US 52 Storm Sewer Improvement AcceptanceDubuque
THE. CITY OF
~~•
~T T~ L, All-An~ricaCity
Masterpiece orr the Mississippi
2007
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: US 52 North Storm Sewer Improvement Project
(CIP 7201810 &CIP 1001122)
DATE: November 26, 2007
City Engineer Gus Psihoyos is recommending acceptance of the improvements for the
US 52 North Storm Sewer Improvement Project, as completed by McClain Excavating
Company, in the final contract amount of $178,150.63.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
V~~
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gus Psihoyos, City Engineer
THE CITY OF Dubuque
DT TT1 ~ All-AmericaCity
V j,~
Masterpiece or7. the Mississippi
2007
TO: Michael C. Van Milligen, City Mana
FROM: Gus Psihoyos, City Engineer
SUBJECT: US52 North Storm Sewer Improvement Project
(CIP 7201810 &CIP 1001122)
DATE: November 21, 2007
INTRODUCTION
The enclosed resolution provides for the acceptance of the improvements for the US52
North Storm Sewer Improvement Project.
BACKGROUND
The US52 North Storm Sewer Improvement Project entailed the replacement of 24-inch
diameter storm sewer with a 48-inch diameter storm sewer from the Flexsteel pumping
station to US 52 and the replacement of two catch basins located at the low spot (sump)
in US52 north of Olympic Heights and south of the Shooting Club drive.
With jurisdiction over US52, the Iowa Department of Transportation (Iowa DOT) also
had an interest in adequate stormwater drainage of the highway. As a result, the Iowa
DOT indicated that the project is eligible for Iowa DOT cost-sharing.
DISCUSSION
The US52 North Storm Sewer Improvement Project was completed by McClain
Excavating Company, Inc. of Peosta, Iowa, in the final contract amount of $178,150.63,
which is a 6.1 % decrease from the original contract of $189,712.
The primary reason for the decreased project cost is that only 28% of the estimated lime
backfill was necessary. This was a savings of $11,490.84.
RECOMMENDATION
recommend that the City Council accept the improvements and to authorize the
payment of the contract amount of $178,150.63 to McClain Excavating Company for the
US52 North Storm Sewer Improvement Project.
BUDGET IMPACT
The project cost summary for the US52 North Storm Sewer Improvement Project is
summarized as follows:
Award Final
Construction Contract $189,712.00 $178,150.63
Contingency 24,314.00
Engineering 40,119.00 41,899.15
Right-of-Way/Easement 3,072.00 3,049.50
$257,217.00 $223,099.28
According to the guidelines provided by the Iowa DOT, they will contribute $39,565.64
in project costs as part of an interagency agreement. This revenue will be applied
toward the project. The project will be funded as follows:
CIP CIP Name Amount
1001122 Jackson & Aquin Drainage $165,560.00
7201810 US52 Storm Sewer 57.539.28
Total Funding $223,099.28
The remaining balance of US 52 Storm Sewer CIP budget will be reserved for additional
storm sewer improvements to be done in conjunction with the Iowa DOT resurfacing of
US52 North in FY2009.
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution to accept the
improvements and to authorize the payment of the contract amount of $178,150.63 to
McClain Excavating Company for the US52 North Storm Sewer Improvement Project.
Prepared by Deron Muehring, Civil Engineer II
cc: Jenny Larson, Budget Director
Deron Muehring, Civil Engineer II
RESOLUTION NO. 566-07
ACCEPTING THE US52 NORTH STORM SEWER IMPROVEMENT PROJECT
AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE
CONTRACTOR
Whereas, the Public Improvement Contract for the US52 North Storm Sewer
Improvement Project (the Project) has been completed and the City Engineer has
examined the work and filed a certificate stating that the Project has been completed
according to the terms of the Public Improvement Contract and that the City Engineer
recommends that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the Jackson & Aquin Drainage Capital Improvement Project ($165,560.00) and US52
Storm Sewer Capital Improvement Project ($12,590.63) appropriation for the contract
amount of $178,150.63 less any retained percentage provided for therein as provided in
Iowa Code chapter 573, and to pay such rtainage only in accordance with the
provisions of Iowa Code chapter 573.
Passed, approved and adopted this 3rd day of December 2007.
Roy D. Buol, Mayor
Attest:
Jeanne F. Schneider, CMC, City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE US52
NORTH STORM SEWER IMPROVEMENT PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the US52 North Storm Sewer Improvement Project, that the Project
has been performed in compliance with the terms of the Public Improvement Contract,
and that the total cost of the completed work is $223,099.28.
Dated this 28th day of November, 2007.
City Engineer
Filed in the office of the City Clerk on the 29th day of November, 2007.
Jeanne F. Schneider, CMC, City Clerk
Project Name: uS52 NORTH
PROJECT CLOSE OUT FORM STORM SEWER IMPROVEMENT
CIP Number: CIP # : 1001122 & 7201810
rxe cmr of City of Dubuque Project Contract Amount: $189,712.00
Engineering
DT T
T Project Com letion Date: 12-Oct-o7
~
B
lJ 1. 50. W. 13th Street
- Dubuque, IA 52001
Masterpiece on the Mississiyyi Contractor Name: McClain Excavatin Co., Inc.
