TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Five Flags HVAC and Promenade Roof Replacement Project
#1514 and #1885
DATE: December 13, 2007
Leisure Services Manager Gil Spence is recommending award of the contract for the
Five Flags HVAC and Promenade Roof Replacement Project to the low bidder, Giese
Sheet Metal Company, Inc., in the amount of $700,580. The Fiscal Year 2008 Capital
Improvement Program budget contains $600,000 for the HVAC replacement and
$70,000 for the promenade roof replacement. The project is $110,580 over budget.
Leisure Services Manager Gil Spence recommends that funds be shifted from the
theater stage lift project budgeted at $175,000 to fund the added cost.
This will leave just over $9,000 to cover part of the recommendation fora $15,000
contingency.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
~~~~ ~~,
~ ~ ~~.
Michael C. Van Milligen
MCVM/jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Gil D. Spence, Leisure Services Manager
. THE CITY OF Dubuque
DUB E
i r
Masterpiece on the Mississippi
2007
TO: Michael C. Van Milligen, City Manager
FROM: Gil D. Spence, Leisure Services Manage
SUBJECT: Five Flags HVAC and Promenade Roof eplacement Project
#1514 and #1885
DATE: December 10, 2007
INTRODUCTION
The purpose of this memorandum is to request that the City Council award a contract to
Giese Sheet Metal Company, Inc. for the Five Flags HVAC and Promenade Roof
Replacement Project.
DISCUSSION
Sealed bids were received on December 6, 2007 for the Five Flags HVAC and
Promenade Roof Replacement Project. A summary of the bids received is as follows:
Geisler
Giese Brothers
Base bid $ 489,300 $ 622,200
Alternate #1 * 156,600 163,200
Alternate #2 * 37,180 49,450
Alternate #3 '~ 9,000 2,520
Alternate #4 51,012 29,295
Alternate #5 * 8,500 8,800
Alternate #6 45,900 0
TOTAL, with $ 700,580 $ 846,170
recommended alternates
* Recommend alternates be accepted.
continued
page two
A summary of the six alternates is as follows:
• Alternate #1 replaces the hot water boiler and domestic hot water heater.
• Alternate #2 replaces the existing condenser serving the theater. This unit is
located on the Promenade roof and is old, so it's a good time to replace it, with the
roof replacement.
• Alternate #3 provides atwenty-year roof system and warranty in lieu of the fifteen-
year roof system and warranty.
• Alternate #4 provides a 90 mil roof system and thirty-year warranty in lieu of a
fifteen-year roof system and warranty.
• Alternate #5 removes all pneumatic controls from the basement mechanical room
and replaces them with DDC controls.
• Alternate #6 covers existing metal panels that are from the roof up the side of the
building, with a new panel system.
Alternates #1 and #2 were part of the original plan but were broken out of the base bid
because of funding concerns with the cost estimate. Alternate #3 is recommended
because an added five years to the roof warranty for $9,000 seems like a good deal.
Alternate #6 is recommended because this will put all the mechanical system under one
system of controls.
A summary of projects costs would be as follows:
construction contract $ 700,580
contingency 15,000
design fees 65,000
TOTAL $ 780, 580
The FY 2008 C.I.P. budget contains $600,000 for the HVAC replacement and $70,000
for the promenade roof replacement. The project is $110,580 over budget and I
recommend that funds be shifted from the theater stage lift project ($175,000) to fund
the added cost.
RECOMMENDATION
I recommend that the contract be awarded to Giese Sheet Metal Company, Inc. in the
amount of $700,580, accepting Alternates 1, 2, 3 and 5.
ACTION STEP
The action requested is that the City Council adopt the attached resolutions awarding a
contract to Giese Sheet Metal Company, Inc. in the amount of $700,580 for the Five
Flags HVAC and Promenade Roof Replacement Project.
GDS:et
attachment
Preparers Gil D. Spence Address: 2200 Bunker Hill Rd Phone: X589) 589-4263
RESOLUTION NO.
AWARDING CONTRACT
WHEREAS, sealed proposals have been submitted by contractors forthe Five Flags
HVAC and Promenade Roof Replacement Project pursuant to Resolution No. 537-07, and
notice to bidders published in a newspaper published in the City of Dubuque, Iowa, on the
9th day of November, 2007.
WHEREAS, said sealed proposals were opened and read on the 6th day of
December, 2007, and it has been determined that the bid of Giese Sheet Metal Company,
Inc. in the amount of $700,580 was the lowest bid for the furnishings of all labor and
materials and performing the work as provided for in the plans and specifications.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
That the contract for the above improvement be awarded to Giese Sheet Metal
Company, Inc., and the Manager be and is hereby directed to execute a contract on behalf
of the City of Dubuque for the complete performance of the work.
