Curb Access Ramps Phase Two - Asphalt Overlay Project Acceptance Copyright 2014
City of Dubuque Consent Items # 8.
ITEM TITLE: Curb Access Ramps Phase Two - Asphalt Overlay Project Acceptance
SUMMARY: City Manager recommending adoption of a resolution accepting the
improvements and establishing the final contract amount for the Asphalt
Overlay Project-Curb Access Ramps Phase Two as completed by Midwest
Concrete, Inc.
RESOLUTION Accepting the Asphalt Overlay Project Curb Access Ramps
Phase Two and authorizing the payment of the contract amount to the
contractor
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt Resolution(s)
ATTACHMENTS:
Description Type
❑ Asphalt Overlay Project Curb Access Ramps Phase Two-MVM Memo City Manager Memo
❑ Staff Memo Staff Memo
❑ Resolution Resolutions
❑ Engineer's Certificate Supporting Documentation
THE CITY OF Dubuque
UBE I
erica .i
Masterpiece on the Mississippi 2007-2012-2013
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Asphalt Overlay Project Curb Access Ramps Phase Two (CIP 30012277)
DATE: October 28, 2014
City Engineer Gus Psihoyos is recommending City Council adoption of the resolutions
accepting the improvements and establish the final contract amount of $62,563.37 for
the Asphalt Overlay Project-Curb Access Ramps Phase Two as completed by Midwest
Concrete.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Mic ael C. Van Milligen
MCVM:sv
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
7"HEC1TY OF DLJ
DUB E iii ii�iit
�r
M.aste—piece on the Mississippi' 2®07.2012.20,3
TO: Michael C. VanMilligan, City Manager
FROM: Gus Psihoyos, City Engineer y.
SUBJECT: Asphalt Overlay Project Curb Access Ramps Phase Two
(CIP 30012277)
DATE: November 3, 2014
INTRODUCTION
The enclosed resolutions provide for the acceptance of the construction contract for the
Asphalt Overlay Project - Curb Ramps Phase Two.
BACKGROUND
This was a project to replace 19 defective access ramps in the Merz Street, Viola
Street, Eagle Street, and Althauser Street areas in conjunction with the Public Works
Asphalt Overlay Program. The enclosed resolutions provide for the acceptance of the
construction contract for the Asphalt Overlay Project - Curb Access Ramps Phase Two.
Due to recent United States Department of Justice (USDOJ) rulings governing the
installation of curb access ramps, and in an effort to comply with those rulings the
engineering and the public works departments have teamed up to address the issues of
which ramps are to be replaced, the design and placement of these ramps and
documenting the newly placed compliant ramps to into the City's transition plan in
conjunction with Public Works yearly asphalt overlay program.
DISCUSSION
The Asphalt Overlay Project - Curb Access Ramps Phase Two received one bid from:
Midwest Concrete of $65,382.00 at 26.03'/0 over the engineers estimate.
The Asphalt Overlay Project - Curb Access Ramps Phase Two was completed by
Midwest Concrete of Peosta, Iowa in the final contract amount of $62,563.37 which is
4.3% below the contract amount of $65,382.00.
The average cost per ramp on the Phase two curb ramp replacement was $3,475.74
due to the topography of the area and the need to utilize the maximum amount of
removal and installation to meet the slopes mandated by the current ADA standards.
BUDGETIMPACT
The project cost summary for the Asphalt Overlay Project - Curb Access Ramps Phase
Two is:
Award Final
Construction Contract $65,382.00 $62,563.37
Contingency $5,187.77 0.00
Construction Engineering & Inspection $7,781 .65 $7,417.00
Total Project Cost $78,351.42 $69,980.37
The funding summary for the project is as follows:
CIP Fund Description Fund
Amount
30012277 Asphalt Overlay Project Curb Access Ramps Phase Two $69,980.37
Total Project Funding $69,980.37
REQUESTED ACTION
The City Council is requested to adopt the attached resolutions accepting the
improvements and establish the final contract amount for the Asphalt Overlay Project -
Curb Access Ramps Phase Two.
Prepared By: Tom Kopp, Engineering Technician
cc: Don Vogt, Public Works Director
John Klostermann, Public Works Supervisor
Jenny Larson, Budget Director
Jon Dienst, Civil Engineer 11
RESOLUTION NO. 340-14
ACCEPTING THE ASPHALT OVERLAY PROJECT CURB ACCESS RAMPS PHASE
TWO AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE
CONTRACTOR
Whereas, the Public Improvement Contract for the Asphalt Overlay Project Curb
Access Ramps Phase Two (the Project) has been completed and the City Engineer has
examined the work and filed a certificate stating that the Project has been completed
according to the terms of the Public Improvement Contract and that the City Engineer
recommends that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project is
hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from the
Asphalt Overlay Project Curb Access Ramps Phase One appropriations for the contract
amount of $62,563.37, less any retained percentage provided for therein as provided in
Iowa Code chapter 573, and to pay such retainage only in accordance with the
provisions of Iowa Code chapter 573.
Passed, approved and adopted this 3rd day of November, 2014.
Attest:
Kevin Firnstahl, Cit
Kakla A. Braig. Mayor Pro/
G
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE ASPHALT r
OVERLAY PROJECT CURB ACCESS RAMPS PHASE TWO s
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he
has inspected the Asphalt Overlay Project Curb Access Ramps Phase Two, that the
Project has been performed in compliance with the terms of the Public Improvement
Contract, and that the total cost of the completed work is $69,980.37.