Loading...
Dubuque Industrial Center South - Paving/Utilities - Phase II Acceptance Copyright 2014 City of Dubuque Consent Items # 9. ITEM TITLE: Dubuque Industrial Center South - Paving/Utilities - Phase II Acceptance SUMMARY: City Manager recommending acceptance of the Dubuque Industrial Center South PCC Paving and Utilities, Phase II, as completed by Horsfield Construction, Inc. RESOLUTION Approving a Housing Enterprise Zone Program agreement by and among the Iowa Economic Development Authority, the City of Dubuque and Weaver Castle, LLC SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt Resolution(s) ATTACHMENTS: Description Type ❑ DICS PCC Paving and Utilities-Phase II-MVM Memo City Manager Memo ❑ Staff Memo Staff Memo ❑ IIW Letter of Project Completion Supporting Documentation ❑ Contract Reconciliation Table Supporting Documentation ❑ City Engineer Cert of Final Completion Supporting Documentation ❑ DOT Certificate of Competion Supporting Documentation ❑ Resolution of Acceptance Resolutions THE CITY OF Dubuque UBE I erica .i Masterpiece on the Mississippi 2007-2012-2013 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: Dubuque Industrial Center South PCC Paving and Utilities - Phase II CIP 360210 - South Siegert Farm DATE: November 10, 2014 City Engineer Gus Psihoyos and Economic Development Director Maurice Jones are recommending acceptance of the Dubuque Industrial Center South PCC Paving and Utilities, Phase 11, as completed by Horsfield Construction, Inc. in the final contract amount of $622,075.48, which is a 6.5% decrease from the original contract amount of $6551611.50. 1 concur with the recommendation and respectfully request Mayor and City Council approval. Micliael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Gus Psihoyos, City Engineer Maurice Jones, Economic Development Director Dubuque Economic Development Department THE CITY OF 50 West 13th Street All-AmericaCitY Dubuque,Iowa 52001-4864 DUB36kE1 ' Office(563)589-4393 TTY(563)690-6678 ® http://www.cityofdubuque.org Masterpiece on the Mississippi 200.2012.2013 TO: Michael Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer Maurice Jones, Economic Development Director SUBJECT: Dubuque Industrial Center South PCC Paving and Utilities — Phase II CI P 3602160 — South Siegert Farm DATE: October 27, 2014 INTRODUCTION The enclosed resolution provides for the acceptance of the public improvements for the Dubuque Industrial Center South — South Siegert Farm — PCC Paving and Utilities, Phase II and establishment of the final contract amount. BACKGROUND Dubuque Industrial Center West— Grading/Expansion of South Siegert Farm is being completed in phases based on budget and developmental needs. The entire project included grading, road construction, utility extensions, and the development of a recreational area. Phase I, the grading portion of this project was awarded to Kueter Construction on July 16, 2012, and accepted by City Council on December 2, 2013. Phase II is Dubuque Industrial Center South — South Siegert Farm — PCC Paving and Utilities. This was awarded to Horsfield Construction on August 5, 2013. DISCUSSION Dubuque Industrial Center South — South Siegert Farm — PCC Paving and Utilities included the following- -900 lined feet of PCC paving -Storm sewer -Water Main -Fiber Optic Conduit -Street Lighting -Trees along the