BE IT FURTHER RESOLVED:
That upon the signing of said contract and the approval of the contractor's bond, the
City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful
bidders.
Passed, approved and adopted this day of , 2007.
Attest:
Roy D. Buol, Mayor
Jeanne F. Schneider, City Clerk
THE CTTY OF Dubuque
DUB
E
Masterpiece on the Mississippi
2007
TO: Michael C. Van Milligen, City Manager
FROM: Gil D. Spence, Leisure Services Manager
SUBJECT: Five Flags HVAC and Promenade Roof Replacement Project
#1514 and #1885
DATE: December 10, 2007
INTRODUCTION
The purpose of this memorandum is to request that the City Council award a contract to
Giese Sheet Metal Company, Inc. for the Five Flags HVAC and Promenade Roof
Replacement Project.
DISCUSSION
Sealed bids were received on December 6, 2007 for the Five Flags HVAC and
Promenade Roof Replacement Project. A summary of the bids received is as follows:
Geisler
Giese Brothers
Base bid $ 489,300 $ 622,200
Alternate #1 * 156,600 163,200
Alternate #2 * 37,180 49,450
Alternate #3 * 9,000 2,520
Alternate #4 51,012 29,295
Alternate #5 * 8,500 8,800
Alternate #6 45,900 0
TOTAL, with $ 700,580 $ 846,170
recommended alternates
* Recommend alternates be accepted.
continued
page two
A summary of the six alternates is as follows:
• Alternate #1 replaces the hot water boiler and domestic hot water heater.
• Alternate #2 replaces the existing condenser serving the theater. This unit is
located on the Promenade roof and is old, so it's a good time to replace it, with the
roof replacement.
• Alternate #3 provides atwenty-year roof system and warranty in lieu of the fifteen-
year roof system and warranty.
• Alternate #4 provides a 90 mil roof system and thirty-year warranty in lieu of a
fifteen-year roof system and warranty.
• Alternate #5 removes all pneumatic controls from the basement mechanical room
and replaces them with. DDC controls.
• Alternate #6 covers existing metal panels that are from the roof up the side of the
building, with a new panel system.
Alternates #1 and #2 were part of the original plan but were broken out of the base bid
because of funding concerns with the cost estimate. Alternate #3 is recommended
because an added five years to the roof warranty for $9,000 seems like a good deal.
Alternate #6 is recommended because this will put all the mechanical system under one
system of controls.
A summary of projects costs would be as follows:
construction contract $ 700,580
contingency 15,000
design fees 65,000
TOTAL $ 780,580
The FY 2008 C.I.P. budget contains $600,000 for the HVAC replacement and $70,000
for the promenade roof replacement. The project is $110,580 over budget and I
recommend that funds be shifted from the theater stage lift project ($175,000) to fund
the added cost.
RECOMMENDATION
I recommend that the contract be awarded to Giese Sheet Metal Company, Inc. in the
amount of $700,580, accepting Alternates 1, 2, 3 and 5.
ACTION STEP
The action requested is that the City Council adopt the attached resolutions awarding a
contract to Giese Sheet Metal Company, Inc. in the amount of $700,580 for the Five
Flags HVAC and Promenade Roof Replacement Project.
GDS:et
attachment
Preparers Gil D. Spence Address: 2200 Bunker Hill Rd Phone: (589) 589-4263
RESOLUTION NO. 593-07
AWARDING CONTRACT
WHEREAS, sealed proposals have been submitted by contractors for the Five Flags
HVAC and Promenade Roof Replacement Project pursuant to Resolution No: 537-07, and
notice to bidders published in a newspaper published in the City of Dubuque, Iowa, on the
9th day of November, 2007.
WHEREAS, said sealed proposals were opened and read on the 6th day of
December, 2007, and it has been determined that the bid of Giese Sheet Metal Company,
Inc. in the amount of $700,580 was the lowest bid for the furnishings of all labor and
materials and performing the work as provided for in the plans and specifications.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
That the contract for the above improvement be awarded to Giese Sheet Metal
Company, Inc., and the Manager be and is hereby directed to execute a contract on behalf
of the City of Dubuque for the complete performance of the work.
BE IT FURTHER RESOLVED:
That upon the signing of said contract and the approval of the contractor's bond, the
City Treasurer is authorized and instructed to return the bid deposits of the unsuccessful
bidders.
Passed, approved and adopted this 17th day of December , 2007.
Roy D. Buol, Mayor
Attest: