City of Dubuque Consent Items # 12.
ITEM TITLE: One-Way to Two-Way Conversion Project Acceptance
SUMMARY: City Manager recommending acceptance of the 9th Street and 11 th Street
One-Way to Two-Way Conversion Project, as completed by Portzen
Construction.
RESOLUTION Accepting the 9th Street and 11th Street One-Way to Two-
Way Conversion Project and authorizing the payment of the contract
amount to the contractor
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt Resolution(s)
ATTACHMENTS:
Description Type
❑ 9th and 11th Street One-Way to Two-Way Conversion-MVM Memo City Manager Memo
❑ Staff Memo Staff Memo
❑ Resolution Resolutions
THE CITY OF Dubuque
UBE I
erica .i
Masterpiece on the Mississippi 2007-2012-2013
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 9th Street and 11th Street One-Way to Two-Way Conversion Project
(CI P 3602442, 1021041, 3001029, 3001615, 3001631)
DATE: December 8, 2014
City Engineer Gus Psihoyos is recommending acceptance of the 9th Street and 11th
Street One-Way to Two-Way Conversion Project, as completed by Portzen
Construction, in the final contract amount of$813,528.35, which is a 2.1% increase from
the original contract of$797,011.20. The increase was due to additional work needed
for the ADA ramps and additional temporary signage required for the traffic conversion.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Micliael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
'I'3-IE C:IT'Y OF � ,.r°' ,�
Dubuque
DUB F AN•AmedcaChy
Masterpiece on the Mississippi
TO: Michael C. Van Milligen, City ManageL
FROM: Gus Psihoyos, City Engineer .
DATE: December 8, 2014
SUBJECT: 9th Street and 11th Street One-way to Two-way Conversion Project
(CIP 3602442, 1021041, 3001029, 3001615, 3001631)
INTRODUCTION
The enclosed resolution provides for the acceptance of the construction contract 9th Street and
11th Street One-way to Two-way Conversion Project.
DISCUSSION
This project involved the conversion of the following streets from one way to two way traffic:
• 9th Street between Locust Street and Kerper Boulevard
• 10th Street between Bluff Street and Central Avenue
• 11th Street between Central Avenue and Kerper Boulevard
• Elm Street from 9th Street to 11 th Street
• Pine Street from 9th Street to 11th Street
The construction work involved the reconfiguration of traffic signals at existing intersections, new
pavement markings, new signage, fiber optic vaults and conduit and pedestrian access ramps.
The two-way traffic pattern on the aforementioned streets began on August 17, 2014.
The railroad crossing signals on 9th street near Elm Street and on 11th Street near Elm Street
were relocated to allow for two-way traffic. City staff coordinated with Canadian Pacific Railroad to
perform this work.
City of Dubuque Engineering coordinated closely with the Iowa Department of Transportation
(IDOT) on this project. IDOT staff reviewed the proposed construction documents and concurred
with the conversion of the streets to two-way.
The 9th Street and 11th Street One-way to Two-way Conversion Project was completed by
Portzen Construction of Dubuque, Iowa, in the final contract amount of$813,528.35, which is a
2.1% increase from the original contract of$797,011.20. This increase is due to additional work
needed for the ADA ramps and additional temporary signage required for the traffic conversion.
RECOMMENDATION
I recommend that the City Council accept the improvements and establish the final contract at
$813,528.35 for the 9th Street and 11 th Street One-way to Two-way Conversion Project.
BUDGET IMPACT
The project cost summary for the 9th Street and 11 th Street One-way to Two-way Conversion
Project is as follows:
Award Final
Construction Contract $797,011.20 $813,528.35
Contingency 113,887.00 0.00
Construction Engineering & Inspection 367,998.00 208,763.71
Purchase of Traffic Equipment & Streetlights 281,971.00 291,635.38
Total Project Cost $1,560.867.20 $1,313,927.44
The project funding summary is as follows:
CIP No. Fund Description Fund Amount
3602442 1-way to 2-way Conversion Project $1,223,927.44
1021041 Curb/Catch Basin Replacement 30,000.00
3001615 Signal Intersection Reconstruction 30,000.00
3001631 Traffic Signal Fiber Optic Network 30,000.00
Total Project Funding $1,313,927.44
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolutions accepting the improvements,
establishing the final contract amount of $813,528.35, and for the payment of the contract amount
to Portzen Construction for the 9th Street and 11 th Street One-way to Two-way Conversion
Project.
Prepared by Jon Dienst, PE
cc: Jenny Larson, Budget Director
Don Vogt, Public Works Director
John Klostermann, Street & Sewer Maintenance Supervisor
Dave Ness, Civil Engineer II
Duane Richter, Civil Engineer 1
2
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE 9TH STREET
AND 11TH STREET ONE-WAY TO TWO-WAY CONVERSION PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the 9th Street and 11th Street One-way to Two-way Conversion
Project, that the Project has been performed in compliance with the terms of the Public
Improvement Contract, and that the total cost of the completed work is $1,313,927.44.
Dated this i 11'day ofl .43,4106,— 2014.
Gus Psihoyos, City Engineer
Filed in the office of the City Clerk on the et" day of .i'L..cX2014.
Trish L. Gleason, Assistant City Clerk
RESOLUTION NO. 382-14
ACCEPTING THE 9TH STREET AND 11TH STREET ONE-WAY TO TWO-WAY
CONVERSION PROJECT AND AUTHORIZING THE PAYMENT OF THE CONTRACT
AMOUNT TO THE CONTRACTOR
Whereas, the Public Improvement Contract for the 9th Street and 11th Street
One-way to Two-way Conversion Project (the Project) has been completed and the City
Engineer has examined the work and filed a certificate stating that the Project has been
completed according to the terms of the Public Improvement Contract and that the City
Engineer recommends that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the 1 -way to 2 -way Conversion Project fund, the Curb/Catch Basin Replacement fund,
The Signal Intersection Reconstruction fund and the Traffic Signal Fiber Optic Network
fund for the contract amount of $813,528.35 less any retained percentage provided for
therein as provided in Iowa Code chapter 573, and to pay such retainage only in
accordance with the provisions of Iowa Code chapter 573.
Passed, approved and adopted this 15th day of December,
Attest:
Trish L. Gleason, Assistant City Clerk
14.
Roy D. Buol, Mayor