proposed cul-de-sac and existing Seippel Road. In May 2013 the City Council approved a RISE contract for a $229,247 grant with the IDOT to help fund this phase of the project. Dubuque Industrial Center South — South Siegert Farm, Phase II — PCC Paving and Utilities was completed by Horsfield Construction, Inc. of Epworth, Iowa, with a final contract amount of$622,075.48, which is a 6.5% decrease from the original contract in the amount of$655,611 .50. BUDGETIMPACT The project cost summary for Dubuque Industrial Center South — South Siegert Farm, Phase II — PCC Paving and Utilities is as follows: Bid Award Final Construction Contract $655,611 .50 $622,075.48 Total Phase II Cost 5655.611.50 5622.075.48 The total project funding summary for both phases of Dubuque Industrial Center South is as follows: CIP No. Fund Description Fund Amount 3602160 General Obligation Bonds (TIF Abated) $4,585,004.00 Transfer from Unused Portion of North $1 ,000,000.00 Siegert GO Bond Sale RISE Grant $229,247.00 Total Project Funding $5,814,251.00 (minus) Phase I costs $2,148,349.81 (minus) Phase II costs $622,075.48 (minus) Engineering/consultant fees $506,256.28 Project Balance Remaining $2,537,569.43 There is a remaining balance of$2,537,569.43 after all expenditures. The remaining funds will be used to fund additional sanitary sewer extensions on each of the building pads, additional industrial or recreational space south of the current development, the Catfish Creek sanitary sewer capacity study, and other economic development activities. The success of future development in our industrial parks and adjacent land will depend upon sufficient capacity of the interceptor sewers to handle flows from these new developments. RECOMMENDATION/ ACTION STEP The City Council is requested to adopt the attached resolution accepting the public improvements and establishing the final contract amount for Dubuque Industrial Center South — South Siegert Farm, Phase II — PCC Paving and Utilities. cc: Todd Irwin, Engineering Technician Jenny Larson, Budget Director Ken TeKippe, Finance Director IIW, P. C. October 9, 2014 www.iiwengr.com Maurice Jones ARCHITECTURE Economic Development Director CIVIL ENGINEERING City of Dubuque CONSTRUCTION SERVICES 50 W. 13th Street ENVIRONMENTAL ENGINEERING Dubuque, IA 52001 LAND SURVEYING MUNICIPAL ENGINEERING Re: Dubuque Industrial Center South STRUCTURAL ENGINEERING PCC Paving&Utilities 2013 TRANSPORTATION ENGINEERING Project Certification IIW Project No.: 11083-01 Dennis F.Waugh,PE/SE* Dear Maurice: Charles A.Cate,PE** Gary D.Sejkora,PE An inspection of the Dubuque Industrial Center South PCC Paving & Utilities 2013 project has been Michael A.Jansen,PE/SE Completed. Ronald A.Balmer,PE/SE/AIA Timothy J.Tranel,PE* John F.Wandsnider,PE We hereby certify that Horsfield Construction, Inc.of Epworth, Iowa, has completed construction of Julie P.Neebel,PE the above referenced project in compliance with the drawings and specifications and the project is James P.Kaune,PE ready for acceptance. The final project construction cost is$622,075.48. Thomas J.Oster,PLS** Wray A.Childers,PLS We have enclosed a Contract Reconciliation Report documenting the differences between the Geoffry T.Blandin,PE original contract quantities and the final installed quantities for your project records. There is no Mark C.Jobgen,PE due the contractor