2015 Sewershed 7 & 20 Manhole Replacement Project Acceptance Copyright 2014 City of Dubuque Consent Items # 13. ITEM TITLE: 2015 Sewershed 7 & 20 Manhole Replacement Project Acceptance SUMMARY: City Manager recommending acceptance of the public improvement construction contract for the 2015 Sewershed 7 & 20 Manhole Replacement Project, as completed by Top Grade Excavating, Inc. RESOLUTION Accepting the 2015 Sewershed 7 & 20 Manhole Replacement Project and authorizing the payment to the contractor SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt Resolution(s) ATTACHMENTS: Description Type Sewershed 7 &20 Manhole Replacement Project-MVM City Manager Memo Memo Staff Memo Staff Memo Engineers Certificate of Completion Supporting Documentation Resolution Resolutions THE CITY OF Dubuque UBE I erica .i Masterpiece on the Mississippi 2007-2012-2013 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: 2015 Sewershed 7 & 20 Manhole Replacement Project CI P 7101335 DATE: June 29, 2016 City Engineer Gus Psihoyos is recommending acceptance of the public improvement construction contract for the 2015 Sewershed 7 & 20 Manhole Replacement Project, as completed by Top Grade Excavating, Inc., in the final contract amount of$150,096.07, which is an 11.6% decrease from the original contract amount of$167,468.00. 1 concur with the recommendation and respectfully request Mayor and City Council approval. Mic ael C. Van Milligen MCVM:jh Attachment cc: Barry Lindahl, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Gus Psihoyos, City Engineer THE CITY OF � Du buqLte DUBUE il.AmedcaCity 1111.1 Masterpiece ori the Mississippi -10„"..2,,,2 ,2013 TO: Michael C. Van Milligen, City Manager FROM: Gus Psihoyos, City Engineer SUBJECT: 2015 Sewershed 7 & 20 Manhole Replacement Project CIP 7101335 DATE: June 23, 2016 INTRODUCTION The enclosed resolution provides for the acceptance of the public improvement construction contract for the 2015 Sewershed 7 & 20 Manhole Replacement Project. BACKGROUND The City of Dubuque, Iowa has entered into a Consent Decree in the case of The United States of America, and the State of Iowa v. The City of Dubuque, Iowa, Civil Action No. Case 2:11-cv-01011-EMJ, Civil Action Number 2008V00041, DOJ Case Number 90-5-1-1-09339, United States District Court for the Northern District of Iowa. The provisions of the Consent Decree apply to and are binding upon the City and its officers, directors, employees, agents, servants, successors, assigns, and all persons, firms and corporations under contract with the City to perform the obligations of the Consent Decree. The City is actively rehabilitating brick manholes and sanitary sewer pipes that were identified in the plan to be deficient. DISCUSSION The 2015 Sewershed 7 & 20 Manhole Replacement Project was completed by Top Grade Excavating, Inc., of Farley, Iowa, in the final contract amount of $150,096.07 which is an 11.6% decrease from the original contract amount of$167,468.00. The project involved the replacement of 14 sanitary sewer manholes and the elimination of 2 sewer manholes at different locations within Sewershed 7. Portions of some water mains were relocated as part of this project due to the replacement of the manholes. RECOMMENDATION I recommend that the City Council accept the improvements and authorize the payment of the contract amount of $150,096.07 to Top Grade Excavating, Inc., for the 2015 Sewershed 7 & 10 Manhole Replacement Project. BUDGET IMPACT The project cost summary for the 2015 Sewershed 7 & 20 Manhole Replacement Project is as follows: Award Final Construction Contract $167,468.00 $ 150,096.07 Contingency 16,746.80 0.00 Admin, Design, Construction Engineering & Inspection 27,632.22 7,504.80 Total Project Cost $ 211.847.02 L 1571600.87 The project funding summary is as follows: CIP No. Fund Description Fund Amount 7101335 Sanitary Sewer Manhole Replacement $ 45,259.67 7202332 Stormwater I & I Elimination Project 112,341.20 Total Funding Available $ 157.600.87 REQUESTED ACTION The City Council is requested to adopt the attached resolution to accept the improvements and to authorize the payment of the contract amount of $150,096.07 to Top Grade Excavating, Inc., for the 2015 Sewershed 7 & 20 Manhole Replacement Project. cc: Jenny Larson, Budget Director Denise Ihrig, P.E. Deron Muehring, Civil Engineer II Charlie Gau, Engineering Tech 2 RESOLUTION NO. 258-16 ACCEPTING THE 2015 SEWERSHED 7 & 20 MANHOLE REPLACEMENT PROJECT AND AUTHORIZING THE PAYMENT TO THE CONTRACTOR WHEREAS, the public improvement contract for the 2015 Sewershed 7 & 20 Manhole Replacement Project (the Project) has been completed by the Contractor, Top Grade Excavating, Inc. (Contractor), the City Engineer has examined the work and recommends that the Project be accepted; and WHEREAS, the final contract amount for the Project is $150,096.07; WHEREAS, the Contractor has previously been paid $142,591.27, leaving a balance of $7,504.80; and WHEREAS, the City Council finds that the recommendation of the City Engineer should be accepted. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor the balance of the retainage of $7,504.80 as provided in Iowa Code chapter 573, and to pay such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa Code chapter 26.13. Passed, approved and adopted this 5th day of July, 2016. Roy D.,& ol, Mayor Attest: Kevin t. Firnstahl,`Qivv City Clerk CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE 2015 SEWERSHED 7 & 20 MANHOLE REPLACEMENT PROJECT The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the 2015 Sewershed 7 & 20 Manhole Replacement Project, and that said Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $157,600.87. Dated this "�Aday of JOvg , 2016. a Gus Psihoyos, City Engirt er fi Filed in the office of the City Clerk on th day of 201,x. � i Ke n S. Firnstahl, WC, City Clerk 7 I� i i a