2015 SCADA Manhole Installation Project - Award Copyright 2014 City of Dubuque Consent Items # 3. ITEM TITLE: SCADA Manhole Installation Project Award SUMMARY: City Manager recommending award of the construction contract for the 2015 SCADA (Flow Metering Stations) Manhole Installation Project to the low bidder, Connolly Construction, Inc. RESOLUTION Awarding public improvement contract for the SCADA (Flow Metering Stations) Manhole Installation Project SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt Resolution(s) ATTACHMENTS: Description Type ❑ SCADA Manhole Installation Project-MVM Memo City Manager Memo ❑ Staff Memo Staff Memo ❑ Resolution Resolutions ❑ Bid Tab Supporting Documentation THE CITY OF Dubuque UBE I erica .i Masterpiece on the Mississippi 2007-2012-2013 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: 2015 SCADA (Flow Metering Stations) Manhole Installation Project CI P 7101335 DATE: December 1, 2015 Sealed bids were received for the 2015 SCADA (Flow Metering Stations) Manhole Installation Project. City Engineer Gus Psihoyos recommends award of the construction contract to the low bidder, Connolly Construction, Inc., in the amount of $127,339.97, which is 20.97% over the estimate of probable cost. The cost increase is due to the complicated nature of the project with the incorporation of fiber optic communication to each of the manholes. Sufficient funds are available in the project budget. I concur with the recommendation and respectfully request Mayor and City Council approval. Micliael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Gus Psihoyos, City Engineer THE ciTY OI� Dubuque DUB E Aill3A•mei•Hica11i1 I Masterpiece oti the Mississippi 71107,2012 2.2013 TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer) SUBJECT: 2015 SCADA (flow metering stations) Manhole Installation Project CIP 7101335 DATE: November 25, 2015 INTRODUCTION The enclosed resolution authorizes the award of the construction contract for the 2015 SCADA (flow metering stations) Manhole Installation Project. BACKGROUND The City of Dubuque, Iowa has entered into a Consent Decree in the case of The United States of America, and the State of Iowa v. The City of Dubuque, Iowa, Civil Action No. Case 2:11-cv-01011-EMJ, Civil Action Number 2008V00041, DOJ Case Number 90-5-1-1-09339, United States District Court for the Northern District of Iowa. The provisions of the Consent Decree apply to and are binding upon the City and its officers, directors, employees, agents, servants, successors, assigns, and all persons, firms and corporations under contract with the City to perform the obligations of the Consent Decree. The City is required to perform collection system flow monitoring per a schedule established in the Consent Decree, the City is flow monitoring beyond the schedule using supervisory control and data acquisition (SCADA) system technology in sanitary sewer manholes. We are requesting several sanitary sewer manholes (flow metering stations) be replaced to provide the best conditions for permanent flow monitoring. DISCUSSION The Consent Decree identifies five sewersheds that are required to be individually flow metered for specific periods over a five year