Accepting the Fire Station #4 Driveway and Sidewalk Replacement Project Copyright 2014
City of Dubuque Consent Items # 6.
ITEM TITLE: Accepting the Fire Station#4 Driveway and Sidewalk
Replacement Project
SUMMARY: City Manager recommending acceptance of the
construction contract for the Fire Station#4 Driveway and
Sidewalk Replacement Project, as completed by Midwest
Concrete Inc.
RESOLUTION Accepting the Fire Station#4 Driveway and
Sidewalk Replacement Project and authorizing the payment
of the contract amount to the contractor
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
Fire Station#4 Driveway and Sidewalk Replacement City Manager Memo
Project-MVM Memo
Staff Memo Staff Memo
Resolution Resolutions
THE CITY OF Dubuque
UBE I
erica .i
Masterpiece on the Mississippi 2007-2012-2013
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Fire Station #4 Driveway and Sidewalk Replacement Project
DATE: December 28, 2015
City Engineer Gus Psihoyos is recommending acceptance of the construction contract
for the Fire Station #4 Driveway and Sidewalk Replacement Project, as completed by
Midwest Concrete Inc., in the final contract amount of $23,670.08, which was $7,037.98
over the contract award.
The driveway was replaced at the same elevation as existed, however with the L512
Rosenbauer, 102' articulating platform truck now at this station had difficulty exiting
without twisting the chassis. Therefore, the added construction costs were due to a
portion of the driveway, walk and approach being replaced and lowered to alleviate any
additional wear and stress on the equipment.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Mic ael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
'I'.FiE CITY OF Dubuque
DUB E Nl-AmedcaCRY
Masterpiece on the Mississippi MY ,2012.2013
TO: Michael Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
SUBJECT: Fire Station #4 Driveway and Sidewalk Replacement Project
DATE: December 28, 2015
INTRODUCTION
This memo provides for the acceptance of the construction contract for the Fire Station
#4, 1697 University, driveway replacement.
BACKGROUND
The project included the replacement and widening of the driveway, approach and
defective public sidewalk along Atlantic, University and N. Grandview.
DISCUSSION
Midwest Concrete Inc. completed the replacements for a final contract amount of
$23,670.08 and authorize final payment to the contractor. The driveway was replaced
at same elevation as existed, however with the L512 Rosenbauer, 102' articulating
platform truck now at this station, the equipment had difficulty exiting without twisting of
the chassis. Therefore, the added construction cost were due to a portion of the
driveway, walk and approach being replaced and lowered to alleviate any additional
wear and stress on the equipment.
RECOMMENDATION
I recommend that the city accept the public improvements, establish the final project
contract amount in the amount of$23,670.08 and authorize final payment to the
contractor.
BUDGETIMPACT
The project cost summary for the Fire Station #4 driveway replacement is as follows:
Award Final
Construction Contract $ 16,632.10 $ 23,670.08
Admin, Design, Construction Engineering & Inspection 2,569.48 3,550.51
Total Project Cost $19,201.58 $ 0.59
The project funding summary is as follows:
CIP No. Fund_Description Fund Amount
1021444 Driveway Replacement 20,200.00
3001041 City Catch Basin & Curbing 7,020.59
Total Project Funding $27,220.59
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution to accept the
improvements and to authorize the payment of the contract amount of$23,670.08 to
Midwest Concrete Inc. for the Fire Station #4 Driveway Replacement Project.
cc: Rick Steines, Fire Chief
Jon Dienst, P.E. Civil Engineer
Tom Ludescher, Fire Dept.
Jane Smith, EAII
FAJANE SMITH\PROJECTS\Fire House#4 University at N Grandview
2
RESOLUTION NO. 2-16
ACCEPTING THE FIRE STATION #4 DRIVEWAY AND SIDEWALK REPLACEMENT
PROJECT AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO
THE CONTRACTOR
Whereas, the Public Improvement Contract for the Fire Station #4 Driveway and
Sidewalk Replacement Project (the Project) has been completed and the City Engineer
has examined the work and filed a certificate stating that the Project has been
completed according to the terms of the Public Improvement Contract and that the City
Engineer recommends that the Project be accepted; and
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor from
the Driveway Replacements and City Catch Basin & Curbing appropriations for the
contract amount of $23,670.08, Tess any retained percentage provided for therein as
provided in Iowa Code chapter 573, and to pay such retainage only in accordance with
the provisions of Iowa Code chapter 573.
Passed, approved and adopted this 4th day of January, 2016.
Attest:
KevirFirristahl,(CM"C, City Clerk
Roy D. Buol, Mayor
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE FIRE STATION
#4 DRIVEWAY AND SIDEWALK REPLACEMENT PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the the Fire Station #4 Driveway and Sidewalk Replacement Project,
that the Project has been performed in compliance with the terms of the Public
Improvement Contract,/g. and that the total cost of the completed work is $27,220.59.