Public Works Director Don Vogt is recommending acceptance of the construction
contract for the Floodwall Pumping Station Improvement Projects, as completed by
Kluck Construction, in the final contract amount of $465,730.81, which is a 4.3%
increase from the original contract by the amount of $19,310.01. The cost increase was
due to additional work at the Bee Branch and Hawthorne Street Floodwall Pumping
Stations, including the removal of a utility pole (Hawthorne), the relocation of an
electrical service (Hawthorne), the replacement of a transformer (Hawthorne), additions
to the Bee Branch screen wall and sidewalk, and, changes to the Bee Branch platform
foundation. Funding is available in the project budget.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
^~ ..
~, w^1
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Don Vogt, Public Works Director
THE CTTY OF
DUB E
Masterpiece on the Mississippi
October 26, 2007
TO: Michael C. Van Milligen, City Manager f
V
FROM: Don Vogt, Public Works Director (~
~/
Public Works Department
925 Kerper Court
Dubuque, Iowa 52001
(563) 589-4250 (office)
(563) 589-4252 (fax)
(563) 589-4193 (TDD)
SUBJECT: Floodwall Pumping Station Improvement Projects
INTRODUCTION
The attached resolutions provide for the acceptance of the construction contract for the
Floodwall Pumping Station Improvement Projects. The base bid for these combined
projects provides for the purchase and installation of generators, transfer switches,
generator enclosures and associated conduit and wiring for providing auxiliary power to
the foodwall pumps located at the Hawthorne Street and Maus Lake pumping facilities.
The projects also provide for the replacement of the 150 horsepower pump control,
installation of two manual transfer switches, construction of a support wall, generator
pad, concrete sidewalk, handrail, and steps, and installation of fencing at the Bee
Branch pumping facility.
DISCUSSION
Work has been completed on the projects by Kluck Construction in the final contract
amount of $465,730.81. I recommend that the City Council accept the improvements
and the final contract price be established at $465,730.81, which is a 4.3% increase
from the original contract by the amount of $19,310.01.
The cost increase was due to additional work at the Bee Branch and Hawthorne Street
Floodwall Pumping Stations, including the removal of a utility pole (Hawthorne), the
relocation of an electrical service (Hawthorne), the replacement of a transformer
(Hawthorne), additions to the Bee Branch screen wall and sidewalk, and, changes to
the Bee Branch platform foundation.
BUDGET IMPACT
A summary of the combined projects is as follows:
Estimate Bid with Alternates Final
Construction Contract $ 440,430.00 $ 446,420.80 $465,730.81
Contingency 48,936.00 42,945.20 0.00
Engineering 66,400.00 66,400.00 66,400.00
TOTAL CONSTRUCTION $ 555.766.00
$ 555.766.00 $532.130.81
The project funding summary is as follows:
CIP No. Fund Description Amount
1001550 Bee Branch Sidewalk $ 20,400.00
1001571 Maus Lake Floodwall Pump $ 54,002.00
7201668 Bee Branch Pump Control $ 43,642.00
7201377 Bee Branch Pump Auxiliary Power Project $335,350.00
7201661 Hawthorne Street Floodwall Pump $102,372.00
Total Project Funding $555,766.00
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolutions accepting the
improvements and establishing the final construction cost.
Dubuque
a~-an~cacm~
zoos
CITY OF DUBUQUE
Date: October 26, 2007
FINAL ESTIMATE FOR: Public Works Department Floodwall Pumping Stations
Improvement Projects.
Furnish all labor and materials for the Public Works Department Floodwall Pumping
Stations Improvement Projects,
Total Due Contractor $465,730.81
Engineering $ 66,400.00
Total Construction Cost $532,130.81
I hereby certify that the above statement shows in detail the correct amount of all work
required to complete the above improvement.
Approved:
Michael C. Van Milligen Donald J. Vogt
City Manager Public Works Director
The undersigned, ,contractor for the above
improvement, does hereby accept the above "Total Due Contractor", as full settlement
for all claims for said improvements.
Contractor: Kluck Construction
By:
RESOLUTION NO. 527-07
ACCEPTING FLOODWALL PUMPING STATION IMPROVEMENTS AND
AUTHORIZING PAYMENT TO THE CONTRACTOR
Whereas, the contract for the Public Works Department Floodwall Pumping
Stations Improvement Projects has been completed and the City Manager has
examined the work and filed his certificate stating that the same has been completed
according to the terms of the contract, plans and specifications and recommends its
acceptance.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. That the recommendation of the City Manager be approved and that
said improvement is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the General Fund and the Stormwater Construction Fund equal to the final amount of
this contract, $465,730.81, less any retained percentage provided for therein as
provided in Iowa Code Chapter 573, and to pay such retainage only in accordance with
the provisions of Iowa Code Chapter 573.
Passed, approved and adopted this 5th day of November, 2007.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
RESOLUTION NO. 07
FINAL ESTIMATE
Whereas, the contract for the Public Works Department Floodwall Pumping
Stations Improvement Projects has been completed and the Public Works Director has
submitted his final estimate showing the cost thereof including the cost of estimates,
notices and inspection and all miscellaneous costs;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. That the cost of said improvement is hereby determined to be
$465,730.81 and the said amount shall be paid from the General Fund and the
Stormwater Construction Fund of the City of Dubuque, Iowa.
Passed, approved and adopted this day of , 2007.