,950.00
$15.00
$8,850.00
WATER..MAIN
Star Brewery Drive Watermain
31 6" DIP, Class 52 w.lPOlywrap .`.._
LF .., ~ ,
22
$40.00
$880.00
$40.00
$880.00
32 6" Mega Lug MJ Each 2 $60.00 $120.00 $75.00 $150.00
33 6" Valve MJ wlBox Each 1 $850.00 $850.00 $750.00 $750.00
34 8" DIP, Class 52 wlPolywrap LF 576 $38.00 $21,888.00 $38.00 $21,888.00
35 8" Valve MJ wlBox Each 2 $860.00 $1,720.00 $900.00 $1,800.00
36 B"x8"x6" Anchoring Tee Each 1 $360.00 $360.00 $325.00 $325.00
37 B"x8"x8" Anchoring Tee Each 1 $350.00 $350.00 $375.00 $375.00
38 12" DIP, Class 52 w./Polywrap LF 2 $45.00 $90.00 $75.00 $150.00
39 12"x12"x8" Anchoring Tee Each 1 $500.00 $500.00 $480.00 $480.00
40 12" Valve MJ wBox Each 1 $900.00 $900.00 $1,425.00 $1,425.00
41 12" Solid Sleeve Each 1 $300.00 $300.00 $275.00 $275.00
42 Hydrant MJ Each 1 $2,000.00 $2,000.00 $1,900.00 $1,900.00
43 Tracer Wire Access Box Each 1 $35.00 $35.00 $50.00 $50.00
44 Copper Tracer Wire LF 600 $0.25 $150.00 $0.50 $300.00
45 Water Service, Meter 8 RPZ EnGosure w/Pad Each 1 $3,500.00 $3,500.00 $4,000.00 $4,000.00
46 Water Service, Conbraco 40 - 200 1 12" RPZ Back Flow Preventer Each 1 $800.00 $800.00 $500.1)0 $500.00
47 Water Service, 1 1!2"x3/4" Manifold 1 - 1 1/2" Intel, 1 - 1"Outlet Each 1 $1,074.96 $1,074.96 $350.00 $350.00
48 Water Service, SR - EC 1 1/2" Water Meter Each 1 $850.00 $850.00 $650.00 $650.00
49 Water Service, 1 1/2" Ball Valve Each 5 $100.00 $500.00 $50.00 $250.00
50 Water Service, 1 1/2" Union Each 2 $125.00 $250.00 $50.00 $100.00
51 Water Service Line Stop Box, Curb Stop, Tap Installation 1 1Y2" Each 1 $650.00 $650.00 $750.00 $750.00
52 Water Service, 1 1/2" Copper Service Line TYPE K LF 50 $42.75 $2,137.50 $30.00 $1,500.00
Bid Tabulation Sheet 1 of 2
CITY OF DUBUQUE -ENGINEERING DIVISION -BID TABULATION SHEET
BID TABULATION FOR: STAR BREWERY DRIVE RECONSTRUCTION BID DATE: July 3, 2007 BIDDER:
Portzen Construc tion. Inc.
