Timber-Hyrst Estates #4 North and South Line Creek Crossing Project Acceptance Copyright 2014
City of Dubuque Consent Items # 14.
ITEM TITLE: Timber-Hyrst Estates #4 North and South Line Creek
Crossing Project Acceptance
SUMMARY: City Manager recommending acceptance of the
construction contract for the Timber-Hyrst Estates #4
Sanitary Sewer North and South Line Creek Crossings
Project, as completed by Gansen Excavating, Inc.
RESOLUTION Accepting the Timber-Hyrst Estates #4
North and South Line Creek Crossings Project and
authorizing the payment to the contractor
SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt
Resolution(s)
ATTACHMENTS:
Description Type
Timber-Hyrst Estates#4 North and South Line Creek City Manager Memo
Crossings-MVM Memo
Staff Memo Staff Memo
Acceptance Resolution Resolutions
Engineer's Certificate of Completion Supporting Documentation
THE CITY OF Dubuque
DUB E i"
Masterpiece on the Mississippi 2007.2012.2013
TO: The Honorable Mayor and City Council Members
FROM: Michael C. Van Milligen, City Manager
SUBJECT: Timber-Hyrst Estates #4 North and South Line Creek Crossings
DATE: November 28, 2016
City Engineer Gus Psihoyos is recommending acceptance of the construction contract
for the Timber-Hyrst Estates #4 Sanitary Sewer North and South Line Creek Crossings
Project, as completed by Gansen Excavating, Inc., in the final contract amount of
$143,383.39.
1 concur with the recommendation and respectfully request Mayor and City Council
approval.
v
Mic ael C. Van Milligen
MCVM:jh
Attachment
cc: Crenna Brumwell, City Attorney
Cindy Steinhauser, Assistant City Manager
Teri Goodmann, Assistant City Manager
Gus Psihoyos, City Engineer
THE CDubuque
DUUB--*'-- TE NI-Am�edcaCianl
11111.1
Masterpiece on the Mississippi 2107•2012-2013
TO: Michael C. Van Milligen, City Manager
FROM: Gus Psihoyos, City Engineer
DATE: November 23, 2016
SUBJECT: Timber-Hyrst Estates#4 North and South Line Creek Crossings
INTRODUCTION
The enclosed resolution provides for the acceptance of the construction contract for the
Timber-Hyrst Estates#4 Sanitary Sewer North and South Line Creek Crossings Project
BACKGROUND
The Timber-Hyrst Estates#4 Sanitary Sewer North and South Line Creek Crossings
Project included the installation of inverted siphons which cross beneath the South Fork
Catfish Creek at two locations. The siphons connected an 18" interceptor sewer to the
Timber-Hyrst Estates phase #4 sanitary sewer lines.
DISCUSSION
Timber-Hyrst Estates #4 North and South Line Creek Crossings Project was completed
by Gansen Excavating, Inc., of Dubuque, Iowa in the final contract amount of
$143,383.39.
RECOMMENDATION
I recommend that the City Council accept the improvements and authorize the payment of
the contract amount of $143,383.39 to Gansen Excavating, Inc., for the Timber Hyrst
Estates #4 North and South Line Creek Crossings Project.
BUDGET IMPACT
The summary of project cost for the Timber-Hyrst Estates #4 Sanitary Sewer North and
South Line Creek Crossings Project is summarized as follows:
Award Final
Construction Contract $139,457.00 $143,383.39
Contingency 13,221.00 0.00
Construction Engineering & Inspection 21,814.65 10,031.50
Easement and Tree Acquisition 26,643.65 26.643.65
Total Project Cost $201,136.30 $180,058.54
The project funding summary is as follows:
Fund
CIP No. Fund Description Amount
7101350 Sewer Extensions New Development $ 180,058.54
ACTION TO BE TAKEN
The City Council is requested to adopt the attached resolution accepting the
improvements, and establishing the final contract amount of$143,383.39, and for the
payment of the contract amount to Gansen Excavating, Inc. for the Timber-Hyrst Estates
#4 Sanitary Sewer North and South Line Creek Crossings Project.
Prepared by: Todd Irwin
cc: Jenny Larson, Budget Director
Alexis Steger, Senior Budget Analyst
Denise Ihrig, Water Department Manager
John Klosterman, Public Works Director
2
RESOLUTION NO. 409-16
ACCEPTING THE TIMBER-HYRST ESTATES #4 NORTH AND SOUTH LINE CREEK
CROSSINGS PROJECT AND AUTHORIZING THE PAYMENT TO THE
CONTRACTOR
WHEREAS, the public improvement contract for the Timber-Hyrst Estates #4
North and South Line Creek Crossings Project (the Project) has been completed by the
Contractor, Connolly Construction, Inc. (Contractor), the City Engineer has examined
the work and recommends that the Project be accepted; and
WHEREAS, the final contract amount for the Project is $143,383.39;
WHEREAS, the Contractor has previously been paid $136,214.22, leaving a
balance of $7,169.17; and
WHEREAS, the City Council finds that the recommendation of the City Engineer
should be accepted.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
DUBUQUE, IOWA:
Section 1. The recommendation of the City Engineer is approved and the Project
is hereby accepted.
Section 2. The Finance Director is hereby directed to pay to the Contractor the
balance of the retainage of $7,169.17 as provided in Iowa Code chapter 573, and to pay
such retainage in accordance with the provisions of Iowa Code chapter 573 or Iowa
Code chapter 26.13.
Passed, approved and adopted this 5th day of December, ?D16.
Roy D. B, Mayor
Attest:
Kevin' Firnstahl, C City Clerk
CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE TIMBER-
HYRST ESTATES #4 NORTH AND SOUTH LINE CREEK CROSSINGS PROJECT
The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that
he has inspected the Timber Hyrst Estates #4 Sanitary Sewer South Line Project, and
that said Project has been performed in compliance with the terms of the Public
Improvement Contract, and that the total cost of the completed work is $180,058.54.
i
Dated this day of Ale , 2016.
Gus Psihoyos, City Engin er