Loading...
3 4 Wk Sess Conf & Educ Ctr HOKMEMORANDUM February 28, 2002 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: March 4 Work Session Attached is the latest information provided by HOK Venue, the consultants designing the Mississippi River National Education and Conference Center. Included in this information is revised elevation drawings, floor level plans, revised schedule and cost estimates. As indicated on the cost estimate summary sheet, the project is at 90% design development and shows a base bid for construction of 26,896,200 or -0.06% less than City resources without our contingency. This means the project is currently $15,000 under budget, The City has a construction contingency for this project of $1,376,042, and there is a design contingency of $1 million. Included in this base bid is the construction of the River Room, which was previously identified as an alternate. Also included is an additional cost of a structural slab foundation due to the poor soil conditions found on site. The cost summary also identifies the list of add alternates in order of priority. As previously mentioned, this project is expected to be complete by November 2003. To meet this schedule the project must be broken into two bidding phases. The first phase would occur in April 2002 and would include site improvements and deep foundations. The second bid package would occur in July 2002 for all other construction. In order to meet this schedule we need to reach consensus on the design so that HOK Venue may proceed to the construction document phase of the project. I respectfully request Mayor and City Council approval of the design for the Mississippi River National Education and Conference Center. MCVM/cs Attachment cc: Barry Lindahl, Corporation Counsel Cindy Steinhauser, Assistant City Manager Pauline Joyce, Administrative Services Manager Design committee MEMORANDUM February 28, 2002 TO: FROM: SUBJECT: Michael C. Van Milligen, City Manager Mississippi River National Education and Conference Center Worksession Introduction The purpose of this memorandum is to provide information on the design of the Mississippi River National Education and Conference Center for the March 4 City Council worksession. Background Since August 2001, city staff began to work with a consultant team to develop a design for the new conference and education center. This Center is part of the City's commitment to the Vision Iowa funding for the America's River project and the City's Development Agreement with Platinum Hospitality. This process included the workgroup called for in the Platinum Hospitality Development Agreement, which includes: - Jerry Enzler, Dubuque County Historical Society - Sue Czeshinski, Convention and Visitor's Bureau, Dubuque Area Chamber of Commerce - Jim Rix, Platinum Hospitality Group - Rick Dickinson, Greater Dubuque Development Corporation - Bill Baum, Economic Development Director - Laura Carstens, Planning Services Manager - Pauline Joyce, Administrative Services Manager - Cindy Steinhauser, Assistant City Manager (Facilitator) In addition, the following participated in the design process: - David Hockenberry, Platinum Hospitality - Rich Russell, Building Services - Pam Myhre, Economic Development - Mike Koch, Public Works This process has included design charrettes, regularly scheduled workgroup meetings, presentation to Port of Dubuque property owner meetings as well as two worksessions with City Council held on November 5 and December 17. This process has also included a two-day value engineering session that included representatives from HOK Venue and their sub-consultants as well as project manager for the City, Jim Kolf and field inspector for the City, Bill Schmelling, both of the Durrant Group and their cost estimators. Discussion Attached are the latest elevation drawings, floor level plans and cost estimations for the Center. This information reflects changes to the design to create a more efficient facility from a construction and management perspective. Some of the changes includes: - Reducing the exhibit hall span from 180' to 150' while retaining the 30,000 square foot exhibit space; - Reconfiguration of"back of house" services such as kitchen, mechanical/electrical room and storage areas; - Factory primed trusses for exhibit hall in lieu of a second finish to the exhibit hall ceiling; - Use of decorative metal mesh panels for railing around river room; - Include operational wall for exhibit hall as a bid alternate - Use of colored concrete on plaza adjacent to riverwalk versus concrete tile; - Minor reduction of plaza adjacent to riverwalk to provide natural slope versus retaining walls; - Include fountain, enhanced landscaping and hardscape as bid alternates; - Include Dubuque plaza on west entrance as a bid alternate; - Modification of spine height and width to improve proportion to building; and Modification of prefunction space adjacent to meeting rooms. The use of native limestone, glass and metal in the design are meant to emulate the bluffs of Dubuque and the reflective nature of the river. This design retains important elements such as the 30,000 square foot exhibit hall with carpet, 12,000 square foot ballroom, 12,000 square foot of meeting space as well as plenty of prefunction space and exterior plaza space to provide for informal gatherings as well as social functions. These spaces are accessible via an elevator, escalator and stairs. This design also retains the signature architectural element of the facility, the glass spine, which peaks to a height of 59' at its easternmost point (73' from ground level) and provides panoramic views of the Mississippi as well as views of the bluffs of Dubuque and the gold dome of the courthouse. Also shown of the elevations are outdoor "party" plazas on the east and west elevations, a covered drop-off area for vehicles, 365 surface and underground parking stalls as well as a connection to the Hotel Waterpark. Currently the project is near completion of design development. As indicated on the attached budget information, revised estimates show the base bid at $26,896,200 or 0.06% underthe City's budget without our contingency of $1,376,042. Included in this base bid is the additional cost of a structural slab foundation under the exhibit hall due to the soil conditions as well as a $1,000,000 design/bid contingency as recommended by HOK Venue and project manager Jim Kolf. The chart below provides information on the various stages of cost estimation and the design/bid contingency allocated to each phase. It is important to note that schematic design is the first phase and costs associated with the eady designs are preliminary. As the project moves from schematic design to design development the costs provide a truer reflection of actual costs and thus the contingency becomes reduced. Date Estimate Contingency 9/30/01 $33,989,000 $2,971,073 10/24/01 $26,946,994 $2,355,506 12/13/01 $27,397,290 $1,970,319 02/07/02 $29,386,436 $1,358,596 02/27/02 $26,896,200 $1,000,000 Phase 20% schematic development 50% schematic development 50% design development 80% design development 90% design development Prior to the bidding process, we will continue to have discussions with HOK Venue and Jim Kolf on incorporating a contractor completion incentive similar to those included in the contracts for Town Clock Plaza and the Fengler Street bridge. Also attached is a revised construction schedule as provided by Jim Kolf. You will recall from previous correspondence that this project will be broken into two bidding phases. The first bid package, scheduled for April 2002, will be for site improvements and a foundation package. The second bid package will be for all other construction and will be bid in July 2002 with a completion date of late November 2003. Action, The requested action is to provide this information to City Council and to request their acceptance of the design in order to proceed to the construction document and bidding phase. Cc: Barry Lindahl, Corporation CoUnsel Pauline Joyce, Administrative Services Manager Design committee Conference and Education Center Cost Summary 90% Design Development Base Project Cost Estimate including River Room* City resoumes without contingency** Difference Pementage under budget *includes $1 million design/bid contingency which accounts for $800,000 variation in HOK cost estimation and CCS cost estimation **includes $900,000 estimated sales tax refund. Does not include $1,376,042 City contingency $26,896,200 $26,911,950 -0.06% Add Alternates in order of priority: Centralized HVAC controls Operation Wall for Exhibit Hall Fountain Enhanced landscape at west entrance Dubuque Plaza at west entrance Hardscape (concrete and bdck pavers at west entrance) Additional enclosed prefunction space $ $ $ $ $ $ $ 60,000 230,000 160,000 100,000 68,000 182,000 644,540 America's River Project City of Dubuque - Public Work Projects Education & Conference Center 104.2 wks Design - HOK Sports 31 wks Bidding & Award 19 wks Construction 75 wks Closeout 4 wks Durrant 20o3 Project Schedule 2/28/02 I of 1 ~m~ m ~c3 ~3 0 0 /2 h~ h~ 0 Z I'll m o 0 Dubuque Riverfront Education and Conference Center 0 m 0 o "~ 0 Dubuque Riveffront Education and Conference Center e ucation and conference cen` ubuque nucriront Educat.Dn 8'Comfer ncc Confer fDubu e -verha t E., ^.,ion o(rr.: a ce Certer dubf' r A d- Cer.0 r bu Cer! r lubuque nvertront down & Coaro erdifffi Cer pubuque rtvertront Ldcca1on & Co7a rence ;DGertcr ubuaue rtvertront Edmonton Cnce Center Dubuque nvertront Education & nver(ronl Educonlon'$.:C nier,,.`,'wt' �ur,ue r,vcrfront,aducal+are& Co.1*:oee'"n1'2r ubr tIIyBrtront rAtt?eAtion e. C ra �g • e 'ter nt tlticatror� S'n DUBUQUE RIVER FRONT EDUCATION & CONFERENCE CENTER DESIGN IN PROGRESS 02.25.02 BUILDING FORM DESIGN ALTERNATE 2 WITH REDUCED FLOOR AREA DUBUQUE RIVER FRONT EDUCATION & CONFERENCE CENTER DL I(i .V' PROGR!. 02.25.02 MGM (2) Aerial Concept SITE OVERVIEW DESIGN ALTERNATE 2 REDUCED FLOOR AREA DUBUQUE RIVER FRONT EDUCATION & CONFERENCE CENTER PR()GRL.c: 02.25.02 (3) Aerial of Site D UBU UE RIVER FRONT EDUCATION & CONFERENCE CENTER Ma DESIGN IN t PQG Et 02 2'_O2 SPORT t ENIE*EVENT (4) East Elevation DUBUQUE RIVER FRONT EDUCATION & CONFERENCE CENTER in::c...AG.\\ IN PROGRESS 0225D2 SPORT +VE NUE-frEWENT (5) East Elevation DUBUQUE RIVER FRONT EDUCATION & CONFERENCE CENTER DESIGN IN PROGRESS 02_25_02 SPORTtVENtiEtEYENT (6) East Elevation DUBUQUE RIVER FRONT EDUCATION & CONFERENCE CENTER DESIGN IN PROGRESS 02.25.02 5PORT*VF (7) Southeast Elevation DUBUQUE RIVER FRONT EDUCATION & CONFERENCE CENTER DESIGN IN PROGRESS 02 25 02 SPORT+VENIFE*EvENT (8) East Elevation DUBUQUE RI R _r.RQNT EDUCATION & CON FERE _e-,-.4 [_,/' I jam`' ��'''T1 �...... 1,.! 1......i 4'ry _[ . 1 ]\ 1 N P R O +�J R 'I L ` SPORT fVEhaLE.U.0102.25.02 (8a) East Elevation Za. SPORT+VENUE*EVENT DUBUQUE RIVER FRONT EDUCATION & CONFERENCE CENTER DESIGN INT PROGRESS 02 25 02 (9) River Room ,__+_==_ su nal AO CLEM Man n ®LEVEL 1 FLOOR PLAN VENUE Q.sa� Yam's Wig wwn..r� arlir.rs ims.oarrw frawarromaimos 11..14r1..isr.. nrrrr 0i4^ rrrrara n+w1� nwamuac^+LNC rG r..l11.1.1.1•nYllrftli 1.ti1.mh1 1•rrrara 11111.NIBID mom» rsarrvror• c,tiaml wr.or. rtiaa VALUE ENGINEERING RESOLUTION FEBRUARY 25, 2002 ra.a =NMI IC MORO .x LEVEL 1 RELLRESCE PLAN Ow* NOLlpn (10) First Level Floor Plan f _4. ,1 ukto I� r SI> Tit - 10 .YiFi Qa • ®LEVEL 2 FLOOR PLAN A. 1 VENUE PROJECT NORTH arrrcra SamOslimmisS .msl uiun..o.mw Um. mil.miwypillay ..r[rr AMBOMMMMOZ .�.rrrra .3MIMULJOIM SIMOMM 1ymylrw.w..r. vm.r+.rr.e w.umaseoMMU MbUsia .rrstw VALUE ENGINEERING RESOLUTION FEBRUARY 25. 2002 MUM DEMml NSUSIOINt IMMISLA MMU 111100,R LEVEL REFERENCE PLAN Al-2 (11) Second Level Floor Plan O ® O G® 000 00 O OK r � \ A7-1-11 ..' CUM \K\A \ J1x 7 ti -vr— • T t'. { L• ,N I NO VOA lY I I ' '1-mmm , 1 I • 0111001 CICLIK OLEVEL 3 FLOOR PLAN 0 VENUE v) PROJECT NORTH Irma,rreati� ali.rrra rgvrr fTPUR1D.VoiraP3 � �iri rr amokrsat 1M1RYY� arrsmni. r >•r�irra oy.,rs A�.� iEL � r..wtirrus sras� w•Ururuw.mu1 urr.Or.o amrlir,r4ar4/ rra� VALUE ENGINEERING RESOLUTION FEBRUARY 25, 2002 mum ti•Q111). MOM MUD It MIA /MI LEVEL 3 REF RE4(E PLAN Al-3 n (12) Third Level Flnor Plan