BID ITEM DESCRIPTION UNIT I TE
E
QUANTITY UN T
COST COST UNIT COST COST
Bell Street Watennain
53 Hydrant MJ, Remove & Reinstall Each 1 $1,000.00 $1,000.00 $600.00 $600.00
54 6" Valve MJ w/Box Remove & Reinstall Each 1 $750.00 $750.00 $350.00 $350.00
55 12"x6" Reducer Remove 8 Salvage Each 1 $500.00 $500.00 $95.00 $95.00
56 12"x8" Reducer Each 1 $450.00 $450.00 $225.00 $225.00
57 8"x6"Reducer Each 1 $220.00 $220.00 $175.00 $175.00
58 6" Mega Lug MJ Each 4 $60.00 $240.00 $75.00 $300.00
59 8" Mega Lug MJ Each 2 $70.00 $140.00 $85.00 $170.00
60 8" DIP Class 52 w./Polywrap LF 202 $38.00 $7,676.00 $38.00 $7,676.00
61 6" DIP Class 52 w./Polywrap LF 8 $40.00 $320.00 $40.00 $320.00
62 Tracer Wire Access Box Each 1 $35.00 $35.00 $50.00 $50.00
63 Copper Tracer Wire LF 210 $0.25 $52.50 $0.50 $105.00
.:'LIGHTING ELEC7"RIGAL .. ~ ,
64 Historic Street Light w! Precast Concrete Foundation, Install Each 19 $1,200.00 $22,800.00 $1,125.00 $21,375.00
65 Relocate Historic Street light w/ Precast Concrete Foundation Each 2 $500.00 $1,000.00 $1,185.00 $2,370.00
66 Electrical Service, Main Controller #1 w/Foundation, Install Each 1 $700.00 $700.00 $2,000.00 $2,000.00
67 Pull Box, Colored, 11"x18" Each 2 $370.00 $740.00 $450.00 $900.00
68 Conduit, 2" PVC Sch 40 w/Trace Wlre LF 130 $9.00 $1,170.00 $8.00 $1,040.00
69 Conduit, 2" PVC Sch 40 LF 1,555 $8.50 $13,217.50 $6.75 $10,496.25
70 Conduit, 4" PVC Sch 40 LF 48 $11.00 $528.00 $9.00 $432.00
71 Electrical Cable #6 XHHW LF 7,711 $0.80 $6,168.80 $1.10 $8,482.10
72 Electrical Cable #8 XHHW LF 1,543 $0.80 $1,234.40 $1.00 $1,543.00
73 Electrical Cable #10 XHHW LF 4,755 $0.80 $3,804.00 $0.65 $3,090.75
74 Sawcut, Concrete LF 100 $3.10 $310.00 $4.00 $400.00
75 Seed, Fertilizer, and Mulch SY _
1,635 $3.00 $4,905.00 $1.00 $1,635.00
76 Sod SY 1,365 $6.40 $8,736.00 $6.00 58,190.00
77 Watering MGAL 15 $25.00 $375.00 $55.00 $825.00
78 Trees Each 30 $500.00 $15,000.00 $190.00 $5,700.00
79 Geotextile Fabric, Subgrade SY 3,645 $3.50 $12,757.50 $3.00 $10,935.00
80 GeoteMile Fabric, Sub-Base SY 3,645 $3.50 $12,757.50 $3.00 $10,935.00
81 Brick Pavers, Salvaged Paver Installation, Complete SF 260 $15.00 $3,900.00 $6.50 $1,690.00
82 Irrigation System LS 1 $15,000.00 $15,000.00 $14,300.00 $14,300.00
83 Dusl Control Surtace Treatment MGAL 10.0 $20.70 $207.00 815.00 $150.00
84 Erosion Control Plan -Operating Procedures LS 1 $3,200.00 $3,200.00 $3,500.00 $3,500.00
85 Traffic Control & Safety Control LS 1 $2,250.00 $2,250.00 $2,000.00 $2,000.00
86 Mobilization LS 1 $7,500.00 $7,500.00 $23,000.00 $23,000.00
Bid Sub-Total 5534,000.00 Bid sub-Total 5528,673.60
Contingency $53,400.00
Construction Engineering 8 Inspection $58,740.00
Total Construction Estimate: 5648,140.00
BASE BID (%) OVER /UNDER (-): -0.8
BID''ALTERNATE 1 -CITY FURNISHEB WATER MATERIAL: ' ` '
87 DEDUCT -WATER MATERIALS LS 1 $ 18,657.54 $18,657.54 $19,020.00 $19,020.D0
ALTERNATE NO. 1 TOTAL: 578,657.54 Deduct-Total 519,020.00
ALTERNATE BID (%) OVER /UNDER (-): 1.9