schedule. While flow metering for short periods of time may result in locating inflow under one or two rain events, it will not capture how the sanitary sewer system will perform under different or changing rain patterns more commonly seen. Long term or permanent flow monitoring is a method used to continually meter the sanitary sewer system, so staff can observe changes in flow; document and measure how rain events impact the system; and provide valuable feedback on how capital improvements have or have not reduced inflow. The proposed permanent flow metering stations are designed to not only monitor and record flows, but also report them in real-time triggering an alarm if there are any changes in the system FAPROJECTS\Storm and Sanitary\Sanitary\SCADA Manholes\Council\INITIATE\Initiate Memo-2015 SCADA Manhole Installation Project.doc where a flow meter is in place. In the event of increased flows or water level changes, or a fouled meter sensor, the flow metering stations will report via the SCADA system to Public Works, the W&RRC, and the Engineering department for immediate response to reduce the possibility of sanitary sewer overflows. This project involves the replacement of four(4) sanitary sewer manholes and their conversion to permanent flow metering stations in Sewersheds 7 (a & b), 11, and 12, please see the following location map. .17cflow &lufiltratiou 11rogrton Sanitary Sew,sheds To&"nspeded a 4qy/*4th KENNEDY RQ 0 r DERBY GRANGE RD ` IL �v W 32ND ST 61115 KALFMAI NSI AVE V • D i. KR LCRbST RD z i • � Sew 'Ile 1 7 tiF m o FKfF RU PENN$YLVANIAAVE w r 1xe t a2 °c� GNAY£N l£ RD rmi. Q f 1 DAGIS The flow metering station for Sewershed 5 is installed and will be operational by November 11, 2015; and the metering station for Sewershed 10 will be delayed until the completion of Phase 2 of the Bee Branch project. Portions of some water mains may need to be relocated as part of this project due to the replacement of the manholes. BID RESULTS The City of Dubuque received the following bids for the 2015 SCADA (flow metering stations) Manhole Installation Project, on November 19, 2015: Contractor Bid Results Connolly Construction, Inc. $ 127,339.97 Portzen Construction, Inc. $ 184,429.50 2 Tschiggfrie Excavating $ 187,712.49 Miller Trucking & Excavating $ 267,002.25 Connolly Construction, Inc. of Peosta, Iowa, submitted the low bid in the amount of $127,339.97. This amount is 20.97% over the estimate of probable cost. The cost increase is due to the complicated nature of the project with the incorporation of fiber optic communication to each of the manholes. RECOMMENDATION I recommend that the contract for the 2015 SCADA (flow metering stations) Manhole Installation Project be awarded to Connolly Construction, Inc. in the amount of $127,339.97. BUDGETIMPACT The estimate of probable cost for the 2015 SCADA(flow metering stations) Manhole Installation Project: Estimate Award Construction Contract $ 105,000.00 $ 127,339.97 Contingency 10,500.00 12,734.00 Construction Engineering & Inspection 15,750.00 21,011.10_ Total Project Cost $131,250.00 $161,085.07 The project funding summary is as follows: Available CIP No. Fund Description Funding 7101335 Sanitary Sewer Manhole