at this time. Lauren N.Ray,PE payment Cody T.Austin,PE* Marc D.Ruden,PE We recommend that the City of Dubuque approve and accept the Dubuque Industrial Center South Mark R.Fassbinder,AIA* PCC Paving &Utilities 2013 project work. Retainage in the amount of$31,103.77 will be held for 30 Michael A.Ruden,NCARB/AIA* days after project acceptance by the city and paid at that time provided no claims from others are Craig J.Elskamp,AIA filed. We will prepare Contract Payment No. 5 Final for the retainage due the contractor at the Robert W.Blok,PE appropriate time. Eric J.Helminiak,PE/SE* Steven J.Hunn,PE Jeffrey J.Brandt,PLS/RLS Approval and acceptance starts the two year warranty period. Craig L.Geiser,PLS/RLS Adam J.Moris,PE Sincerely, David A.Leapaldt,AIA,CID* IIW, P.C. Nathan W.Miller,PE Damian D.Baumhover,AIA Gene Farach,PE Nickolas A.Schneider,PE Christian J.Hendrie,AIA Cody T.Austin, P.E. John F.Wandsnider, P.E. Eldon M.Schneider,PE Project Engineer Project Manager&Municipal Engineer Enc. *LEED AP Copy: HorsfieId Construction **Retired Todd Irwin, City of Dubuque Jennifer Kolacia, Iowa DOT RISE PM IkO831083-011Secretarial Docs1PCC PavinglContract DocslProject Certification Letter-DICS PCC Paving 10-8-2014.docx 4155 Pennsylvania Avenue, Dubuque, IA 52002-2628 ♦ [P]563.556.2464/800.556.4491 ♦ [F] 563.556.7811 A. O . CONTRACT RECONCILIATION REPORT 11W, P.C. City of Dubuque, Iowa 4155 Pennsylvania Ave. Dubuque Industrial Center PCC Paving & Utilities Dubuque, IA 52002-2628 RISE Project No. RM-2100(677)--9D-31 IIW Project No. 11083-01 A. Contract adjustment based on measured quantities LINE SUDAS ORIGINAL FINAL QUANTITY UNIT NO. NUMBER ITEM UNIT QUANT QUANT DIFF. PRICE INCREASE DECREASE 1 1010-103 Mobilization LS 1 1 0.00 $3,500.00 $0.00 $0.00 2 1070-206-A-0 Traffic Control LS 1 1 0.00 $600.00 $0.00 $0.00 DIVISION 2010-EARTHWORK,SUBGRADE, SUBBASE 3 2010-108-D-1 Topsoil,On-Site CY 875 850 25.00 $4.50 $0.00 $112.50 4 2010-108-G-0 Subgrade Preparation SY 4986 4986 0.00 $0.80 $0.00 $0.00 5 2010-108-1-0 Subbase, Granular Subbase-Gradation 12a TON 3141 2911.92 229.08 $12.20 $0.00 $2,794.78 DIVISION 3010-TRENCH EXCAVATION AND BACKFILL 6 3010-108-C-0 Trench Foundation TON 1 308 0 308.00 $13.00 $0.00 $4,004.00 7 3010-108-D-0 Bedding, Material Gradation 3 TON 4290 76.83 4,213.17 $13.00 $0.00 $54,771.21 8 3010-108-D-0 Bedding Material Gradation 29 TON 132 94.07 37.93 $17.00 $0.00 $644.81 9 3010-108-D-0 Bedding Material Gradation 32 TON 962 2689.29 1,727.29 $13.00 $22,454.77 $0.00 10 3010-108-1-2 Trenching, 26 Inch Depth LF 264 219 45.00 $2.00 $0.00 $90.00 11 3010-108-J-3 Trenching, 48 Inch Depth LF 3292 3385 93.00 $2.00 $186.00 1 $0.00 DIVISION 3020-TRENCHLESS CONSTRUCTION 12 3020-108-A-0 Directional Drilling LF 110 112 2.00 $19.00 $38.00 $0.00 DIVISION 4020-STORM SEWERS 13 4020-108-A-1 Storm Sewer Gravity Main, Trenched, 18 Inch RCP LF 646 645 1.00 $26.00 0.00 26.00 DIVISION 4040-SUBDRAINS&FOOTING DRAT N COLLECTORS 14 4040-108-A-0 Subdrain, 6 Inch Perforated CPE LF 1960 1807 153.00 $7.00 0.00 1,071.00 15 4040-108-D-0 Subdrain Outlets and Connections,Core Drill, 4Inches EA 6 5 1.00 $250.00 $0.00 $250.00 16 4040-108-A-0 Subdrain, 4 Inch Non-Perforated CPE LF 671 1091 420.00 $6.00 $2,520.00 $0.00 DIVISION 5010-PIPE AND FITTINGS 17 5010-108-A-1 Water Main,Trenched, DIP, 6 Inch LF 38 38 0.00 $70.00 $0.00 $0.00 18 5010-108-A-1 