Loading...
Acceptance of 2016 Asphalt Overlay Access Ramp Project Two Copyright 2014 City of Dubuque Consent Items # 24. ITEM TITLE: Acceptance of 2016 Asphalt Overlay Access Ramp Project Two SUMMARY: City Manager recommending acceptance of the construction contract for the 2016 Asphalt Overlay Access Ramp Project Two as completed by Midwest Concrete. RESOLUTION Accepting the 2016 Asphalt Overlay Access Ramps Project Two and authorizing the payment of the contract amount to the contractor SUGGESTED DISPOSITION: Suggested Disposition: Receive and File; Adopt Resolution(s) ATTACHMENTS: Description Type 2016 Asphalt Overlay Access Ramp Project Two-MVM City Manager Memo Memo Staff Memo Staff Memo Acceptance Resolution Resolutions Engineer's Cert Supporting Documentation THE CITY OF Dubuque DUB E i" Masterpiece on the Mississippi 2007.2012.2013 TO: The Honorable Mayor and City Council Members FROM: Michael C. Van Milligen, City Manager SUBJECT: 2016 Asphalt Overlay Access Ramp Project Two (CIP 3001227) DATE: December 12, 2016 City Engineer Gus Psihoyos is recommending acceptance of the construction contract for the 2016 Asphalt Overlay Access Ramp Project Two, as completed by Midwest Concrete, in the final contract amount of $93,898.90, which is 19.3% over the contract amount of$78,696.00. The cost increase was caused by the following additional work: • Additional defective curb and gutter replacement, • Removal and relocation of two pedestrian ramps to create a safer crossing, • Two intake adjustments, • An additional pedestrian ramp installation, and • Soil stabilization and rock. I concur with the recommendation and respectfully request Mayor and City Council approval. ZIA-i k�4 6&-zn' Mic ael C. Van Milligen MCVM:jh Attachment cc: Crenna Brumwell, City Attorney Cindy Steinhauser, Assistant City Manager Teri Goodmann, Assistant City Manager Gus Psihoyos, City Engineer 'rHE crrYOF - D buqUe DUB E F�ACRY 11111.1 Masterpiece on the Mississippi 2007.2012.2013 TO: Michael C. VanMilligen, City Manager FROM: Gus Psihoyos, City Engineer SUBJECT: 2016 Asphalt Overlay Access Ramp Project Two (CIP 3001227) DATE: December 19, 2016 INTRODUCTION The enclosed resolutions provide for the acceptance of the construction contract for the 2016 Asphalt Overlay Access Ramp Project Two. BACKGROUND The project replaced twenty six non-compliant pedestrian access ramps with thirty four directional pedestrian access ramps as per Public Right of Way Accessibilities Guidelines (PROWAG) specifications in conjunction with the Public Works Asphalt Overlay Program and involved the intersections of: • Pennsylvania Avenue and Lenox Street, southwest and southeast corners. • Pennsylvania Avenue and Illinois Avenue, southwest and southeast corners. • Pennsylvania Avenue and Enid Street, southeast corner. • Pennsylvania Avenue and Alpha Avenue, southwest and southeast corners. • Pennsylvania Avenue and Ohio Avenue, southwest and southeast corners removed and relocated. • Pennsylvania Avenue and Drexel Avenue, southwest and southeast corners. • Drexel Avenue and Illinois Avenue, northwest corner. • Illinois Avenue and Ohio Avenue, northeast and northwest corners. • Enid Street and Illinois Avenue, relocation at the northeast and new ramp at the northwest corner. • Key Way Drive and Southway, northwest and northeast corners. • Key Way Drive and Delmonaco Drive northwest and northeast corners. • Delmonaco Drive and Venture Court, southeast corner. • Delmonaco Drive and Dana Drive, southeast corner, double directional at the southwest corner and mid-block crossing on north side of Dana Drive. • Southway and Dana Drive, southeast and northeast corners. In accordance with Iowa Code § 384.103 and § 364.12(3)(c), and Iowa Code, Section 26.14, the City solicited informal bids for the 2016 Asphalt Overlay Access Ramp Project Two. The sole bid from Midwest Concrete Inc. was 5.83% over the Engineer's estimate of $74,361.00 Contractor Bid Results Midwest Concrete, Inc. $78,696.10 DISCUSSION The Asphalt Overlay Access Ramps Project Two was completed by Midwest Concrete Inc. of Peosta, Iowa in the final contract amount of$93,898.90, 19.3% over the contract amount of$78,696.00. Additional work was required including: • Additional defective curb and gutter replacement • Removal and relocation of two pedestrian ramps to create a safer crossing • Two intake adjustments • An additional pedestrian ramp installation • Soil stabilization and rock Not including the cost of the extra curb & gutter, the average cost per ramp was $3,185.34. BUDGET IMPACT The project cost summary for the 2016 Asphalt Overlay Access Ramp Project Two is as follows: Award Final Construction Contract $78,696.00 $93,898.90 Contingency $7,436.10 0.00 Construction Engineering & Inspection $12,269.57 $5,671.87 Total Project Cost94 066.67 $99,570,77 2 The funding summary for the project is as follows: CIP Fund Description Fund Amount 3001227 Curb Ramp Program $99,570.77 Total Project Funding 9$ 570.7 REQUESTED ACTION The City Council is requested to adopt the attached resolutions accepting the improvements and establish the final contract amount for the 2016 Asphalt Overlay Access Ramp Project Two in the amount of $93,898.91. Prepared By: Tom Kopp, Engineering Technician cc: John Klostermann, Public Works Director Jenny Larson, Budget Director Jon Dienst, Civil Engineer II 3 RESOLUTION NO. 425-16 ACCEPTING THE 2016 ASPHALT OVERLAY ACCESS RAMPS PROJECT TWO AND AUTHORIZING THE PAYMENT OF THE CONTRACT AMOUNT TO THE CONTRACTOR Whereas, the Public Improvement Contract for the 2016 Asphalt Overlay Access Ramps Project Two (the Project) has been completed and the City Engineer has examined the work and filed a certificate stating that the Project has been completed according to the terms of the Public Improvement Contract and that the City Engineer recommends that the Project be accepted; and NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF DUBUQUE, IOWA: Section 1. The recommendation of the City Engineer is approved and the Project is hereby accepted. Section 2. The Finance Director is hereby directed to pay to the Contractor from the Curb Ramp Program appropriations for the contract amount of $93,898.90 Tess any retained percentage provided for therein as provided in Iowa Code chapter 573, and to pay such retainage only in accordance with the provisions of Iowa Code chapter 573. Attest: Passed, approved and adopted this 19th day of December, 2016. (Kevin Firnsta Roy D. Buol, Mayor CITY ENGINEER'S CERTIFICATE OF FINAL COMPLETION OF THE 2016 ASPHALT OVERLAY ACCESS RAMPS PROJECT TWO The undersigned City Engineer of the City of Dubuque, Iowa, hereby certifies that he has inspected the 2016 Asphalt Overlay Access Ramps Project Two, that the Project has been performed in compliance with the terms of the Public Improvement Contract, and that the total cost of the completed work is $99,570.77. D ated this day of , 2016. Gus Psihoyos, City Engineer Filed in the office of the City Clerk on the day o -, 2016. n Firnst hl, CMC, City Clerk ( 1,