Replacement $ 267,000.00 REQUESTED ACTION I recommend that the City Council adopt the attached resolution awarding the construction contract for the 2015 SCADA (flow metering stations) Manhole Installation Project to Connolly Construction, Inc. in the amount of$127,339.97. cc: Jenny Larson, Budget Director Gus Psihoyos, City Engineer Ken TeKippe, Finance Director Todd Irwin, Engineering Technician 3 RESOLUTION NO. 404-15 AWARDING PUBLIC IMPROVEMENT CONTRACT FOR THE SCADA (FLOW METERING STATIONS) MANHOLE INSTALLATION PROJECT Whereas, sealed proposals have been submitted by contractors for the SCADA (flow metering stations) Manhole Installation Project (the Project) pursuant to Resolution No. 379-15 and Notice to Bidders published in a newspaper published in the City of Dubuque, Iowa on the 6th day of November, 2015. Whereas, said sealed proposals were opened and read on the 19th day of November, 2015, and it has been determined that Connolly Construction, Inc. of Peosta, Iowa, with a bid in the amount of $127,339.97, is the lowest responsive, responsible bidder for the Project. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: That a Public Improvement Contract for the Project is hereby awarded Top Grade Excavating, Inc. and the City Manager is hereby directed to execute a Public Improvement Contract on behalf of the City of Dubuque for the Project. Passed, approved and adopted this 7th day of December, 2015. Attest: Kev n Firnstahl, GM, City Clerk V. Sutton, Mayor Pro Tem trs crryos E DUB Masterpiece on the Mississippi City of Dubuque,Iowa Bid Tabulation Pro]ed Name: 2015 SCADA(Flow Metering Stations)Manhole l nstallatlon Project Bid Daze Engineers Estim ate Connolly Construcing Inc. Portaen Construction Tscbiggfrie Excavating Miller Trucking B Excavating 19-Nov-15 LINE I ESTIMATED 0. NU RNUMBERE BID REM DESCRIPTION OONNTRv UNIT UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE Division 1-General Provisions 1 1090T05 Mobllhabon 1 ITS $ 10,00090 $ 10,00090 $ 8,50090 $ 8,50090 $ 15,00090 $ 15,00090 $ 18,76270 $ 1876270 $ 40,00090 $ 40,00090 Sub Total $ 1090090 Sub Total $ 8,50090 Sub Total $ 1590090 Sub Total $ 18 762 70 Sub Total $ 4090090 Division 3010-Trench Excavated and Backfill 2 301010880 Trench Foundation-3"Breaker 20 TON $ 2090 $ 40090 $ 16 35 $ 32790 $ 3090 $ 60090 $ 3870 $ 77490 $ 1500 $ 30090 3 301010880 Bedding Matenal,1 Commercial Clean Stone 50 TON $ 1500 $ 75090 $ 1890 $ 80090 $ 2890 $ 1,40090 $ 3340 $ 1,67090 $ 1200 $ 60090 4 301010880 Replacement of Unsuitable Backfill Matenal Gradation 32 220 TON $ 1500 $ 3,30090 $ 1550 $ 3,41090 $ 2200 $ 4,84090 $ 2850 $ 8,27090 $ 1200 $ 2,64090 5 201O108L0 Compaction Testing 1 ITS $ 1,20090 $ 1,20090 $ 78590 $ 78500 $ 4,50090 $ 4,50090 $ 27590 $ 27500 $ 4,50090 $ 4,50090 6 3010108)-2 Trenching,26 Inch Depth 320 LF $ 890 $ 1,92090 $ 640 $ 2,04890 $ 890 $ 2,56090 $ 7.10 $ 2,27200 $ 790 $ 2,24090 7 3010108)-3 Trenching,48 Inch Depth 485 LF $ 890 $ 3,88090 $ 890 $ 3,88090 $ 1190 $ 5,33590 $ 1180 $ 5,82890 $ 1090 $ 4,85090 Sub Total $ 1145090 Sub Total $ 11,25090 Sub Total $ 1923590 Sub Total $ 1688790 Sub Total $ 15,13090 Drasi 3020-Tramblas Construction 8 3010108x0 Directional Drilling,who Pipe 175 LF $ 2090 $ 3,50090 $ 1965 $ 3,43875 $ 1650 $ 2,88750 $ 2430 $ 4,25250 $ 3500 $ 8,12500 Sub Total 7--7777 90 Sub Total 7--7777 43875 Sub Total 7-7777 Sub Total 7--7777 50 Sub Total $ 5125 90 Division aoio-sanitary Severs 9 4010108-A1 Sandary Sewer Shockley Main,Trenched 12 PVC 84 LF $ 5090 $ 4,20090 $ 9430 $ 7,92120 $ 24090 $ 20,16090 $ 7585 $ 8,37140 $ 40090 $ 33,60090 10 4010108-hi Sandary Sewer Shockley Main,Trenched 12 DIP 18 LF $ 8500 $ 1,53090 $ 18275 $ 3,28950 $ 29090 $ 5,22090 $ 9935 $ 178830 $ 50090 $ 9,00090 11 401010881 Sandary Sewer Shockley Main with Casing Pipe,Trenched 12 DIP 50 LF $ 15090 $ 7,50090 $ 17750 $ 8,87500 $ 31090 $ 15,50090 $ 21785 $ 10,89250 $ 55090 $ 27,50090 12 4010108E-1 Sandary Sewer Service Pipe,Trenched 4"DIP 5 LF $ 5500 $ 27590 $ 14790 $ 73500 $ 35090 $ 1,75090 $ 29685 $ 1,48425 $ 90090 $ 4,50090 Sub Total $ 1350590 Sub Total $ 20,82070 Sub Total $ 4293090 Sub Total $ 20,53645 Sub Total $ 7490090 Division 5010-Pipe and Fittings 13 5010108-A1 Water Main,Trenched DIP,B 30 LF $ 4500 $ 1,35090 $ 2890 $ 78090 $ 14090 $ 4,20090 $ 7260 $ 2,17890 $ 62090 $ 18,60090 14 501010881 Figrres,Dl Bend 45 Deg,8' 4 EA $ 20090 $ 80090 $ 19290 $ 76890 $ 65090 $ 2,60090 $ 29155 $ 1,18820 $ 14500 $ 58090 15 501010881 Figrres,Dl Sleeve,8' 1 EA $ 17500 $ 17590 $ 19890 $ 19890 $ 65090 $ 65090 $ 484 95 $ 48495 $ 15090 $ 15090 16 501010881 Figrres,Mega lug,6" 10 EA $ 10090 $ 1,00090 $ 11390 $ 1,13090 $ 8500 $ 85090 $ 5790 $ 57090 $ 7500 $ 75090 Sub Total $ 332590 Sub Total $ 2,Wil 90 Sub Total $ 830090 Sub Total $ 4,399.15 Sub Total $ 2098090 Division 6010-strucW res for sanitary and Storm sewers 17 6010108-A0 Manhole Type,PC,48"SW301 40.17 VF $ 48090 $ 19,281 60 $ 80890 $ 32,37792 $ 85090 $ 34,144 50 $ 1,63790 $ 65 758 29 $ 90090 $ 38,15390 18 601O108IT0 Decade Manhole 2 EA $ 50090 $ 1,00090 $ 69590 $ 1,39090 $ 8,50090 $ 13,00090 $ 44365 $ 88730 $ 75090 $ 1,50090 Sub Total $ 2028190 Sub Total $ 33 767 02 Sub Total $ 47,14450 Sub Total $ 66 645 59 Sub Total $ 3795390 Division TWO-sidewalks,shared Use Paths,and Drivervays 19 7030108-A0 Removal N Sidewalk 36 SY $ 890 $ 28890 $ 990 $ 32490 $ 3090 $ 1,08090 $ 1645 $ 59220 $ 1890 $ 64890 29 7030108E-0 Sltlewalk,PCC,5"(Thickness) 36 SY $ 6090 $ 2,16090 $ 7045 $ 2,53620 $ 7500 $ 2,70090 $ 10985 $ 3,95460 $ 11090 $ 3,96090 Sub Total $ 244890 Sub Total $ 2,86020 Sub Total $ 378090 Sub Total $ 4,54680 Sub Total $ 490890 Division TWO-Pavement Rehabilitation 21 7040108-A0 Full Depth Patches PCC 72 SY $ 7500 $ 5,40090 $ 70.15 $ 5,05080 $ 8500 $ 8,12090 $ 10170 $ 7,32240 $ 11500 $ 8,28090 22 7040108-A0 Full Depth Patches HMA 194 SY $ 5190 $ 9,89490 $ 5735 $ 11,12590 $ 5500 $ 10,67090 $ 7365 $ 14,288.10 $ 5090 $ 9,70090 23 70401081.1 Curb and Proton Decade and Replace 16 LF $ 4090 $ 64090 $ 5040 $ 80640 $ 5500 $ 88090 $ 9835 $ 1,57360 $ 6090 $ 96090 24 Temporary COltl Mix Asphalt Patch 72 SY $ 7500 $ 5,40090 $ 61.10 $ 4,39920 $ 4090 $ 2,88090 $ 84.10 $ 8,05520 $ 12500 $ 9,00090 Sub Total $ 2133490 Sub Total $ 21,38230 Sub Total $ 2055090 Sub Total $ 29,23930 Sub Total $ 2794090 Project Name: 2015 SCADA Flow Metering Stations Manhole Installation Project Bid Date Engineer's Estimate Connolly COnsfruCin In C. POrfzen COnsfrUCUOn Tschl