Water Main,Trenched, DIP, 12 Inch LF 1 71 64 7.00 $75.00 $0.00 $525.00 19 5010-108-A-1 Water Main,Trenched, DIP, 16 Inch LF 1003 954 49.00 $66.00 $0.00 $3,234.00 20 5010-108-C-2 Fittings by Weight, DI LBS 3403 3605 202.00 $6.50 $1,313.00 $0.00 21 5010-108-C-1 Fittings, Mega Lug, 6 Inch EA 9 32 23.00 $37.00 $851.00 $0.00 22 5010-108-C-1 Fittings, Mega Lug, 12 Inch EA 8 13 5.00 $188.00 $940.00 $0.00 23 5010-108-C-1 Fittings, Mega Lug, 16 Inch EA 27 32 5.00 $295.00 $1,475.00 $0.00 DIVISION 5020-VALVES, FIRE HYDRANTS, &APPURTENANCES 24 5020-108-A-0 Valve, Gate, DIP, 61nch EA 2 2 0.00 $950.00 $0.00 $0.00 25 5020-108-A-0 Valve, Gate, DIP, 12 Inch EA3 3 0.00 $2,100.00 $0.00 $0.00 26 5020-108-C-0 Fire Hydrant Assembly EA 5 5 0.00 $2,444.00 $0.00 $0.00 27 5020-108-A-0 Valve, BF, DIP, 161nch EA 2 2 0.00 $2,520.00 $0.00 $0.00 Page 1 of 2 LINE SUDAS ORIGINAL FINAL QUANTITY UNIT NO. NUMBER ITEM UNIT QUANT QUANT DIFF. PRICE INCREASE DECREASE DIVISION 6010-STRUCTURES FOR SANITARY&STORM SEWERS 28 6010-108-B-0 Intake Type, CIP, SW-501 (101-B) EA 4 4 0.00 $1,825.00 $0.00 $0.00 29 6010-108-B-0 Intake, Type, CIP,SW-505(104-B) EA 2 2 0.00 $2,500.00 $0.00 $0.00 30 6010-108-G-0 Connection to Existing Intake EA 1 1 0.00 $475.00 $0.00 $0.00 DIVISION 7010-PORTLAND CEMENT CONCRETE PAVEMENT 31 7010-108-A-0 Pavement, PCC, 9Inch(Thickness) SY 4374 4417.69 43.69 $33.00 $1,441.77 $0.00 DIVISION 7040-PAVEMENT REHABILITATION 32 7040-108-H-0 Removal-Pavement SY 1 66 66 0.00 $14.00 $0.00 $0.00 DIVISION 8010-TRAFFIC SIGNALS 33 8010-108-A-2 Handhole-Composite EA 20 20 0.00 $344.00 $0.00 $0.00 34 8010-108-B-0 Conduit-Trenched, HDPE, 1-1/2 Inch LF 13152 13492 340.00 $2.50 $850.00 $0.00 35 8010-108-B-0 Conduit-Trenchless, HDPE, 1-1/2 Inch LF 240 240 0.00 $4.10 $0.00 $0.00 36 8010-108-B-0 Conduit-Trenched, HDPE, 2Inch LF 3422 3422 0.00 $3.25 $0.00 $0.00 37 8010-108-B-0 Conduit-Trenchless, HDPE, 2Inch LF 50 50 0.00 $3.30 $0.00 $0.00 38 8010-108-C-0 Wring and Cable-Power LF 11976 10611 1,365.00 $1.50 $0.00 $2,047.50 39 8010-108-D.1 Street Light Precast Concrete Base, 2' Dia x 6' EA 1 19 19 0.00 $1,030.00 $0.00 $0.00 40 8010-108-D.5 Electrical Service Control Pedestal Precast Concrete Base EA 1 1 0.00 $1,220.00 $0.00 $0.00 41 8010-108-F.1 Fiber Optic Vault Precast Concrete EA 10 10 0.00 $2,607.00 $0.00 $0.00 42 8010-108-M-0 Street Light,35' EA 19 19 0.00 $2,740.00 $0.00 $0.00 43 8010-108-J-0 Electrical Service Control Pedestal EA 1 1 0.00 $5,100.00 $0.00 $0.00 DIVISION 9010-SEEDING 44 9010-108-A-0 Conventional Seeding, Seeding, Fertilizing and Mulching SY 14500 13034 1,466.00 $0.36 $0.00 $527.76 DIVISION 9030-PLANT MATERIAL AND PLANTING 45 1 9030-108-C-0 Plants LS 1 1 1 0.00 $20,000.00 $0.00 $0.00 DIVISION 9040-EROSION AND SEDIMENT CONTROL 46 9040-108-A-2 SWPPP Management LS 1 1 0.00 $1,000.00 $0.00 $0.00 47 9040-108-N-1 Silt Fence or Silt Fence Ditch Check LF 1254 60 1194.00 $2.00 $0.00 $2,388.00 48 9040-108-N-2 Silt Fence or Silt Fence Ditch Check, Removal of Sediment LF 1254 0 1254.00 $0.50 $0.00M$627.0049 9040-108-N-3 Silt Fence or Silt Fence Ditch Check, Removal of Device LF 1254 60 1194.00 $0.50 $0.0050 9040-108-0-1 Stabilized Construction Entrance SQ 11 0 11.00 $70.00 $0.0051 9040-108-T-1 Inlet Protection Device, Filter Sock/Silt Fence EA 9 0 9.00 $100.00 $0.0052 9040-108-T-2 Inlet Protection Device, Maintenance EA 9 0 9.00 $25.00 $0.00 TOTALS $32,069.54 (75,605.56) Contract decrease due to measurement of installed quantities ($43,536.02) CONTRACTSUMMARY Original Contract Amount $665,611.50 Contract decrease due to measurement of installed quantities ($43,536.02) FINAL CONTRACT AMOUNT $622,075.48 Page 2 of 2 RESOLUTION NO. 356-14 ACCEPTING THE PUBLIC IMPROVEMENTS IN THE DUBUQUE INDUSTRIAL CENTER SOUTH — SOUTH SIEGERT FARM, PHASE II — PCC PAVING AND UTILITIES PROJECT, ESTABLISHING THE FINAL CONTRACT AMOUNT, AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR Whereas, Public Improvement Contract for the Dubuque Industrial Center South - South Siegert Farm, Phase II PCC Paving and Utilities (the Project) has been completed and the City Engineer has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and recommending that the Project be accepted. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The mayor and City Engineer are hereby directed to sign the DOT Certificate of Completion form. Section 3. The final contract amount is established as $622,075.48. The Finance Director is hereby directed to pay to the Contractor from the Revitalize Iowa's Sound Economy Rise (RISE) Program and General Obligation Bonds Proceeds (TIF -Abated) appropriations for the contract amount of $622,075.48 Tess any retained percentage provided for therein as provided in Iowa Code chapter 573, and to pay such retainage only in accordance with the provisions of Iowa Code chapter 573. Passed, approved and adopted this 17th day of November, 2014. ATTEST: Roy D. Buol, Mayor Form 640003 03,-04 wd Iowa Department of Transportation CERTIFICATE of COMPLETION and FINAL ACCEPTANCE of AGREEMENT WORK COMPANY: Horsfield Construction, Inc. COUNTY/CITY: Dubuque P.O. Box 305, 505 E. Main St. ADDRESS: Epworth, IA 52045 KIND OF WORK: PCC Paving & Utilities PROJECT NO.: RM -2100(677)--9D-31 AGREEMENT DATE: May 15, 2013 FIELD COMPLETION DATE: October 9, 2014 This is to certify that the work covered by the above referenced agreement has been completed in accordance with said agreement and is hereby accepted, subject to final audit of costs. SIGNATURE: *SIGNATURE: FOR IIW, P.C. Fect E" gineer (Res. Construction) (Area Engineer) (County) (City) (Consultant) Cody Austin, P.E. District (Construction) (Maintenance) (Local Systems) Engineer DATE: DATE: Year Approved and work accepted by the Board of Supervisors/City Council of this day of 2014 . Year Dubuque, Iowa, SIGNATURE: Chairman/Mayor Acknowledge completion of project in accordance with referenced agreement by the Iowa Department of Transportation this day of Year SIGNATURE: Iowa Department of Transportation *On Local State Assisted Projects District does NOT certify but acknowledges completion of project. DO NOT WRITE IN THIS BOX. CENTRAL OFFICE USE ONLY. (Check or Initial Appropriate Box) ❑ Office of Audits ❑ Copy to Company ❑Copies to District ❑ Original to Files CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE DUBUQUE INDUSTRIAL CENTER SOUTH PCC PAVING AND UTILITIES — PHASE II The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the Dubuque Industrial Center South PCC Paving and Utilities — Phase II, and that said Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $622,075.48. Dated this day of November, 2014. Filed in the office of the City Clerk on the Gus Psihoyos, City Engineer day of November, 2014. Ken S. Firnst1117-CfClerk