(563) 589-4270
Contractor Address:
P.O. Box 77
City, State, Zip: Peosta, IA 52068-0077
Contractor Tele hone: 563-556-2348
ITEM
NO. CONTRACT ITEM
DESCRIPTION CONTRACT ITEM
QUANTITY UNIT UNIT PRICE PROJECT TOTAL
QUANTrrY TOTAL PERCENT
COMPLETE TOTAL
Over /Under
1 Clearing & Grubbing 25860 SF $ 0.10 25860.00 $ 2,586.00 100.00% $ -
2 Topsoil Strip, Salvage, Stockpile and Spreading 94 CY $ 10.00 94.00 $ 940.00 100.00% $ -
3 Lime Backfill 2650 Ton $ 6.00 734.86 $ 4,409.16 27.73% $ (11,490.84)
4 Subbase (Patches) 241 SY $ 10.00 214.03 $ 2,140.30 88.81% $ (269.70)
5 Granular Surfacing 190 Tan $ 12.00 120.86 $ 1,450.32 63.61% $ (829.68)
6 Bedding Stone, 1" Clean 700 Ton $ 10.50 1077.08 $ 11,309.34 153.87% $ 3,959.34
7 Hot Mix Asphalt (Composite Section) 35 Ton $ 217.00 40.21 $ 8,725.57 114.89% $ 1,130.57
8 Patches, Full Depth Finish, By Count 8 Each $ 5.00 8.00 $ 40.00 100.00% $ -
9 Patches, Full Depth Finish, By Area 224 SY $ 65.00 214.03 $ 13,911.95 95.55% $ (648.05)
10 Plowable Mortar 17 CY $ 145.00 3.50 $ 507.50 20.59% $ (1,957.50)
11 RCP Storm Sewer 15" 6 LF $ 36.00 8.00 $ 288.00 133.33% $ 72.00
12 RCP Storrs Sewer 18" 6 LF $ 37.50 8.00 $ 300.00 133.33% $ 75.00
13 RCP Storm Sewer 24" 60 LF $ 130.00 55.00 $ 7,150.00 91.67% $ (650.00)
14 RCP Storm Sewer 36" 6 LF $ 57.00 8.00 $ 456.00 133.33% $ 114.00
15 RCP Stone Sewer 42" 75 LF $ 58.00 80.00 $ 4,640.00 106.67% $ 290.00
16 RCP Stone Sewer 48" 923 LF $ 67.50 914.50 $ 61,728.75 99.08% $ (573.75)
17 Stone Sewer, Manhole Type "M-A" 84" 3 Each $ 5,000.00 3.00 $ 15,000.00 100.00% $ -
18 Stone Sewer, Manhole Type "M-A" 108" 1 Each $ 6,960.00 1.00 $ 6,960.00 100.00% $ -
19 RCP Aprons Stone Sewer 48" 1 Each $ 800.00 1.00 $ 800.00 100.00% $ -
20 Stone Sewer, Intake RA-43 2 Each $ 2,950.00 2.00 $ 5,900.00 100.00% $ -
21 Storm Sewer, Intake RA-62 Modified 2 Each $ 2,570.00 2.00 $ 5,140.00 100.00% $ -
22 Removal of Intakes 2 Each $ 750.00 2.00 $ 1,500.00 100.00% $ -
23 Removal of Manholes 3 Each $ 750.00 3.00 $ 2,250.00 100.00% $ -
24 Storm Sewer Pipe, 24" HDPE 34 LF $ 40.00 34.00 $ 1,360.00 100.00% $ -
25 Seeding, Fertilizing & Mulching 2721 SY $ 1.00 2721.00 $ 2,721.00 100.00% $ -
26 Soil Erosion, Silt fences for ditch checks 90 LF $ 3.00 0.00 $ - 0.00% $ (270.00)
27 Soil Erosion, Silt fence 1050 LF $ 1.50 0.00 $ - 0.00% $ (1,575.00)
28 Stone Revetment Class C (Rip Rap) 50 Ton $ 22.00 13.77 $ 302.94 27.54% $ (797.06)
29 Revetment, Fabric, Engineering 92 SY $ 1.50 0.00 $ - 0.00% $ (138.00)
30 Fence, Remove & Replace Chain link 91 LF $ 1.50 262.00 $ 393.00 287.91% $ 256.50
31 Traffic Control 1 LS $ 8,500.00 1.00 $ 8,500.00 100.00% $ -
32 Mobilization 1 LS $ 5,000.00 1.00 $ 5,000.00 100.00% $ -
Sub Total $ 176,409.83 $ (13,302.17)
. ~ ~ -
CHANGE ORDERS
No. Date Description
1
16-Jul-07
Add drain file around storm sewerjunction boxes and manholes TOTAL
2
26-Jul-07 .
Excavate Fiber and cut pipe to span gas main. $480.C
3
6-Nov-07
Delete Item 26, Soil Erosion, Sik Fence for ditch checks -due to terrain, not required $1,260.8
4
6-Nov-07 .
Delete Item 27, Soil Erosion, Silt Fence -due to terrain, not required.
$0 0
5 6-Nov-07 Delete Item 29, Revetment, Fabric, Engineering -due to terrain, not reauimd $0.0
Sub Total ~ $1
PROJECT COST SUMMARY
Total Contract Work Performed to Date:
Total Change Order Work Performed to Date:
Total Contract and Change Order Work Due Contractor:
Total miscellaneous Project Costs:
Total Engineering Work Pertormed:
Total Land Acquiskion and/or Easement Costs:
TOTAL PROJECT COST:
I hereby certify that the above statement shows, in detail, the correct
amount of all work required to complete the above improvement.
Gus Psihoyos, City Engineer
Dubuque, Iowa
APPROVED: DATE
Michael Van Milligen, City Manager
Dubuque,lowa __...
_ ~~ ~
L- _ - ,~ Li-~'t~~ DATE / ~ ~Z~l "
$ 176,409.83
$1,740.80
$178,150.63
$ -
$ 41,899.15
$ 3,049.50
$217,000.28
The Undersigned,~CLCu1~1lCA~tatWC~c~ un,contractorfortheabove
improvement, does hereby accept the above "Total Due Contractor", as
full settlement fora ims f r said imp ement.
APPROVED: DATE
BY: