Pavement Marking Project Phase II Acceptance Copyright 2014
City of Dubuque Consent Items # 18.
ITEM TITLE: Pavement Marking Project Phase II Acceptance
SUMMARY: City Manager recommending acceptance of the public
improvement construction contract for the 2015 Pavement
Marking Project Phase II, as completed by SELCO, Inc.
RESOLUTION Accepting the 2015 Pavement Marking
Project Phase I I and authorizing the payment to the
contractor
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
2015 Payment Marking Project Phase I I-MVM Memo City Manager Memo
Staff Memo Staff Memo
Resolution Resolutions
THE CITY OF Dubuque
UBE I
erica .i
Masterpiece on the Mississippi 2007-2012-2013
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: 2015 Pavement Marking Project Phase II
DATE: February 25, 2016
City Engineer Gus Psihoyos is recommending acceptance of the public improvement
construction contract for the 2015 Pavement Marking Project Phase II, as completed by
SELCO, Inc., in the final contract amount of $9,161.79, which is a decrease from the
original contract of $19,495.95 due to the fact that SELCO was unable to complete all
the markings before the cold weather set in.
I concur with the recommendation and respectfully request Mayor and City Council
approval.
Micliael C. Van Milligen
MCVM:jh
Attachment
cc: Barry Lindahl, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
que
THF C: OF Lr'` DUb=DU�j- B 1111111
Masterpiece o-n the Mississippi 200"•2012.2011
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer ` s.
SUBJECT: 2015 Pavement Marking Project Phase II
DATE: February 24, 2016
INTRODUCTION
The enclosed resolution provides for the acceptance of the public improvement
construction contract for the 2015 Pavement Marking Project Phase 11.
BACKGROUND
The project provided for painting of symbols and legends on City owned streets.
DISCUSSION
The 2015 Pavement Marking Project was completed by SELCO, Inc. of Dubuque, Iowa
in the final contract amount of$9,161.79 which is a decrease from the original contract
amount of$19,495.95. The decrease was due to the fact that SELCO was unable to
complete all the markings before the cold weather set in.
BUDGET IMPACT
The project was funded from the Pavement Marking CIP 3002245. The cost summary
for the 2015 Pavement Marking Project Phase II is:
Award Final
Construction Contract $19,495.95 $9,161.79
Total Project Cost $19,495.95ILI61 7
The project funding summary is as follows:
CIP No. Fund Description Fund Amount
3002245 Pavement Marking $9,161.79
Total Project Funding IaJ61.79
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution to accept the
improvements and to authorize the payment of the contract amount of$9,161.79 to
SELCO, Inc. for the 2015 Pavement Marking Project Phase II.
GNP/kb
cc: Bob Schiesl, Assistant City Engineer
Troy Kress, Engineering Technician
RESOLUTION NO. 61-16
ACCEPTING THE 2015 PAVEMENT MARKING PROJECT PHASE II AND
AUTHORIZING THE PAYMENT TO THE CONTRACTOR
WHEREAS, the public improvement contract for the 2015 Pavement Marking Project
Phase II (the Project) has been completed by the Contractor, SELCO, Inc. (Contractor),
the City Engineer has examined the work and recommends that the Project be
accepted; and
WHEREAS, the final contract amount for the Project is $9,161.79;
WHEREAS, the Contractor has previously been paid $8,703.70, leaving a balance of
$458.09; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project is
hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $458.09 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa
Code chapter 26.13.
Passed, approved and adopted this 7th day of March, 2016.
Attest:
tifMrAr
Kevin irnstahl, CMC 'ity Clerk
GQ,
Roy D. juol, Mayor
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE 2015
PAVEMENT MARKING PROJECT PHASE II
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the 2015 Pavement Marking Project Phase II, and that said Project
has been performed in compliance with the terms of the Public Improvement Contract,
and that the total cost of the completed work is $9,161.79.
Dated this day of J 2016.
Filed in the office of the City Clerk on the
Gus Psihoyos, City Engin er
day of
, 2016.
Kevi6 Firnsta
C, City Clerk