fde Excavatio Miller Trucking&Excavatio ( 9 ) 1 9 Y 9 99 9 9 9 19-Nov-15 ESTIMATED NO.L INRNUMBER E BID REM DESCRIPTION qll TlTv UNIT UNIT PRICE TOTAL PRICE UNI BID BID TOTAL PRICE UNI BPRICE TOTAL PRICE UNI BID BID TOTAL PRICE UNI BPRICE TOTAL PRICE Division 8010-Traffic Signals&Lighting 25 8010-108-A.1 Handhole,PC,Rectangular 3 EA $ 650.00 $ 1,950.00 $ 375.00 $ 1,125.00 $ 425.00 $ 1,275.00 $ 349.90 $ 1,049.70 $ 925.00 $ 2,775.00 26 8010-108-A.2 Handhole,Composite,Medium 2 EA $ 200.00 $ 400.00 $ 445.00 $ 890.00 $ 425.00 $ 850.00 $ 389.90 $ 779.80 $ 475.00 $ 950.00 27 8010-108-B-1 Conduit,Trenched,PVC,2" 790 LF $ 7.00 $ 5,530.00 $ 3.00 $ 2,370.00 $ 3.00 $ 2,370.00 $ 3.45 $ 2,725.50 $ 2.50 $ 1,975.00 28 8010-108-B-1 Conduit,Trenchless,HDPE,2" 175 LF $ 6.00 $ 1,050.00 $ 5.55 $ 971.25 $ 4.50 $ 787.50 $ 3.25 $ 568.75 $ 4.75 $ 831.25 29 8010-108-B-1 Conduit,Trenched,PVC,4" 20 LF $ 9.00 $ 180.00 $ 30.65 $ 613.00 $ 29.00 $ 580.00 $ 28.80 $ 576.00 $ 11.75 $ 235.00 30 8010-108-D.2 Fiber Optic Hub Precast Concrete Base 3 EA $ 700.00 $ 2,100.00 $ 560.00 $ 1,680.00 $ 1,300.00 $ 3,900.00 $ 862.80 $ 2,588.40 $ 1,275.00 $ 3,825.00 31 8010-108-G-0 Connections to Handholes and Vaults 2 EA $ 80.00 $ 160.00 $ 270.00 $ 540.00 $ 275.00 $ 550.00 $ 366.20 $ 732.40 $ 475.00 $ 950.00 32 8010-108-H-0 Fiber Optic Hub Cabinet 3 EA $ 470.00 $ 1,410.00 $ 345.00 $ 1,035.00 $ 335.00 $ 1,005.00 $ 336.60 $ 1,009.80 $ 900.00 $ 2,700.00 33 8010-108-J-0 Electrical Service Control Pedestal-Direct Bury 3 EA $ 750.00 $ 2,250.00 $ 161.00 $ 483.00 $ 175.00 $ 525.00 $ 157.30 $ 471.90 $ 2,895.00 $ 8,685.00 Sub Total $ 15,030.00 Sub Total $ 9,707.25 Sub Total $ 11,842.50 Sub Total $ 10,502.25 Sub Total $ 22,926.25 IDOT Division 2528-Traffic Control 34 IDOT 2528.04-A Traffic Control Fulton School 1 LS $ 300.00 $ 300.00 $ 1,805.00 $ 1,805.00 $ 1,800.00 $ 1,800.00 $ 1,843.15 $ 1,843.15 $ 1,850.00 $ 1,850.00 35 IDOT 2528.04-A Traffic Control Phase 24th St 1 LS $ 500.00 $ 500.00 $ 2,685.00 $ 2,685.00 $ 2,600.00 $ 2,600.00 $ 2,730.95 $ 2,730.95 $ 2,750.00 $ 2,750.00 36 IDOT 2528.04-A Traffic Control Phase W.Locust St 1 LS $ 1,500.00 $ 1,500.00 $ 4,388.00 $ 4,388.00 $ 4,300.00 $ 4,300.00 $ 4,391.95 $ 4,391.95 $ 4,500.00 $ 4,500.00 37 IDOT 2528.04-A Traffic Control 1st St 1 LS $ 1,200.00 $ 1,200.00 $ 1,974.00 $ 1,974.00 $ 2,000.00 $ 2,000.00 $ 2,037.95 $ 2,037.95 $ 2,025.00 $ 2,025.00 Sub Total $ 3,500.00 Sub Total $ 10,852.00 Sub Total $ 10,700.00 Sub Total $ 11,004.00 Sub Total $ 11,125.00 Division 9010-Seeding 38 9010-108-A-0 Conventional-Seeding,Fertilizing,and Mulching,Type 1 145 SV $ 1.00 $ 145.00 $ 5.35 $ 775.75 $ 8.00 $ 1,160.00 $ 6.45 $ 935.25 $ 35.00 $ 5,075.00 Sub Total $ 145.00 Sub Total $ 775.75 Sub Total $ 1,160.00 Sub Total $ 935.25 Sub Total $ 5,075.00 Division 9060-Chain Link Fence 39 9060-108-D-0 Removal and Reinstallation of Existing Fence,Chainlink,8' 30 LF $ 25.00 $ 750.00 $ 37.00 $ 1,110.00 $ 40.00 $ 1,200.00 $ 0.05 $ 1.50 $ 58.00 $ 1,740.00 Sub Total $ 750.00 Sub Total $ 1,110.00 Sub Total $ 1,200.00 Sub Total $ 1.50 Sub Total $ 1,740.00 Total Est. $ 105,268.60 Total Bid $ 127,339.97 Total Bid $ 184,429.50 Total Bid $ 187,712.49 Total Bid $ 267,002.25 Over/Under(-) 20.97% 75.20% 78.32% 153.64%